CBRE Investment Management, then owner of the Frye Data Center at 2500 W Frye Rd in Chandler, proposed a 243,000 square foot expansion with a new building. Chandler City Council approved a development agreement, rezoning and preliminary development plan for it on June 27, 2024.
Proposed data center in 2500 W Frye Rd, Chandler. Being developed by Lincoln Property Company.
Lincoln Property Company announced the purchase on October 31, 2025, with plans to build out the facility’s vacant shell space and make cooling system improvements. As part of fitting out the remaining three halls, Lincoln targeted an initial 4.2MW for delivery in early Q1 2026.

Outlined in yellow: Two parcels identified through Chandler's Frye Data Center permit and Bank of America Data Center Lot 1B record. It shows the land, not where buildings would go. Parcels: City of Chandler, Ordinance 5105, CBRE Data Center Expansion, Exhibit A including Bank of America Data Center Lot 1B. Shapes: Maricopa County Assessor (read November 8, 2026).
Per-facility headcount is not published here: no reliable public figures exist for these sites, and construction announcements are not permanent employment. Lincoln Property Company is developing this site rather than operating it, so any long-term operator has not been established here.
Compiled from public records and checked on 2026-11-13. Confidence in this record: high. Blank figures mean the number is not publicly established, not that it is zero.
Each statement on this page is listed with the page it came from and the words that say it. Sources open in a new tab.
Status: Proposed
Note: Planned refers to the expansion. The site already has an existing data center.
expand the existing data center with a new building.
The 2500 W. Frye property's existing data center totals around 150,000 sq ft (13,935 sqm) on a 14.5-acre site.
Chandler City Council voted June 27 to pass and adopt a resolution for a development agreement, rezoning and preliminary development plan for the expansion
Floor area: 243,000 sq ft
Note: This is the planned expansion size reported in July 2024, not the existing building.
The development plans would expand Frye Data Center by 243,000 square feet.
Land: 14.5 acres
The 2500 W. Frye property's existing data center totals around 150,000 sq ft (13,935 sqm) on a 14.5-acre site.
Location: 2500 W Frye Rd, Chandler
The campus is located in Chandler's Price Corridor and carries an address of 2500 W. Frye Road.
Lincoln Property Company announced the purchase on October 31, 2025, with plans to build out the facility’s vacant shell space and make cooling system improvements. As part of fitting out the remaining three halls, Lincoln targeted an initial 4.2MW for delivery in early Q1 2026.
Lincoln will serve as the building’s property manager.
CHANDLER, Arizona, October 31, 2025 [...] announced the purchase of a 191,000-square-foot, partially occupied data center in Chandler, Arizona. The company plans to build out the facility’s vacant shell space, delivering new turnkey data center inventory and making cooling system improvements
Lincoln plans to fit out the remaining three halls, adding 16MW of critical capacity and positioning the building for immediate lease-up. An initial 4.2MW is targeted for delivery in early Q1 2026.
An existing building of about 150,000 sq ft, converted to a data center in 2002.
The 2500 W. Frye property's existing data center totals around 150,000 sq ft (13,935 sqm) on a 14.5-acre site.
Originally a manufacturing building constructed in 1988, the property was converted to a data center in 2002.
Chandler approved a 243,000 sq ft expansion in June 2024 for the owner, CBRE Investment Management.
Chandler City Council voted June 27 to pass and adopt a resolution for a development agreement, rezoning and preliminary development plan for the expansion
The development plans would expand Frye Data Center by 243,000 square feet.
a 150,000-square-foot campus owned by CBRE Investment Management. The campus is located in Chandler's Price Corridor and carries an address of 2500 W. Frye Road.
In October 2025 the former tenant appeared to have left and Lincoln Property Company was working to buy the site.
INAP is now HorizonIQ and focused on cloud and hosting services, and has seemingly exited the site.
Lincoln Property Company is working with the city of Chandler to update a development agreement that will allow the company to complete its purchase
Lincoln Property Company announced the purchase on October 31, 2025.
Full-service commercial real estate firm Lincoln Property Company (Lincoln) today announced the purchase of a 191,000-square-foot, partially occupied data center in Chandler, Arizona.
The county recorded a deed for the parcel on October 30, 2025, and the county assessor now lists 2500 West Frye Road Owner LLC as its owner.
"APN":"30324019A","PHYSICAL_ADDRESS":"2500 W FRYE RD CHANDLER 85224","OWNER_NAME":"2500 WEST FRYE ROAD OWNER LLC","DEED_NUMBER":"20250629554"
"names":["2500 WEST FRYE ROAD OWNER LLC","CPUS WEST FRYE ROAD LP"],"documentCodes":["SPEC/W D"],"recordingDate":"10-30-2025"
The Real Deal, citing the Phoenix Business Journal, reported that Lincoln paid CBRE Global Investment $130 million for the data center and its on-site substation.
The Dallas-based company bought the data center at 2500 West Frye Road in Chandler and a substation on-site from CBRE Global Investment for $130 million, the Phoenix Business Journal reported.
Lincoln Property Company said the property offers 28MW of confirmed utility power, served by an existing and dedicated on-site Salt River Project (SRP) substation, a utility supply figure and not the computing capacity of the building.
The Frye Road property offers 28MW of confirmed utility power, served by an existing and dedicated on-site Salt River Project (SRP) substation.
Lincoln said the building has four data center halls, one of them fully leased to a Fortune 500 enterprise user, and that it plans to fit out the remaining three halls, adding 16MW of critical capacity, with an initial 4.2MW targeted for delivery in early Q1 2026.
It features four data center halls, one of which is fully leased to a Fortune 500 enterprise user. Lincoln plans to fit out the remaining three halls, adding 16MW of critical capacity
An initial 4.2MW is targeted for delivery in early Q1 2026.
Lincoln said it will move the project from an evaporative cooled to an air cooled mechanical system, which it said creates the potential for up to 3 million gallons of water savings per month.
Lincoln will also transition the project from an evaporative cooled to air cooled mechanical system, creating the potential for up to 3 million gallons of water savings per month
Baxtel, in an undated listing, says Lincoln is fitting out the remaining three halls as new, liquid-cooling-capable capacity, with a first phase ready for service in June 2027 and a second phase in September 2027, and that long-lead equipment is on order.
Lincoln is fitting out the remaining three halls as new, liquid-cooling-capable capacity, with a first phase ready for service in June 2027 and a second phase in September 2027. Long-lead equipment is on order.