By Arizona AI · Profile reviewed · 46 sourced facts
Meta Platforms, the company behind Facebook, Instagram, Messenger and WhatsApp, runs the Mesa Data Center in Mesa, Arizona, which Meta announced was serving traffic on January 30, 2025. Meta broke ground in Mesa in August 2021, and as of January 2025 the first two Mesa Data Center buildings were operating and three more were under construction. Meta's Mesa info sheet lists $1.2 billion of data center investment in Arizona. Salt River Project says its Eleven Mile Solar Center in Pinal County provides power to Meta's Mesa data center.
Sources: KTAR News (Phoenix Business Journal), U.S. Securities and Exchange Commission · Addresses open Google Maps in a new tab
Modern AI runs on physical silicon, and that silicon passes through several hands before it ever answers a question. Here is the path, and where Meta sits on it. Stages not marked below are shown for context and are not claims about Meta.
Company-wide, Meta reports two segments: Family of Apps, which includes Facebook, Instagram, Messenger and WhatsApp, and Reality Labs, which covers virtual and augmented reality products. It was incorporated in Delaware in July 2004, introduced the Meta company brand in October 2021, and has its principal executive offices in Menlo Park, California; SRP and DPR Construction documents from 2022 refer to it as Meta (formerly Facebook).
Meta owns 30 data center locations worldwide.
Mesa campus: Meta Platforms, the company behind Facebook, Instagram, Messenger and WhatsApp, runs the Mesa Data Center at 3841 S. Ellsworth Road in Mesa, which has been serving traffic since January 2025. As of January 2025 the first two buildings were operating and three more were under construction, with the second phase expected in 2026. The City of Mesa issued a temporary power permit for the campus's second phase in December 2025, and the Maricopa County Assessor listed the campus as partly complete for the 2027 tax year. Meta's Mesa info sheet, as of October 2026, lists $1.2 billion of data center investment in Arizona without saying whether that figure is spent to date or the planned total.
In May 2021 the City of Mesa considered agreements with Redale LLC covering approximately 396 acres at the southeast corner of Elliot and Ellsworth roads. City documents name the developer as Redale LLC, which Data Center Dynamics reported was the name Facebook used while negotiating the project.
Meta broke ground in Mesa in August 2021, and in May 2022 it announced three more buildings, describing a planned campus of more than 2.5 million square feet. The city agreement allows up to 3 million square feet.
On January 30, 2025, Meta announced that the Mesa Data Center was serving traffic. As of January 2025, the first two buildings were operating, three more were under construction and the second phase was expected in 2026. The City of Mesa issued a temporary power permit for the campus's second phase in December 2025, and the Maricopa County Assessor listed the campus as partly complete for the 2027 tax year.
In January 2025, Meta said the facility supported more than 200 operational jobs; its Mesa info sheet, as of October 2026, lists 200+ operational jobs supported once completed. Meta also said construction drew an average of 2,000 skilled trade workers on site at peak. Meta describes these as jobs the facility supports and does not say how many are Meta employees; no source states how many people Meta employs in Arizona.
In its January 2025 announcement, Meta describes the Mesa site as part of the global infrastructure that brings its technologies and services to life; the announcement does not say which workloads run there.
Power infrastructure: Salt River Project proposed Project Huckleberry, a half-mile 230 kV transmission line and substation to serve the data center, with Meta funding the cost of that infrastructure. The Arizona Corporation Commission approved the project's Certificate of Environmental Compatibility at its August 16, 2022 open meeting. No source read confirmed when the line entered service.
In October 2024 SRP celebrated the official commencement of the Eleven Mile Solar Center in Pinal County, a 300 MW solar project with a 300 MW / 1,200 MWh battery system that SRP says provides power to Meta's Mesa data center. In December 2023, SRP announced an allocation to Meta of 50 MW from the West Line Solar Facility in Eloy plus a portion of the Brittlebush Solar Facility in Coolidge; no source read confirms the size of the Brittlebush allocation or when it began. In January 2025 Meta said three Meta-supported SRP projects were adding 450 MW of new renewable energy in Arizona.
