La Osa Energy Center is Vermaland's plan for a data center and natural gas power campus on 3,385 acres south of Eloy in Pinal County. Supervisors denied its rezoning 4-1 on August 26, 2026, and Vermaland plans to resubmit a smaller version.
Status: Original plans denied; may resubmit. On August 26, 2026, the Pinal County Board of Supervisors voted 4-1 to deny the rezoning and the Planned Area Development overlay the project needed. Vermaland had already cut the plan from up to 59 data center buildings to 11. In an Arizona Globe article published September 10, 2026, founder and CEO Kuldip Verma said Vermaland is still pursuing the project and plans to resubmit it at 200 or 500 MW. Its figures describe what was proposed. They are not counted in the statewide totals.
In an Arizona Globe article published September 10, 2026, founder and CEO Kuldip Verma said: "We are pursuing the project." Vermaland plans to downscale it from a 1 GW facility to either 200 or 500 MW and resubmit, with no timeline or final size confirmed yet. "The board gave us a thorough hearing, and we respect that," he said. In July 2026, county planning staff said they were working on a potential ordinance or standards for data centers. The county's August 2026 staff report notes the site's land-use designation was approved under case PZ-PA-011-25 (the Board vote was November 19, 2025). The land is still zoned General Rural.
Vermaland's application, after a county concept review on May 13, 2025, described the La Osa Employment Center: data centers with natural gas generation. EPS Group Inc. was the civil engineer and planner, and attorney Court Rich of Rose Law Group represented the applicant. Kuldip Verma told KJZZ in August 2025 the plan would cost over $33 billion and could support about 3 gigawatts, and that he expected county approval in the first quarter of 2026.
On August 7 and 14 the applicant submitted 22 more stipulations; its hearing presentation counted 23 new and 56 conditions in all. Among them:
Its August 26 presentation said electric service would come from Electrical District 4, the site sits on the Kinder Morgan El Paso Natural Gas system, a 15-year firm gas supply, at the term sheet stage, was arranged to start in November 2027, and 200 MW of aeroderivative turbines were confirmed available. It priced grid upgrades at roughly $150 million, paid by the project. Citing Elliott D. Pollack & Co., it projected about 360 direct jobs, $18.6 billion of capital investment for a 1,000 MW campus and $31.6 million a year in public tax revenue at buildout. It also quoted Derek McEachern, general manager of Electrical District 4 and the Central Arizona Irrigation and Drainage District: "We believe the aquifer can easily accommodate this use."
County staff and the Planning and Zoning Commission had not reviewed the 22 added stipulations, and staff recorded 123 letters in opposition and 16 in support. Staff's report also noted that the Mayor of Eloy submitted a recommendation of support, and called La Osa the first proposed data center campus for Pinal County. The Board also received 105 comment cards from people who did not speak, 100 of them opposed. Forty-eight members of the public spoke against and 14 in favor, including members of local construction unions; opponents cited water, electrical infrastructure, noise, air pollution and property values.
On August 26, 2026, Supervisor Rich Vitiello moved to deny and Vice-Chairman Jeff Serdy seconded. Chairman Jeffrey McClure and Supervisor Mike Goodman also voted to deny, and Supervisor Stephen Miller voted against denial, so both the rezoning and the overlay were denied 4-1. "Individuals have a right to use their property the way they want," Miller said. "When 90% of the people are against it, I'm going to vote the will of the people," Serdy said.

Outlined in yellow: the 40 parcels in the county case. It shows the land, not where buildings would go. Parcels: Pinal County Board of Supervisors, Regular Session Minutes, November 19, 2025 (Item 10). Shapes: Pinal County GIS (read November 6, 2026).
Capacity: Operator's own figure: at full build-out. Vermaland's August 26, 2026 presentation to the Board of Supervisors describes a 1,000 MW campus, and the stipulations it proposed would have capped on-site natural gas generation at 1,000 MW. The 2025 plan was described as up to about 3 GW. The source does not say what the figure measures.
We are pursuing the project.
Individuals have a right to use their property the way they want.
When 90% of the people are against it, I’m going to vote the will of the people.
Stories in Arizona AI's news feed that name this facility, newest first.
Compiled from public records and checked on 2026-11-05. Confidence in this record: high. Blank figures mean the number is not publicly established, not that it is zero.
Each statement on this page is listed with the page it came from and the words that say it. Sources open in a new tab.
