The live tracker for Arizona's AI economy

Meta in Arizona

By Arizona AI · Profile reviewed · 46 sourced facts

At a glance

Meta Platforms, the company behind Facebook, Instagram, Messenger and WhatsApp, runs the Mesa Data Center in Mesa, Arizona, which Meta announced was serving traffic on January 30, 2025. Meta broke ground in Mesa in August 2021, and as of January 2025 the first two Mesa Data Center buildings were operating and three more were under construction. Meta's Mesa info sheet lists $1.2 billion of data center investment in Arizona. Salt River Project says its Eleven Mile Solar Center in Pinal County provides power to Meta's Mesa data center.

Key facts

Arizona location
Headquarters
Menlo Park, California
Ownership
Public company
Nasdaq: META
Website
meta.com

Sources: KTAR News (Phoenix Business Journal), U.S. Securities and Exchange Commission · Addresses open Google Maps in a new tab

Meta in Arizona: Key Developments

How does Meta fit into AI?

Modern AI runs on physical silicon, and that silicon passes through several hands before it ever answers a question. Here is the path, and where Meta sits on it. Stages not marked below are shown for context and are not claims about Meta.

  1. Chip design: Companies like Nvidia, Apple and AMD design the chips. Chip designers decide what a chip does and hand the blueprint to a factory. The three companies whose designs matter most to AI - Nvidia, Apple and AMD - do that work elsewhere, then send the designs to fabs. None of them owns a fab of its own.
  2. Wafer fabrication: Fabs print billions of transistors onto silicon wafers. A fab prints a design onto a polished disc of silicon called a wafer, layer by layer, until billions of transistors exist where there was blank material. It is the hardest and most expensive step in the chain, and the reason a single factory can cost tens of billions of dollars.
  3. Advanced packaging: Wafers are cut and assembled into finished chips. Packaging cuts a finished wafer into individual chips and assembles them, often stacking several pieces of silicon and memory into one component. For AI chips this step is nearly as demanding as fabrication, and a wafer is not a usable product until it is done.
  4. Servers and devices: Chips are built into AI servers, phones and PCs. Finished chips are assembled into the things people actually buy and deploy: data-center servers, phones, laptops. This is where a chip stops being a component and starts being a product.
  5. AI in use (here today): Data centers and devices run AI models on that silicon. Meta's Mesa Data Center is online as part of its global infrastructure. The end of the chain: models answering questions, generating images and driving software, running on the silicon every earlier step produced. Every AI service anyone uses is running on physical hardware somewhere, and that hardware started as a wafer.

Meta: AI in use (here today)

  • AI across Meta's apps (company-wide) (company-reported): Meta says its AI investments help power content ranking, recommendations, advertiser tools and new generative AI experiences across its products. Source: U.S. Securities and Exchange Commission
  • Meta AI assistant (company-wide) (company-reported): Meta AI is an assistant available across Meta's apps, as a stand-alone app, on its AI glasses and on the web. Source: U.S. Securities and Exchange Commission

About Meta

What Meta does

Company-wide, Meta reports two segments: Family of Apps, which includes Facebook, Instagram, Messenger and WhatsApp, and Reality Labs, which covers virtual and augmented reality products. It was incorporated in Delaware in July 2004, introduced the Meta company brand in October 2021, and has its principal executive offices in Menlo Park, California; SRP and DPR Construction documents from 2022 refer to it as Meta (formerly Facebook).

Meta owns 30 data center locations worldwide.

In Arizona

Mesa campus: Meta Platforms, the company behind Facebook, Instagram, Messenger and WhatsApp, runs the Mesa Data Center at 3841 S. Ellsworth Road in Mesa, which has been serving traffic since January 2025. As of January 2025 the first two buildings were operating and three more were under construction, with the second phase expected in 2026. The City of Mesa issued a temporary power permit for the campus's second phase in December 2025, and the Maricopa County Assessor listed the campus as partly complete for the 2027 tax year. Meta's Mesa info sheet, as of October 2026, lists $1.2 billion of data center investment in Arizona without saying whether that figure is spent to date or the planned total.

In May 2021 the City of Mesa considered agreements with Redale LLC covering approximately 396 acres at the southeast corner of Elliot and Ellsworth roads. City documents name the developer as Redale LLC, which Data Center Dynamics reported was the name Facebook used while negotiating the project.

  • The Mesa City Council approved the item on May 17, 2021, with Vice Mayor Duff casting the only no vote and opposing a mega data center on 396 acres over its water use.
  • The Phoenix Business Journal reported that Meta acquired its 396-acre site in 2021 for $123.2 million.
  • Data Center Dynamics, citing the Phoenix Business Journal, reported in February 2023 that Meta had sold about 15 acres in Mesa, likely part of the site, to EdgeCore for about $1.2 million.