Water and electricity: Under Mesa's 2021 agreement for the site, the annual water allowance is 550 acre-feet for the first phase, rising to 1,100 and 1,400 acre-feet if later phases are built, and the company must assign 5,500 acre-feet of long-term storage credits to Mesa. Meta reported 24,657 MWh of electricity use and 57 megaliters of water withdrawal at Mesa for 2024, before Meta announced in January 2025 that the site was serving traffic. Meta says it pays the full cost of the energy and the water and wastewater service its data center uses, and that it will restore 200% of the water the data center consumes to local watersheds; its info sheet, as of October 2026, says it has supported 12 water restoration projects so far.
Locally, Meta says it has provided more than $2.4 million in direct funding to Maricopa County-area schools and nonprofits, and says its total support for the Mesa College Promise program at Mesa Community College reached $300,000 with a $225,000 grant announced in January 2025. In August 2022, DPR Construction announced that it and Meta were bringing Meta's paid, eight-week Hardhat in Hand skilled trades training program to the Mesa site; no source says whether the program is still running.
Taken together, the facts show a large data center campus in Mesa that began serving traffic in January 2025 and, as of January 2025, was partly built, with a dedicated SRP line and substation proposed for the site in 2022 whose in-service date no source confirmed, solar power that SRP says serves it, and city water allowances set by a 2021 agreement.
Company-wide, Meta says its AI investments help power content ranking, recommendations, advertiser tools and new generative AI experiences, and in its July 2026 filing it projects capital expenditures of approximately $130 billion to $145 billion in 2026 to support its AI efforts and core business. The filing gives no Arizona breakdown of that spending, so Arizona AI does not attribute it to Mesa.
Arizona AI found no source stating the Mesa campus's role in Meta's AI work, and no source states an Arizona employee count.
2023 state lawsuit over teen social media features, settled 2026: In October 2023 Arizona and dozens of other states sued Meta, alleging that it purposely addicted children and teens to its social media platforms. On August 26, 2026 the Arizona Attorney General announced a multistate settlement under which Arizona will receive approximately $223 million, and the federal court in Oakland, California approved the deal the same day. Meta has denied the allegations. The case concerns Meta's social media products, not its Mesa data center.
2026 workforce reduction, company-wide: Meta told employees in April 2026 it would cut roughly 8,000 jobs, about 10 percent of its workforce, and its quarterly report for the period ended September 30, 2026 records a May 2026 headcount reduction of approximately 8,000 employees.
Papers from the past 12 months in Arizona AI's research catalog with an author affiliated with Meta, as indexed by OpenAlex. Company authors may work outside Arizona.
Each figure is dated and linked to its source. Figures that are company-reported, announced, or projected rather than measured are labeled.
| Measure | Value | As of | Basis | Source |
|---|---|---|---|---|
| Address | 3841 S. Ellsworth Road, Mesa, AZ 85212 | 2026-10-28 | verified | KTAR News (Phoenix Business Journal) |
| Role | Data center serving traffic for Meta's technologies and services as part of its global infrastructure | 2025-01-30 | verified | Meta |
| Status | First two buildings operating; three more data center buildings under construction, with the second phase expected in 2026 (as of January 2025) | 2025-01-31 | verified | KTAR News (Phoenix Business Journal) |
| Phase two temporary power permit | Issued December 2, 2025 (City of Mesa permit PMT23-14327) | 2025-12-02 | verified | City of Mesa Open Data |
| Planned campus layout | Five-building campus | 2022-08-23 | announced From a public announcement. Plans can change. | DPR Construction |
| Mesa Data Center begins serving traffic | January 2025 | 2025-01-30 | verified | Meta |
| Measure | Value | As of | Basis | Source |
|---|---|---|---|---|
| Facebook announces and breaks ground on its Mesa data center | August 2021 | 2021-08-12 | verified | Meta |
