Proposed data center in Near Highway 98, Page (site not final). Being developed by Huntley LLC.
This is a proposed or under-construction project. It is not operating capacity, and announced projects do sometimes change scope or fail to proceed.
Per-facility headcount is not published here: no reliable public figures exist for these sites, and construction announcements are not permanent employment. Huntley LLC is developing this site rather than operating it, so any long-term operator has not been established here.
Compiled from public records and checked on 2026-10-07. Confidence in this record: high. Blank figures mean the number is not publicly established, not that it is zero.
Each statement on this page is listed with the page it came from and the words that say it. Sources open in a new tab.
Status: Proposed
Note: The city says only a land sale agreement exists and no development approvals have been granted.
City Council approved Ordinance 744-25, a land sale agreement that establishes a feasibility period for a potential future project.
No construction, zoning, utilities, or development approvals have been granted.
The agreement includes specific performance requirements and timelines. The sale cannot close until zoning and related issues are resolved.
Location: Near Highway 98, Page (site not final)
City-owned land defined in the land sale agreement, on the south-west side of Page near Highway 98.
No. The City has not committed to a specific design, size, or final site.
Page City Council approved a land sale agreement with Huntley LLC in October 2025 for a site within about 500 acres of city land.
City Council approved Ordinance 744-25, a land sale agreement that establishes a feasibility period for a potential future project.
a future site could be located anywhere within the approximately 500 acres of City-owned land defined in the land sale agreement
Then, at an October 2025 meeting, the council approved the sale in a 5-2 vote.
it states Huntley LLC wishes to develop a “1GW Data Center,”
As of September 2026 the city says the sale cannot close until zoning is resolved and it has not committed to a design, size or final site.
The agreement includes specific performance requirements and timelines. The sale cannot close until zoning and related issues are resolved.
No. The City has not committed to a specific design, size, or final site.
A 1 GW figure was reported in January 2026 but the city has committed to no size, so none is shown.
it states Huntley LLC wishes to develop a “1GW Data Center,”
No. The City has not committed to a specific design, size, or final site.