Status: Original plans denied; may resubmit
The board voted 4-1 against rezoning the land, essentially killing the project.
Pinal County supervisors on Wednesday rejected plans to build La Osa Energy Center, a massive development planned outside Eloy.
To deny Ordinance No. 2026-PZ-003-26, an Ordinance approving case PZ-003-26
it plans to downscale and resubmit its proposal
Proposed capacity at full build-out: 1.0 GW
Note: The developer's own figure for the scaled-back plan. Stipulation 55, one of the 22 conditions the applicant added in August 2026, would have capped on-site natural gas generating capacity at 1,000 megawatts.
1,000 MW campus
that generate electricity through the combustion of natural gas shall not exceed 1,000 megawatts
Land: 3,385 acres
rezone a total of 3,385 acres from General Rural (GR)
Location: South of Eloy, Pinal County (approximate)
in the planning area boundary south of the City of Eloy, in the unincorporated area of Pinal County
On August 26, 2026, the Pinal County Board of Supervisors voted 4-1 to deny the rezoning and the Planned Area Development overlay the project needed.
To deny Ordinance No. 2026-PZ-003-26, an Ordinance approving case PZ-003-26
To deny Ordinance No. 2026- PZ-PD-003-26
Ayes: Goodman, McClure, Serdy, Vitiello (4)
Vermaland had already cut the plan from up to 59 data center buildings to 11.
Number of Data center buildings reduced from 59 to 11 buildings, under stipulation # 34.
In an Arizona Globe article published September 10, 2026, founder and CEO Kuldip Verma said Vermaland is still pursuing the project and plans to resubmit it at 200 or 500 MW.
“We are pursuing the project,” said Vermaland’s founder and CEO, Kuldip Verma.
planning to downscale the project from a 1 GW facility to either a 200 or 500 MW facility
La Osa Ranch covers about 18,300 acres of southern Pinal County, from the Santa Cruz River west toward the Tohono O'odham Nation.
about 18,300 acres of land in southern Pinal County spreading from the Santa Cruz River west toward the Tohono O'odham Reservation
In December 2003 the Board of Supervisors amended the county land-use plan to allow a previous owner up to 61,299 homes and 5,682 apartments on 19,670 acres at La Osa.
approves an amendment to its land-use plan that would allow Johnson to build up to 61,299 homes and 5,682 apartments on 19,670 acres
In March 2004 the county Planning and Zoning Commission recommended against rezoning La Osa, even after the plan was cut to 30,000 homes on 9,116 acres.
recommends disapproval of rezoning La Osa, which Johnson had offered to cut down to putting only 30,000 homes on 9,116 acres
In January 2008 the City of Eloy expanded its planning area to take in all of La Osa Ranch, with the intent to annex it later.
On Jan. 14 the Eloy City Council approved a plan by City Manager Joe Blanton
taking in the entirety of La Osa Ranch with the intent to annex the property in the future
The site is still unincorporated county land inside Eloy's extended planning boundary.
in the extended planning boundary south of the City of Eloy, in the unincorporated area of Pinal County
Vermaland bought 4,000 acres of La Osa Ranch in 2012 and another 4,000 acres in 2013.
Vermaland bought 4,000 acres in La Osa Ranch in 2012 and recently acquired an additional 4,000 acres in the same community.
The buyer was Verma La Osa Ranch, an LLC holding company for Verma Legacy Trust.
The purchasing entity for the project is Verma La Osa Ranch, an LLC holding company for Verma Legacy Trust.
Kuldip Verma said at the time: "We purchased this property because of its extremely low value and the growth potential."
We purchased this property because of its extremely low value and the growth potential,
Vermaland's 2013 plans called for more than 33,000 residential lots, 1,000 acres of commercial development and 2,000 acres of open space.
Current plans call for more than 33,000 residential lots, 1,000 acres of commercial development and 2,000 acres of open space
Vermaland, founded in 2006 by Kuldip Verma, is a Phoenix land development and land banking company with more than 25,000 acres in its portfolio.
Established in 2006 by Kuldip Verma, Vermaland, LLC is a land development and land banking company based in Phoenix, Arizona.
With a portfolio encompassing over 25,000 acres
County parcel records list Verma La Osa Ranch I-10/Sasco 3700 LLC as the owner of 26 of the 33 parcels in the recorded Sasco subdivision. Two of them, and ten lots in Sasco's Smelter Addition held by Verma La Osa Ranch I-10/Sasco Rd Casa Grande 3677 Acres LLC, were in the La Osa case.