| Meta announces three more buildings for the Mesa campus | May 2022 | 2022-05-04 | announced From a public announcement. Plans can change. | Meta |
| Maximum build-out authorized under Mesa's development agreement | Up to 3 million sq ft | 2021-05-17 | verified | City of Mesa |
| Mesa Data Center electricity consumption, 2024 | 24,657 MWh | 2024-12-31 | company-reported From the company's own published information. | Meta |
| Eleven Mile Solar Center, a Pinal County power source for the Mesa data center | 300 MW solar project with a 300 MW / 1,200 MWh battery system; operating since October 2024 | 2024-10-11 | verified | Salt River Project |
| Other SRP solar allocations for the Mesa data center | 50 MW from the 100 MW West Line Solar Facility in Eloy, plus a portion of the 200 MW Brittlebush Solar Facility in Coolidge | 2023-12-11 | announced From a public announcement. Plans can change. | Salt River Project |
| Dedicated SRP power line and substation (Project Huckleberry) | Half-mile 230 kV transmission line and substation proposed by SRP to serve the data center, with Meta funding the cost of SRP's infrastructure | 2022-04-28 | announced From a public announcement. Plans can change. | Salt River Project |
| Meta's statement on paying utility costs | Meta says it pays the full cost of the energy its data center uses and the full cost of its water and wastewater service | 2026-10-02 | company-reported From the company's own published information. | Meta |
| Data center locations Meta owns worldwide | 30 | 2025-12-31 | verified | U.S. Securities and Exchange Commission |
| Measure | Value | As of | Basis | Source |
|---|---|---|---|---|
| Worldwide capital spending outlook for 2026, to support AI and core business | Approximately $130 billion to $145 billion | 2026-07-30 | projected A forward-looking estimate, not a measured result. | U.S. Securities and Exchange Commission |
| Reported purchase price of the 396-acre Mesa site (2021) | $123.2 million | 2021-01-01 | verified | KTAR News (Phoenix Business Journal) |
| Direct funding to Maricopa County-area schools and nonprofits | More than $2.4 million | 2026-10-02 | company-reported From the company's own published information. | Meta |
| Total support for the Mesa College Promise program at Mesa Community College | $300,000 | 2025-01-30 | company-reported From the company's own published information. | Meta |
| Revenue worldwide, 2025 | $200.97 billion | 2025-12-31 | verified | U.S. Securities and Exchange Commission |
| Measure | Value | As of | Basis | Source |
|---|---|---|---|---|
| Skilled trade workers on site at peak construction | An average of 2,000 at peak | 2025-01-30 | company-reported From the company's own published information. | Meta |
| Employees worldwide (headcount) | 75,472 | 2026-06-30 | verified | U.S. Securities and Exchange Commission |
| Worldwide headcount reduction, May 2026 | Approximately 8,000 employees | 2026-05-01 | verified | U.S. Securities and Exchange Commission |
| 2026 Community Action Grant recipients near the Mesa Data Center | STEM and technology grants to the Arizona Science Center, Queen Creek Unified School District, a Gilbert Public Schools junior high and Mesa Public Schools, among other recipients | 2026-10-02 | company-reported From the company's own published information. | Meta |
| Hardhat in Hand skilled trades training at the Mesa Data Center (launched 2022) | Paid, eight-week construction trades training program run with DPR Construction, the Maricopa County Community College District and the nonprofit Chicanos Por La Causa | 2022-08-16 | announced From a public announcement. Plans can change. | DPR Construction (via PR Newswire) |
| Measure | Value | As of | Basis | Source |
|---|---|---|---|---|
| City water allowance by project phase | 550 acre-feet per year for Phase 1; 1,100 for Phase 2 and 1,400 for Phase 3, if those phases are built | 2021-05-17 | verified | City of Mesa |
| Water credits the company must transfer to Mesa for the first phase | 5,500 acre-feet of long-term storage credits | 2021-05-17 | verified | City of Mesa |
| Mesa Data Center water withdrawal, 2024 | 57 megaliters | 2024-12-31 | company-reported From the company's own published information. | Meta |
| Water restoration commitment for the Mesa Data Center | Meta says it will restore 200% of the water the data center consumes to local watersheds and has supported 12 water restoration projects so far | 2026-10-02 | company-reported From the company's own published information. | Meta |
