Entrata Data Center (Mohave County)

The Entrata Data Center is a proposed project by developer Clean Cloud Energy on a 776-acre site near White Hills Airport, east of Highway 93 in unincorporated Mohave County. A December 2025 report gives a potential maximum capacity of 1.25 GW.

Proposed data center in Near White Hills Airport, east of Highway 93, unincorporated Mohave County (approximate). Being developed by Clean Cloud Energy.

Where it stands

AZBEX reported in December 2025 that the Entrata Data Center had already submitted a preliminary site plan application, and that Sakellakis said the current plan envisions starting development of the data center in 2027 or 2028. AZBEX reported in December 2025 that the Mohave County Board of Supervisors had approved zoning changes requiring proposed data centers to provide their own electricity and water, and that the Entrata Data Center may be exempt because its application was already submitted. AZBEX also reported that some members of the Board of Supervisors had expressed major reservations about a large-scale data center development near an airport.

The short version

Where does the project stand?

  • Aileron Investments LLC announced on November 29, 2023 that the county Planning and Zoning Commission and Board of Supervisors had unanimously approved the General Plan and land use zoning applications for Entrata, a master-planned community. AZBEX quoted a statement in December 2025 that the data center would sit on existing, zoned industrial property.
  • AZBEX reported in December 2025 that the project had already submitted a preliminary site plan application to Mohave County, and that Sakellakis said the current plan envisions starting development in 2027 or 2028.
  • AZBEX reported that Mohave County now requires proposed data centers to provide their own electricity and water, and that the Entrata Data Center may be exempt because it had already submitted its preliminary site plan application.
  • AZBEX also reported that some members of the Board of Supervisors had expressed major reservations about a large-scale data center development near an airport.

How big could it be?

  • AZBEX reported that the site plan shows 776.11 acres, with 34 data center modules ranging between 500 by 500 feet, 600 by 600 feet and 500 by 720 feet, three high-voltage substation pads, a hybrid cooling and water plant and nine retention basins.
  • AZBEX reported that the planned data center could create a $12.5 billion capital investment for the powered shell and up to 1,200 construction jobs and 150 full-time positions. Barbarich said the estimates are based on a ratio of $10 million per megawatt, with a potential maximum capacity of 1.25 GW.

Where would power and water come from?

  • AZBEX reported that Manny Sakellakis of Clean Cloud Energy, whom AZBEX calls its CEO, said primary power would come from the Mead Substation in Nevada and that the company is working with the Western Area Power Administration on transporting it to the site.
  • Mahomet Daily reported that Clean Cloud plans a solar project on adjacent federal land as a secondary power source.
  • AZBEX reported that the Entrata development already has a 100-year Certificate of Assured Water Supply in place from the Arizona Department of Water Resources.

Who is the developer?

  • AZBEX names Clean Cloud Energy as the project developer and Atwell, Inc. as the civil engineer.
  • Mahomet Daily reported in October 2026 that Clean Cloud, a name adopted when reNRG Partners changed its name in September 2024, has acted as a site-and-power developer rather than the eventual operator in each of its locations.
  • Capacity at full build-out: 1.3 GW
  • Land: 776.11 acres

Capacity: Figure reported in the press: at full build-out. Potential maximum, reported December 2025. The source does not say what the figure measures.

Timeline

  1. : AZBEX reported that the county Planning and Zoning Commission would consider the Entrata master plan requests on Oct. 11 and that supervisors could take up the matter in November or December. Source: AZBEX, Mohave P&Z to Consider 10,000-acre Master Plan Requests
  2. : Aileron Investments LLC announced unanimous county approval of the General Plan and zoning applications for Entrata, a master-planned community. Source: Digital Journal (Accesswire press release), Mohave County Welcomes Entrata: a New Master-Planned Community Approved for Development
  3. : The Mohave County Board of Supervisors approved zoning ordinance changes requiring proposed data centers to provide their own electricity and water, AZBEX reported. Source: AZBEX, Mohave County to Require Data Centers to Provide Power and Water

Working here

Per-facility headcount is not published here: no reliable public figures exist for these sites, and construction announcements are not permanent employment. Clean Cloud Energy is developing this site rather than operating it, so any long-term operator has not been established here.

How we know this

Compiled from public records and checked on 2026-11-13. Confidence in this record: high. Blank figures mean the number is not publicly established, not that it is zero.

Each statement on this page is listed with the page it came from and the words that say it. Sources open in a new tab.