Meta broke ground in Mesa in August 2021, and in May 2022 it announced three more buildings, describing a planned campus of more than 2.5 million square feet. The city agreement allows up to 3 million square feet.

On January 30, 2025, Meta announced that the Mesa Data Center was serving traffic. As of January 2025, the first two buildings were operating, three more were under construction and the second phase was expected in 2026. The City of Mesa issued a temporary power permit for the campus's second phase in December 2025, and the Maricopa County Assessor listed the campus as partly complete for the 2027 tax year.

In January 2025, Meta said the facility supported more than 200 operational jobs; its Mesa info sheet, as of October 2026, lists 200+ operational jobs supported once completed. Meta also said construction drew an average of 2,000 skilled trade workers on site at peak. Meta describes these as jobs the facility supports and does not say how many are Meta employees; no source states how many people Meta employs in Arizona.

In its January 2025 announcement, Meta describes the Mesa site as part of the global infrastructure that brings its technologies and services to life; the announcement does not say which workloads run there.

Power infrastructure: Salt River Project proposed Project Huckleberry, a half-mile 230 kV transmission line and substation to serve the data center, with Meta funding the cost of that infrastructure. The Arizona Corporation Commission approved the project's Certificate of Environmental Compatibility at its August 16, 2022 open meeting. No source read confirmed when the line entered service.

In October 2024 SRP celebrated the official commencement of the Eleven Mile Solar Center in Pinal County, a 300 MW solar project with a 300 MW / 1,200 MWh battery system that SRP says provides power to Meta's Mesa data center. In December 2023, SRP announced an allocation to Meta of 50 MW from the West Line Solar Facility in Eloy plus a portion of the Brittlebush Solar Facility in Coolidge; no source read confirms the size of the Brittlebush allocation or when it began. In January 2025 Meta said three Meta-supported SRP projects were adding 450 MW of new renewable energy in Arizona.

Water and electricity: Under Mesa's 2021 agreement for the site, the annual water allowance is 550 acre-feet for the first phase, rising to 1,100 and 1,400 acre-feet if later phases are built, and the company must assign 5,500 acre-feet of long-term storage credits to Mesa. Meta reported 24,657 MWh of electricity use and 57 megaliters of water withdrawal at Mesa for 2024, before Meta announced in January 2025 that the site was serving traffic. Meta says it pays the full cost of the energy and the water and wastewater service its data center uses, and that it will restore 200% of the water the data center consumes to local watersheds; its info sheet, as of October 2026, says it has supported 12 water restoration projects so far.

Locally, Meta says it has provided more than $2.4 million in direct funding to Maricopa County-area schools and nonprofits, and says its total support for the Mesa College Promise program at Mesa Community College reached $300,000 with a $225,000 grant announced in January 2025. In August 2022, DPR Construction announced that it and Meta were bringing Meta's paid, eight-week Hardhat in Hand skilled trades training program to the Mesa site; no source says whether the program is still running.

Taken together, the facts show a large data center campus in Mesa that began serving traffic in January 2025 and, as of January 2025, was partly built, with a dedicated SRP line and substation proposed for the site in 2022 whose in-service date no source confirmed, solar power that SRP says serves it, and city water allowances set by a 2021 agreement.

Role in AI and technology

Company-wide, Meta says its AI investments help power content ranking, recommendations, advertiser tools and new generative AI experiences, and in its July 2026 filing it projects capital expenditures of approximately $130 billion to $145 billion in 2026 to support its AI efforts and core business. The filing gives no Arizona breakdown of that spending, so Arizona AI does not attribute it to Mesa.

Arizona AI found no source stating the Mesa campus's role in Meta's AI work, and no source states an Arizona employee count.

Controversies and Issues

2023 state lawsuit over teen social media features, settled 2026: In October 2023 Arizona and dozens of other states sued Meta, alleging that it purposely addicted children and teens to its social media platforms. On August 26, 2026 the Arizona Attorney General announced a multistate settlement under which Arizona will receive approximately $223 million, and the federal court in Oakland, California approved the deal the same day. Meta has denied the allegations. The case concerns Meta's social media products, not its Mesa data center.

2026 workforce reduction, company-wide: Meta told employees in April 2026 it would cut roughly 8,000 jobs, about 10 percent of its workforce, and its quarterly report for the period ended September 30, 2026 records a May 2026 headcount reduction of approximately 8,000 employees.

Research

Papers from the past 12 months in Arizona AI's research catalog with an author affiliated with Meta, as indexed by OpenAlex. Company authors may work outside Arizona.

Browse research

Meta in Arizona: By the Numbers

Each figure is dated and linked to its source. Figures that are company-reported, announced, or projected rather than measured are labeled.