| Volumetric water benefits of Meta-funded Colorado River Basin projects tied to the Mesa Data Center, 2024 | 568.6 million gallons | 2024-12-31 | company-reported From the company's own published information. | Meta (prepared by LimnoTech) |
| Measure | Value | As of | Basis | Source |
|---|---|---|---|---|
| What Meta is | Technology company whose Family of Apps segment includes Facebook, Instagram, Messenger and WhatsApp, and whose Reality Labs segment covers virtual and augmented reality products | 2025-12-31 | verified | U.S. Securities and Exchange Commission |
| Ownership and headquarters | Public company listed on Nasdaq under the symbol META; principal executive offices at 1 Meta Way, Menlo Park, California | 2025-12-31 | verified | U.S. Securities and Exchange Commission |
| Company incorporated in Delaware | July 2004 | 2004-07-01 | verified | U.S. Securities and Exchange Commission |
| Facebook company rebrands as Meta | October 2021 | 2021-10-28 | verified | Meta |
| Mesa City Council vote on the data center agreements (May 17, 2021) | Resolution No. 11680 carried by majority vote; Vice Mayor Duff cast the only no vote, citing the project's water use | 2021-05-17 | verified | City of Mesa |
| Arizona Attorney General lawsuit against Meta over youth mental health (filed October 2023) | Arizona joined a multistate federal lawsuit alleging Meta designed features on Instagram and other platforms that addict children and teens | 2023-10-24 | verified | Arizona Attorney General's Office |
| Arizona's share of the multistate youth-safety settlement with Meta | Approximately $223 million | 2026-08-26 | announced From a public announcement. Plans can change. | Arizona Attorney General's Office |
| Foreign Trade Zone provision in Mesa's development agreement | On the company's request and at its cost, and subject to City Council approval, the city will support Foreign Trade Zone designation for the site within Foreign Trade Zone No. 221 | 2021-05-17 | verified | City of Mesa |
| Off-site infrastructure under Mesa's development agreement | The company must build and dedicate required off-site improvements at its own cost, including half-street improvements on Elliot, Ellsworth and Warner roads and Eastmark Parkway | 2021-05-17 | verified | City of Mesa |
Arizona AI does not currently read an online jobs board for Meta, so openings are best checked on the company's own website. Arizona AI does not collect applications or charge job seekers.
Meta's Mesa Data Center is at 3841 S. Ellsworth Road in Mesa, on a 396-acre site that the Phoenix Business Journal reported Meta acquired in 2021.
On January 30, 2025, Meta announced that the Mesa Data Center was serving traffic. As of January 2025, the first two buildings were operating and three more were under construction, with the second phase expected in 2026. The City of Mesa issued a temporary power permit for the campus's second phase in December 2025, and the Maricopa County Assessor listed the campus as partly complete for the 2027 tax year.
Meta's Mesa info sheet, as of October 2026, says its data center investment in Arizona is $1.2 billion. The info sheet does not say whether that figure is spent to date or the planned total.
In January 2025, Meta said the facility supported more than 200 operational jobs; its Mesa info sheet, as of October 2026, lists 200+ operational jobs supported once completed. Meta also said construction had an average of 2,000 skilled trade workers on site at peak. No source states how many people Meta employs in Arizona.
Salt River Project proposed Project Huckleberry, a half-mile 230 kV line and substation to serve the site, with Meta funding the cost; no source read confirmed when it entered service. SRP says the 300 MW Eleven Mile Solar Center in Pinal County provides power to the data center, and in December 2023 SRP announced a 50 MW allocation to Meta from the West Line Solar Facility in Eloy.
Meta reported 57 megaliters of water withdrawal at Mesa for 2024, before Meta announced in January 2025 that the site was serving traffic. Mesa's 2021 agreement for the site sets an annual water allowance of 550 acre-feet for the first phase, rising to 1,100 and 1,400 acre-feet if later phases are built.