VERMA LA OSA RANCH 1-10/SASCO 3700 LLC
"count": 33
VERMA LA OSA RANCH 1-10/SASCO RD CASA GRANDE 3677 ACRES LLC
409-26-0010; 409-26-002A; 409-26-002B; 409-26-0240; 409-26-0220; 409-26-0250;
Sasco was named for the Southern Arizona Smelting Co., whose smelter there processed copper ore from the Silverbell Mountains beginning in 1908.
Sasco, an acronym for the Southern Arizona Smelting Co. that operated the nearby smelter in 1908.
the Sasco smelter processed low-grade copper ore mined from the Silverbell Mountains.
By 1910 Sasco had more than 600 residents, and its smelter buildings were dismantled in the 1930s.
By 1910, Sasco had a population of more than 600
During the 1930s, the train tracks and smelter buildings were dismantled and removed.
Pinal County places the site along the Greene Wash, south of Baumgartner Road and the City of Eloy, in Supervisor District 4.
south of Baumgartner Road, and east of Eleven Mile Corner Road, south of the City of Eloy
located along the Greene Wash of the Santa Cruz Wash
Supervisor District #4.
The land is still zoned General Rural.
The property is currently zoned General Rural (GR)
rezone a total of 3,385 acres from General Rural (GR)
To deny Ordinance No. 2026-PZ-003-26, an Ordinance approving case PZ-003-26
Two 115 kV Western Area Power Administration lines cross the middle of the site, and a 230 kV APS line crosses its southern edge.
two 115 kV Power lines (WAPA) and cross the parcels in the center and a 230 kV power line (APS)
Most of the land around the site is state land, with Bureau of Land Management land to the south.
You can see BLM to the south, State Land, most of it State Land
The landowners of record are Verma La Osa Ranch I-10/Sasco 3700 LLC and Verma La Osa Ranch I-10/Sasco Rd Casa Grande 3677 Acres LLC, with Vermaland LLC as their contact.
Verma La Osa Ranch I-10/Sasco 3700 LLC Contact: Vermaland LLC
Verma La Osa Ranch I-10/Sasco Rd Casa Grande 3677 Acres LLC
Vermaland's application, after a county concept review on May 13, 2025, described an industrial employment facility called the La Osa Employment Center, made up of data centers and natural gas generation.
The developer is seeking to develop an industrial employment facility (La Osa Employment Center) comprised of data centers and natural gas energy generation facilities.
Date of Concept Review: 05/13/2025
EPS Group Inc. was the civil engineer and planner, and attorney Court Rich of Rose Law Group represented the applicant.
Civil Engineer and Planner: EPS Group Inc.
Law Group, Court Rich, who is representing the applicant.
Kuldip Verma told KJZZ in August 2025 that the plan would cost over $33 billion and could support about 3 gigawatts.
CEO Kuldip Verma says the plan would cost over $33 billion when all is said and done.
Verma said the project would be able to support about 3-GW of energy
He said he expected Pinal County's approval in the first quarter of 2026.
And we are anticipated to get approval from Pinal County in first quarter of 2026,
The comprehensive plan amendment, case PZ-PA-011-25, first asked to re-designate 3,374 acres of residential and open space land to 1,910 acres of Employment, 480 acres of public facilities for energy generation and 983 acres of open space.
re-designate 3,374± acres of land from Very Low Density Residential
to 1,910± acres Employment, to 480± acres General Public Facilities/Services, and 983± acres of Proposed Open Space
The intent of the General Public Facilities/Services is to provide energy generation to support
At the Citizens Advisory Committee on September 4, 2025, Court Rich said the project would not use water cooling technology.
We’re not using water cooling technology here, and the developer will be stipulating to this
The committee recommended approval 11-4.
The Citizen Advisory Committee has recommended approval of Case PZ-PA-011-25 with a vote of 11-4
On October 16, 2025, the Planning and Zoning Commission recommended approval 7-3.
The Planning and Zoning Commission recommended approval (7-3) of case PZ-PA-011-25 with no stipulations.
MEETING DATE: OCTOBER 16, 2025
On November 19, 2025, the Board of Supervisors approved the amendment 5-0 as Resolution No. 2025-PZ-PA-011-25.
