Fluidstack, a New York-based company that builds and runs AI data centers, makes modular data center equipment at a factory in two leased Luke Field buildings with Glendale, Arizona addresses. Fluidstack said on November 24, 2026 that the Glendale plant was up and running and will support 1,250 jobs. Maricopa County issued permits in September 2026 for production lines and fabrication lines in the two buildings Fluidstack leases. Fluidstack says its Arizona plant will supply Blackbird modules, Compute Modules and Electrical Skids for AI data centers.
Sources: Google Maps: Map of Maricopa County Assessor parcel 501-52-005S, Google Maps: Map of Maricopa County Assessor parcel 501-52-005Q, Fluidstack (PR Newswire), U.S. Securities and Exchange Commission · Addresses open Google Maps in a new tab
Modern AI runs on physical silicon, and that silicon passes through several hands before it ever answers a question. Here is the path, and where Fluidstack sits on it. Stages not marked below are shown for context and are not claims about Fluidstack.
Fluidstack says it builds AI data centers in the United States, "from the factory floor to the finished campus." Gary Wu and Jamie Cox, who met at Oxford, started Fluidstack in 2017, according to Forbes; César Maklary, the third co-founder, joined in 2020. Gary Wu is chief executive.
Headquarters and ownership: Fluidstack moved its global headquarters to Midtown Manhattan in New York City in December 2025. Fluidstack Ltd, a private company registered in England (Companies House no. 10985545), reports its private share sales to the SEC on Form D; the June 30, 2026 notice reported $729,999,546 sold of a $1.5 billion offering.
Funding: In July 2026 Fluidstack announced an $830 million Series A at a $7.5 billion valuation, led by Situational Awareness.
Anthropic: In November 2025 Anthropic announced a $50 billion investment "building data centers with Fluidstack in Texas and New York." Neither company's announcement names Arizona, and Fluidstack's November 2026 release about its Arizona plant does not mention Anthropic.
The factory: Fluidstack says its first manufacturing facility is "now up and running in Glendale, Arizona," in two Luke Field buildings totaling more than 1.1 million square feet, and that it converted the site "from an empty shell to an operating plant in six months." Fluidstack says the plant will support 1,250 permanent manufacturing and skilled trades jobs. Current openings are in the jobs section of this page.
The buildings: Luke Field's landlord, Lincoln Property Company, announced on June 24, 2026 that a company in the AI sector would lease Building A (695,750 sq ft) and Building B (454,761 sq ft), without naming it. KTAR and the Phoenix Business Journal identified the tenant as Fluidstack from a financing statement recorded with Maricopa County on June 5, 2026 (no. 20260339836), which names Fluidstack Int LLC and the property owner, Northern Parkway Owner LLC.
The two buildings are at:
County permits: The site has Glendale addresses but is in unincorporated Maricopa County, so its building permits are issued by the county, not the City of Glendale. The county issued the Building A permit for production lines on September 23, 2026, describing "a new tenant build-out for a new manufacturing facility," and the Building B permit for fabrication lines and distribution storage on September 14, 2026, for a plant that will make "fully integrated, transportable technology mezzanine modules."
A partial-occupancy permit issued September 16, 2026 covers a secured area for "initial employee operational training." On November 27, 2026 the production and fabrication permits showed as issued, not finaled, and the office build-outs for both buildings were still in review.
As of November 27, 2026, no Arizona Commerce Authority, City of Glendale or Maricopa County announcement or incentive for the plant has been published, and Fluidstack has not announced an Arizona data center. The plant makes data center equipment; it is not a data center.
On November 24, 2026 Fluidstack launched Blackbird, a modular 400 MW data center design it says can be built in six months, along with a Compute Module and an Electrical Skid. DCD reports all three are made at the Glendale plant.
A company target: Interesting Engineering noted that the six-month timeline "remains a company target" that actual deployments have yet to prove.
Other projects: DCD reports that Fluidstack began building a data center project in Wythe County, Virginia, in November 2026 and is developing or operating data centers in Indiana, Texas and New York.