  • Meta's stated data center investment in Arizona: $1.2 billion (company-reported)
  • Planned Mesa campus size after the 2022 expansion: More than 2.5 million sq ft (announced)
  • Operational jobs supported at the Mesa Data Center: More than 200 (company-reported)
  • Data center site at Elliot and Ellsworth roads, Mesa: Approximately 396 acres
  • New renewable energy in Arizona from Meta-supported SRP projects: 450 MW (company-reported)

The Arizona build-out, 2004 to 2025

  • 2004: Company incorporated in Delaware
  • 2021: Facebook announces and breaks ground on its Mesa data center
  • 2021: Facebook company rebrands as Meta
  • 2022: Meta announces three more buildings for the Mesa campus
  • 2025: Mesa Data Center: mesa Data Center begins serving traffic

Meta Mesa Data Center, Arizona

MeasureValueAs ofBasisSource
Address3841 S. Ellsworth Road, Mesa, AZ 852122026-10-28verifiedKTAR News (Phoenix Business Journal)
RoleData center serving traffic for Meta's technologies and services as part of its global infrastructure2025-01-30verifiedMeta
StatusFirst two buildings operating; three more data center buildings under construction, with the second phase expected in 2026 (as of January 2025)2025-01-31verifiedKTAR News (Phoenix Business Journal)
Phase two temporary power permitIssued December 2, 2025 (City of Mesa permit PMT23-14327)2025-12-02verifiedCity of Mesa Open Data
Planned campus layoutFive-building campus2022-08-23announced From a public announcement. Plans can change.DPR Construction
Mesa Data Center begins serving trafficJanuary 20252025-01-30verifiedMeta

Facilities

MeasureValueAs ofBasisSource
Facebook announces and breaks ground on its Mesa data centerAugust 20212021-08-12verifiedMeta
Meta announces three more buildings for the Mesa campusMay 20222022-05-04announced From a public announcement. Plans can change.Meta
Maximum build-out authorized under Mesa's development agreementUp to 3 million sq ft2021-05-17verifiedCity of Mesa
Mesa Data Center electricity consumption, 202424,657 MWh2024-12-31company-reported From the company's own published information.Meta
Eleven Mile Solar Center, a Pinal County power source for the Mesa data center300 MW solar project with a 300 MW / 1,200 MWh battery system; operating since October 20242024-10-11verifiedSalt River Project
Other SRP solar allocations for the Mesa data center50 MW from the 100 MW West Line Solar Facility in Eloy, plus a portion of the 200 MW Brittlebush Solar Facility in Coolidge2023-12-11announced From a public announcement. Plans can change.Salt River Project
Dedicated SRP power line and substation (Project Huckleberry)Half-mile 230 kV transmission line and substation proposed by SRP to serve the data center, with Meta funding the cost of SRP's infrastructure2022-04-28announced From a public announcement. Plans can change.Salt River Project
Meta's statement on paying utility costsMeta says it pays the full cost of the energy its data center uses and the full cost of its water and wastewater service2026-10-02company-reported From the company's own published information.Meta
Data center locations Meta owns worldwide302025-12-31verifiedU.S. Securities and Exchange Commission

Investment

MeasureValueAs ofBasisSource
Worldwide capital spending outlook for 2026, to support AI and core businessApproximately $130 billion to $145 billion2026-07-30projected A forward-looking estimate, not a measured result.U.S. Securities and Exchange Commission
Reported purchase price of the 396-acre Mesa site (2021)$123.2 million2021-01-01verifiedKTAR News (Phoenix Business Journal)
Direct funding to Maricopa County-area schools and nonprofitsMore than $2.4 million2026-10-02company-reported From the company's own published information.Meta
Total support for the Mesa College Promise program at Mesa Community College$300,0002025-01-30company-reported From the company's own published information.Meta
Revenue worldwide, 2025$200.97 billion2025-12-31verifiedU.S. Securities and Exchange Commission

Workforce

MeasureValueAs ofBasisSource
Skilled trade workers on site at peak constructionAn average of 2,000 at peak2025-01-30company-reported From the company's own published information.Meta
Employees worldwide (headcount)75,4722026-06-30verifiedU.S. Securities and Exchange Commission
Worldwide headcount reduction, May 2026Approximately 8,000 employees2026-05-01verifiedU.S. Securities and Exchange Commission
2026 Community Action Grant recipients near the Mesa Data CenterSTEM and technology grants to the Arizona Science Center, Queen Creek Unified School District, a Gilbert Public Schools junior high and Mesa Public Schools, among other recipients2026-10-02company-reported From the company's own published information.Meta
Hardhat in Hand skilled trades training at the Mesa Data Center (launched 2022)Paid, eight-week construction trades training program run with DPR Construction, the Maricopa County Community College District and the nonprofit Chicanos Por La Causa2022-08-16announced From a public announcement. Plans can change.DPR Construction (via PR Newswire)