To approve Resolution No. 2025-PZ-PA-011-25, a Resolution approving case PZ-PA-011-25
Ayes: Goodman, McClure, Miller, Serdy, Vitiello (5)
As approved, it re-designated 3,385.32 acres: 1,907.12 acres of Employment, 486.51 acres of General Public Facilities/Services and 991.69 acres of open space.
1,907.12 ± acres of Employment; 486.51 ± acres of General Public Facilities/Services, and 991.69 ± acres of Proposed Open Space
Five members of the public spoke in favor, including the Arizona Technology Council and the Arizona City Fire District's fire chief, and three spoke against, including Rural Arizona Engagement's senior political advisor.
Cepand Alizadeh, Arizona Technology Council; and Jeff Heaton, Fire Chief, Arizona City Fire District.
In opposition; Tyler Stein, Casa Grande; Tom Prizsky, Senior Political Advisor, Rural Arizona Engagement
The 2026 rezoning, case PZ-003-26, asked to rezone 2,393 acres from General Rural to I-3 Industrial and keep 992 acres as open space.
to 2,393 acres of Industrial (I-3) zoning district and 992 acres of Proposed Open Space
A companion Planned Area Development overlay, case PZ-PD-003-26, covered data centers, gas-fired power generation and battery storage.
CASE NO(S): PZ-003-26/PZ-PD-003-26- LA OSA ENERGY PROJECT
for a Data Center, Gas Fired Power Generation, Battery Storage, and associated offices and facilities
The county's May 2026 presentation showed up to 59 data center buildings across more than 2,000 acres and two gas-fired power plants, built in three phases.
Maximum Data center buildings: 59 buildings across 2000 + acres
Gas Fired Power generation: 2 plants
Project consists of 3 phases:
On April 16, 2026, the Planning and Zoning Commission recommended approval of both cases 7-2, with one stipulation on the rezoning and 33 on the overlay.
PZ-003-26: Recommended Approval 7-2
PZ-003-26 (1 stipulation)
PZ-PD-003-26 (33 stipulations)
At the Board's May 27, 2026 hearing, before public comment, Court Rich asked for a continuance to cut the project by 80 percent.
requested a continuance to modify the project by an 80% reduction.
The Board continued the case to August 26, 2026, by a 3-1 vote, with Supervisor Vitiello opposed and Vice-Chairman Serdy absent.
To continue to August 26, 2026 Board Meeting with Public Hearing.
Ayes: Goodman, McClure, Miller (3)
Nays: Vitiello (1)
Absent: Serdy (1)
Forty-one members of the public spoke against and three in favor, including the Arizona Commerce Authority and the Avra Valley Fire District's fire chief; 65 of 67 comment cards from people who did not speak were opposed.
Fire Chief, Avra Valley Fire District; and Keith Watkins, Arizona Commerce Authority.
sixty-seven (67) comment cards were received who did not wish to address the Board; sixty-five (65) in opposition
By the August 26, 2026 hearing, attorney Taylor Earl of Earl & Curley had replaced Rose Law Group as the applicant's representative.
Applicant changed from Rose Law Group PC to Earl & Curly. Taylor Earl, Attorney.
On August 7 and 14, 2026, the applicant submitted 22 more stipulations, including a limit of 11 data center buildings of no more than 400,000 square feet each, plus ancillary structures.
Additional 22 stipulations to address community concerns submitted to the County on 7th &14th August.
The number of data center buildings within the Subject Property shall be limited to eleven
No data center building shall exceed 400,000 square feet in gross floor area
Vermaland's hearing presentation counted 23 new stipulations and 56 conditions in all.
The 23 new stipulations add to them: 56 binding conditions in all.
The added stipulations would have capped potable water at 600 net acre-feet a year for the data centers, power generation and battery storage, and required closed-loop cooling for data center and battery storage buildings.
The Owner shall not exceed an aggregate of 600 net acre-feet per year of potable water
all data center and battery storage buildings shall utilize only closed-loop systems for cooling
They would have required the data centers to run on on-site power until a utility could serve them, and capped on-site natural gas generation at 1,000 megawatts.
any data center usage shall utilize on-site generation or behind the meter power generation facilities
that generate electricity through the combustion of natural gas shall not exceed 1,000 megawatts
They would have set noise limits of 60 dBA by day and 55 dBA at night, measured from the nearest property line.
does not exceed 60dBA between the hours of 8:00 a.m. and 9:00 p.m., and 55dBA between the hours of 9:00 p.m. and 8:00 a.m.
as measured from the nearest property line of the Subject Property.
