SpaceX says it is the owner of a proposed AI supercomputer campus on about 747 acres next to Apache Generating Station at Cochise, Arizona. Up to nine buildings would draw about 6 GW at full build-out. The application, filed by Tombstone Resources LLC, goes to a county hearing on December 9, 2026.
Proposed data center in U.S. Highway 191 at Cochise, next to Apache Generating Station. Being developed by SpaceX.
Cochise County is reviewing the campus's Special Use Authorization request, docket SU26-22. The Planning and Zoning Commission will hold its public hearing on December 9, 2026, at 2 p.m. in Bisbee, and its decision is final unless appealed to the Board of Supervisors. The electric cooperative that would serve the campus says no final electric service agreement has been reached.

Outlined in yellow: the 31 tax parcels in county case SU26-22 (two only in part). It shows the land, not where buildings would go. Parcels: Cochise County, Legal Notice SU26-22: US Hwy 191 Data Center Campus. Shapes: Cochise County GIS (read November 11, 2026).
Capacity: Figure from an official record: expected electricity demand, at full build-out. Applicant estimate in the county application: peak electric demand at full build-out, not secured service or operating computing load.
Data Centers are not permitted by right and cannot be approved through a building permit alone.
SpaceX is the owner, and with approval, will be the builder and the owner of the project long term.
If this development moves forward, we want to ensure that our members are protected and that any benefits to them are real.
Per-facility headcount is not published here: no reliable public figures exist for these sites, and construction announcements are not permanent employment. SpaceX is developing this site rather than operating it, so any long-term operator has not been established here.
Stories in Arizona AI's news feed that name this facility, newest first.
Compiled from public records and checked on 2026-11-11. Confidence in this record: high. Blank figures mean the number is not publicly established, not that it is zero.
Each statement on this page is listed with the page it came from and the words that say it. Sources open in a new tab. Where a source is listed without a quote, none was recorded.
Status: Pending county approval
Expected power demand at full build-out: 6.0 GW
Note: Applicant estimate of peak electric demand at full build-out, not operating computing load or secured electric service.
Floor area: 4.4M sq ft
Note: About 493,000 square feet in each of up to nine buildings.
Land: 747 acres
Note: Two of the 31 listed tax parcels are included only in part.
Location: U.S. Highway 191 at Cochise, next to Apache Generating Station
Note: Cochise is an unincorporated community; the site has no street address yet.
Cochise County is reviewing the campus's Special Use Authorization request, docket SU26-22. The Planning and Zoning Commission will hold its public hearing on December 9, 2026, at 2 p.m. in Bisbee, and its decision is final unless appealed to the Board of Supervisors. The electric cooperative that would serve the campus says no final electric service agreement has been reached.
Tombstone Resources LLC filed Special Use Authorization request SU26-22 with Cochise County on October 30, 2026, for a supercomputer and AI data center campus with battery energy storage.
The campus would cover about 747 acres on two properties along U.S. Highway 191 at Cochise, each next to Apache Generating Station land: about 400 acres owned by Arizona Electric Power Cooperative (AEPCO) and about 348 acres owned by Southline Transmission LLC.
The county hearing notice lists 31 tax parcels, two of them only in part, zoned RU-4 (rural, one dwelling per 4 acres).
The plan calls for up to nine single-story computing buildings in four phases, each about 1,900 by 260 feet and about 493,000 square feet, or about 4.4 million square feet in all.
The campus would include a 24 GWh battery energy storage installation, substation and transformer yards, and natural-gas standby generators for critical services only.
The application describes owner-operated high-performance computing for AI model training and inference, primarily for the applicant and its affiliates.
Cochise County says data centers are not permitted by right and cannot be approved through a building permit alone.
Data Centers are not permitted by right and cannot be approved through a building permit alone.
A November 4 statement on Tombstone Resources letterhead said SpaceX would host a community town hall that evening at Cochise Elementary School.
SpaceX will host a community town hall on Wednesday, November 4, at 6:00 p.m. at Cochise Elementary School
At that meeting Riley Trettel, who leads energy and supercomputer development at SpaceX, said SpaceX is the owner of the project and, if it is approved, will build it and own it long term.
I do want to confirm to you all here tonight that SpaceX is the owner, and with approval, will be the builder and the owner of the project long term
He put the investment at up to $50 billion, the company's own estimate rather than a published budget.
The application says Tombstone Resources is under contract to buy the AEPCO land, is under agreement with Southline Transmission for its land, and files as both owners' authorized agent.
County tax records for tax year 2027 list AEPCO or Southline Transmission as owner of 24 of the 31 parcels, a family trust on six and the state highway department on one.
The applicant estimates about 6,000 MW of electric demand at full build-out, all from the grid through Sulphur Springs Valley Electric Cooperative (SSVEC) and its wholesale supplier AEPCO, with about 1,500 MW in the first phase.
The application targets March 2027 for initial electric service for construction, and says each phase would take about one to two years from the start of vertical construction to occupancy.
The applicant says it would pay for about $3.6 billion of transmission and substation improvements.
SSVEC said on November 5 that no final electric service agreement had been reached and that any agreement will need Arizona Corporation Commission approval.
The application says the power arrangement is designed to cut SSVEC members' electric bills by about 10% to 40% and to give $13 million to $53 million a year to the SSVEC Foundation, subject to Corporation Commission approval.
SSVEC says none of these potential benefits is guaranteed.
no final electric service agreement has been reached, and none of these benefits is guaranteed.
SSVEC chief executive Jason Bowling said the cooperative wants its members protected if the development moves forward.
If this development moves forward, we want to ensure that our members are protected and that any benefits to them are real.
The concept drawings label the two properties 3,500 MW and 2,800 MW, which add up to 6,300 MW, while the rest of the application says about 6,000 MW.
The campus would be dry-cooled, with closed liquid loops and fan-cooled dry coolers, and no cooling towers or evaporative spray in normal operation.
The applicant estimates water use of about 7 to 10 acre-feet a year at full build-out, mostly for the operating staff, plus a one-time fill of each building's cooling loops, about 3 to 6 million gallons across the campus.
Its planned non-potable water source is treated wastewater from Apache Generating Station, with trucked water as a backup, and no new Willcox AMA production well is proposed.
The site is near the Willcox Playa, a wintering area for sandhill cranes, and the application lists measures such as no open water, bird-safe glass and shielded lighting.
The applicant estimates about 5,500 construction workers at peak and about 1,000 permanent jobs at full build-out, including on-site contractors.
It also estimates $34 million to $103 million a year in new county property tax revenue and a one-time county sales tax benefit of about $250 million.
The county Local Emergency Planning Committee will hold a special public meeting on the proposal on November 12, 2026, at 1 p.m.; its role is advisory.
Written comments must reach the county by noon on November 27, 2026, to be included in the hearing packet.
The Planning and Zoning Commission will hold its public hearing at or after 2 p.m. on December 9, 2026, in the Board of Supervisors Hearing Room at 1415 Melody Lane, Building G, Bisbee.
Comments at the hearing are limited to two minutes per speaker unless the chair directs otherwise.
The Commission's decision is final unless appealed to the Board of Supervisors.
If the campus is approved, building permits would be obtained phase by phase.