Each figure is dated and linked to its source. Figures that are company-reported, announced, or projected rather than measured are labeled.
| Measure | Value | As of | Basis | Source |
|---|---|---|---|---|
| Address | 7911 N Litchfield Rd, Glendale, AZ 85307 | 2026-11-27 | verified | Google Maps |
| Building size | 695,750 sq ft | 2026-06-24 | company-reported From the company's own published information. | Lincoln Property Company |
| Production line build-out | Permit issued September 23, 2026 for production lines; described as "a new tenant build-out for a new manufacturing facility" | 2026-11-27 | verified | Maricopa County Planning and Development |
| Measure | Value | As of | Basis | Source |
|---|---|---|---|---|
| Address | 13543 W Northern Ave, Glendale, AZ 85307 | 2026-11-27 | verified | Google Maps |
| Building size | 454,761 sq ft | 2026-06-24 | company-reported From the company's own published information. | Lincoln Property Company |
| Fabrication line build-out | Permit issued September 14, 2026 for fabrication lines and distribution storage, to make "fully integrated, transportable technology mezzanine modules" | 2026-11-27 | verified | Maricopa County Planning and Development |
| Partial occupancy for training | Permit issued September 16, 2026 for a secured area for "initial employee operational training" | 2026-11-27 | verified | Maricopa County Planning and Development |
| Measure | Value | As of | Basis | Source |
|---|---|---|---|---|
| Permitting authority | Maricopa County (the site is in unincorporated Maricopa County; its addresses say Glendale) | 2026-11-27 | verified | Maricopa County Assessor |
| Shell to operating plant (company figure) | Six months | 2026-11-24 | company-reported From the company's own published information. | Fluidstack |
| Luke Field leases announced | June 2026 | 2026-06-24 | company-reported From the company's own published information. | Lincoln Property Company |
| Fluidstack says the plant is running | November 2026 | 2026-11-24 | company-reported From the company's own published information. | Fluidstack |
| Measure | Value | As of | Basis | Source |
|---|---|---|---|---|
| Series A funding (company announcement) | $830 million at a $7.5 billion valuation | 2026-07-20 | company-reported From the company's own published information. | Fluidstack |
| Private share sale reported to the SEC (June 2026) | $729,999,546 sold of a $1.5 billion offering | 2026-06-30 | verified | U.S. Securities and Exchange Commission |
| Measure | Value | As of | Basis | Source |
|---|---|---|---|---|
| Anthropic data center partnership (not in Arizona) | $50 billion of data centers with Fluidstack in Texas and New York, announced November 2025 | 2025-11-12 | company-reported From the company's own published information. | Anthropic |
| Measure | Value | As of | Basis | Source |
|---|---|---|---|---|
| County filing naming Fluidstack | Financing statement recorded June 5, 2026 (no. 20260339836), naming Fluidstack Int LLC and the owner, Northern Parkway Owner LLC | 2026-06-05 | verified | Maricopa County Recorder |
| Founded | 2017 | 2017-09-28 | verified | Companies House (UK) |
| Global headquarters moved to New York City | December 2025 | 2025-12-04 | company-reported From the company's own published information. | Fluidstack (PR Newswire) |
| Chief executive | Gary Wu | 2026-11-24 | company-reported From the company's own published information. | Fluidstack (PR Newswire) |
No coverage of Fluidstack in Arizona has been picked up yet. Browse all Arizona AI news.
Arizona AI is not tracking any open Fluidstack roles in Arizona at the moment. Listings refresh automatically twice a day.
Each listing on this page links through to Fluidstack's own application page. Arizona AI does not collect applications or charge job seekers, and roles are aggregated from the employer's official careers system rather than from third-party recruiters.
Fluidstack has not announced an Arizona data center as of November 27, 2026. Fluidstack's Arizona site is a factory at Luke Field near Glendale that makes modular data center equipment, which Fluidstack says it will supply to AI data centers.
Fluidstack leases Buildings A and B at Luke Field: 7911 N Litchfield Rd, Glendale, AZ 85307 and 13543 W Northern Ave, Glendale, AZ 85307. The addresses say Glendale, but the site is in unincorporated Maricopa County, so the county issues its building permits.
Fluidstack says the plant will supply its Blackbird modular data center modules, Compute Modules and Electrical Skids. Maricopa County's permit describes the products as "fully integrated, transportable technology mezzanine modules."
Fluidstack says the plant will support 1,250 permanent manufacturing and skilled trades jobs. That is the company's plan, not a current headcount.
Neither company has said so. Anthropic's November 2025 announcement covers data centers with Fluidstack in Texas and New York, and Fluidstack's November 2026 release about the Arizona plant does not mention Anthropic.