Vermaland's August 26 presentation said electric service would come from Electrical District 4.
Electric service will come from ED-4.
It said the site sits on the Kinder Morgan El Paso Natural Gas system and that a 15-year firm gas supply, at the term sheet stage, was arranged to start in November 2027.
The site sits on the Kinder Morgan El Paso Natural Gas system.
A 15-year enhanced firm gas supply is arranged with a national supplier, starts Nov 2027
TERM SHEET
It said 200 MW of aeroderivative turbines were confirmed available and priced grid upgrades at roughly $150 million, paid by the project.
200 MW of zero-hour, fully OEM-warrantied aeroderivative turbines confirmed available
roughly $150 million to serve this project
Citing Elliott D. Pollack & Co., it projected about 360 direct jobs, $18.6 billion of capital investment for a 1,000 MW campus and $31.6 million a year in public tax revenue at buildout.
the project will employ approximately 360 direct onsite jobs
$18.6B total capital investment
$31.6 MILLION in public tax revenue
It quoted an August 5, 2026 letter from Derek McEachern, general manager of ED-4 and the Central Arizona Irrigation and Drainage District: "We believe the aquifer can easily accommodate this use."
We believe the aquifer can easily accommodate this use.
County staff and the Planning and Zoning Commission had not reviewed the 22 added stipulations, and staff recorded 123 letters in opposition and 16 in support.
Pinal County staff have not reviewed the additional 22 stipulations submitted by the applicant.
Planning and Zoning Commission have not reviewed the additional 22 stipulations submitted by the applicant.
Staff received 123 opposition letters from people and 16 letters of support for the case.
Staff's report also noted that the Mayor of Eloy submitted a recommendation of support, and called La Osa the first proposed data center campus for Pinal County.
The City of Eloy Mayor submitted a recommendation of support for the proposed La Osa Energy project.
The La Osa Energy Center represents the first proposed data center campus for Pinal County.
On August 26, 2026, Supervisor Rich Vitiello moved to deny and Vice-Chairman Jeff Serdy seconded; Chairman Jeffrey McClure and Supervisor Mike Goodman also voted to deny, and Supervisor Stephen Miller voted against denial.
Motion Made By: Supervisor Vitiello
Seconded By: Supervisor Serdy
Nays: Miller (1)
Chairman Jeffrey McClure, Vice-Chairman Jeff Serdy, and supervisors Rich Vitiello, Mike Goodman and Stephen Miller
The Board also received 105 comment cards from people who did not speak, 100 of them opposed.
one hundred five (105) comments card were received who did not wish to address the Board; one hundred in opposition
Forty-eight members of the public spoke against and 14 in favor, including members of local construction unions; opponents cited water, electrical infrastructure, noise, air pollution and property values.
The following members of the public appeared before the Board and spoke:
Members of local construction unions supported the project
listing concerns about water use, the need for new electrical infrastructure, noise, air pollution, property values
Supervisor Miller said: "Individuals have a right to use their property the way they want."
Individuals have a right to use their property the way they want,
Vice-Chairman Serdy said: "When 90% of the people are against it, I'm going to vote the will of the people."
When 90% of the people are against it, I’m going to vote the will of the people,
Kuldip Verma said in an Arizona Globe article published September 10, 2026: "We are pursuing the project."
“We are pursuing the project,” said Vermaland’s founder and CEO, Kuldip Verma.
He said Vermaland plans to downscale it from a 1 GW facility to either 200 or 500 MW and resubmit, with no timeline or final size confirmed yet.
planning to downscale the project from a 1 GW facility to either a 200 or 500 MW facility
Vermaland could not confirm a timeline for the new proposal, nor the exact size of the new smaller facility
He also said: "The board gave us a thorough hearing, and we respect that."
The board gave us a thorough hearing, and we respect that
County planning staff told the Planning and Zoning Commission in July 2026 that they were working on a potential ordinance or standards for data centers.
yes, staff is working on a potential ordinance or standards for data centers.
County staff's August 2026 report states that the site's land-use designation was approved under case PZ-PA-011-25.
The land-use designation for La Osa Energy Center was approved under Major Comprehensive Plan Amendment case PZ-PA-011-25
These remarks are Arizona AI's own. They say how this record is counted or what we could not find, so there is no outside page to link.
No new La Osa or Vermaland case appeared on Pinal County's public meeting agendas from August 27 through November 4, 2026.