Compass Datacenters El Mirage Campus

Proposed data center in El Mirage Road and Peoria Avenue, El Mirage. Operated by Compass Datacenters.

This is a proposed or under-construction project. It is not operating capacity, and announced projects do sometimes change scope or fail to proceed.

Where it is

2023 aerial photo of the Compass PHX II platted campus area, including common Tract A, outlined in yellow.
Aerial photo flown September 17, 2023: USDA National Agriculture Imagery Program (NAIP); source: USGS, USDA, The National Map: Orthoimagery (public domain). Outline drawn by Arizona AI from Maricopa County Assessor parcel records.

Outlined in yellow: Compass PHX II platted campus area, including common Tract A. It shows the land, not where buildings would go. Parcels: City of El Mirage, Replat for Compass Datacenters PHX II, four numbered lots and common Tract A. Shapes: Maricopa County Assessor (read November 8, 2026).

Open in Google Maps

  • Capacity for the whole campus: 108 MW
  • Land: 121 acres

Capacity: Operator's own figure: whole campus. Compass: a 108 MW campus. The source does not say what the figure measures.

Timeline

  1. : Data Center Dynamics reports that Compass bought 121 acres at El Mirage Road and Peoria Avenue for $79.3 million. Source: Data Center Dynamics, Compass Datacenters acquires 120 acres in El Mirage, Arizona
  2. : The El Mirage City Council approves a final plat for Compass Datacenters PHX II (vote: 5-1 yes). Source: City of El Mirage, City Council regular meeting minutes, August 17, 2026
  3. : The El Mirage City Council approves a development agreement with Compass Datacenters PHX II (vote: 5-1 yes). Source: City of El Mirage, City Council regular meeting minutes, August 17, 2026

Working here

Per-facility headcount is not published here: no reliable public figures exist for these sites, and construction announcements are not permanent employment. Open Arizona roles at this operator, where there are any, are listed on the operator's company page.

Other Compass Datacenters facilities in Arizona

How we know this

Compiled from public records and checked on 2026-10-11. Confidence in this record: high. Blank figures mean the number is not publicly established, not that it is zero.

Each statement on this page is listed with the page it came from and the words that say it. Sources open in a new tab.

Our own notes

These remarks are Arizona AI's own. They say how this record is counted or what we could not find, so there is no outside page to link.

None of these permits shows a completion date in the reports through September 2026, so the campus stays with the announced projects.