Water and environment

MeasureValueAs ofBasisSource
City water allowance by project phase550 acre-feet per year for Phase 1; 1,100 for Phase 2 and 1,400 for Phase 3, if those phases are built2021-05-17verifiedCity of Mesa
Water credits the company must transfer to Mesa for the first phase5,500 acre-feet of long-term storage credits2021-05-17verifiedCity of Mesa
Mesa Data Center water withdrawal, 202457 megaliters2024-12-31company-reported From the company's own published information.Meta
Water restoration commitment for the Mesa Data CenterMeta says it will restore 200% of the water the data center consumes to local watersheds and has supported 12 water restoration projects so far2026-10-02company-reported From the company's own published information.Meta
Volumetric water benefits of Meta-funded Colorado River Basin projects tied to the Mesa Data Center, 2024568.6 million gallons2024-12-31company-reported From the company's own published information.Meta (prepared by LimnoTech)

Other

MeasureValueAs ofBasisSource
What Meta isTechnology company whose Family of Apps segment includes Facebook, Instagram, Messenger and WhatsApp, and whose Reality Labs segment covers virtual and augmented reality products2025-12-31verifiedU.S. Securities and Exchange Commission
Ownership and headquartersPublic company listed on Nasdaq under the symbol META; principal executive offices at 1 Meta Way, Menlo Park, California2025-12-31verifiedU.S. Securities and Exchange Commission
Company incorporated in DelawareJuly 20042004-07-01verifiedU.S. Securities and Exchange Commission
Facebook company rebrands as MetaOctober 20212021-10-28verifiedMeta
Mesa City Council vote on the data center agreements (May 17, 2021)Resolution No. 11680 carried by majority vote; Vice Mayor Duff cast the only no vote, citing the project's water use2021-05-17verifiedCity of Mesa
Arizona Attorney General lawsuit against Meta over youth mental health (filed October 2023)Arizona joined a multistate federal lawsuit alleging Meta designed features on Instagram and other platforms that addict children and teens2023-10-24verifiedArizona Attorney General's Office
Arizona's share of the multistate youth-safety settlement with MetaApproximately $223 million2026-08-26announced From a public announcement. Plans can change.Arizona Attorney General's Office
Foreign Trade Zone provision in Mesa's development agreementOn the company's request and at its cost, and subject to City Council approval, the city will support Foreign Trade Zone designation for the site within Foreign Trade Zone No. 2212021-05-17verifiedCity of Mesa
Off-site infrastructure under Mesa's development agreementThe company must build and dedicate required off-site improvements at its own cost, including half-street improvements on Elliot, Ellsworth and Warner roads and Eastmark Parkway2021-05-17verifiedCity of Mesa

Sources

Meta Jobs in Arizona (0 open)

Meta in Arizona: Common Questions

How do I apply for a job at Meta in Arizona?

Arizona AI does not currently read an online jobs board for Meta, so openings are best checked on the company's own website. Arizona AI does not collect applications or charge job seekers.

Where is Meta's data center in Arizona?

Meta's Mesa Data Center is at 3841 S. Ellsworth Road in Mesa, on a 396-acre site that the Phoenix Business Journal reported Meta acquired in 2021.

When did the Meta Mesa data center open?

On January 30, 2025, Meta announced that the Mesa Data Center was serving traffic. As of January 2025, the first two buildings were operating and three more were under construction, with the second phase expected in 2026. The City of Mesa issued a temporary power permit for the campus's second phase in December 2025, and the Maricopa County Assessor listed the campus as partly complete for the 2027 tax year.

How much has Meta invested in Arizona?

Meta's Mesa info sheet, as of October 2026, says its data center investment in Arizona is $1.2 billion. The info sheet does not say whether that figure is spent to date or the planned total.

How many jobs does the Meta data center in Mesa have?

In January 2025, Meta said the facility supported more than 200 operational jobs; its Mesa info sheet, as of October 2026, lists 200+ operational jobs supported once completed. Meta also said construction had an average of 2,000 skilled trade workers on site at peak. No source states how many people Meta employs in Arizona.

Where does Meta's Mesa data center get its power?

Salt River Project proposed Project Huckleberry, a half-mile 230 kV line and substation to serve the site, with Meta funding the cost; no source read confirmed when it entered service. SRP says the 300 MW Eleven Mile Solar Center in Pinal County provides power to the data center, and in December 2023 SRP announced a 50 MW allocation to Meta from the West Line Solar Facility in Eloy.

How much water does the Meta data center in Mesa use?

Meta reported 57 megaliters of water withdrawal at Mesa for 2024, before Meta announced in January 2025 that the site was serving traffic. Mesa's 2021 agreement for the site sets an annual water allowance of 550 acre-feet for the first phase, rising to 1,100 and 1,400 acre-feet if later phases are built.