Proposed data center in West of Houghton Road, north of the Pima County Fairgrounds (approximate). Being developed by Beale Infrastructure.
This is a proposed or under-construction project. It is not operating capacity, and announced projects do sometimes change scope or fail to proceed.
Capacity: Figure reported in the press: power the utility has agreed to supply, one phase. Tucson Electric Power supply by 2028, reported August 2025.
Per-facility headcount is not published here: no reliable public figures exist for these sites, and construction announcements are not permanent employment. Beale Infrastructure is developing this site rather than operating it, so any long-term operator has not been established here.
Stories in Arizona AI's news feed that name this facility, newest first.
Compiled from public records and checked on 2026-10-07. Confidence in this record: high. Blank figures mean the number is not publicly established, not that it is zero.
Each statement on this page is listed with the page it came from and the words that say it. Sources open in a new tab.
Status: Proposed
Note: A news report in April 2026 said work was underway with several permits under review.
Work is underway on the proposed Project Blue data center, located just north of the Pima County Fairgrounds.
on the development of the project that has several permits under review.
The first building could be operational as soon as 2027.
Utility power supply for one phase: 286 MW
Note: This is power the utility said it will supply by 2028, not a built figure.
The application to the Arizona Corporation Commission says TEP will provide 286 megawatts of capacity by 2028.
Data Center Project Under Contract Project Blue Phase 1: 286 MW
Land: 290 acres
Project Blue is located on a 290-acre parcel immediately north of the Pima County Fairgrounds
Expected: 2027
Note: Pima County says the first building could be operational as soon as 2027.
The first building could be operational as soon as 2027.
Location: West of Houghton Road, north of the Pima County Fairgrounds (approximate)
Its proposed location is west of Houghton Road, north of the Pima County Fairgrounds.
Project Blue is located on a 290-acre parcel immediately north of the Pima County Fairgrounds
The land transaction for the project, which Beale Infrastructure is developing, closed in December 2025 and work was under way in April 2026.
$20.85 million from the project's land transaction that closed on December 24, 2025
Work is underway on the proposed Project Blue data center, located just north of the Pima County Fairgrounds.
Blue Owl-owned Beale Infrastructure is developing the project.
Pima County says the first phase could support four buildings and up to 10 at full build-out.
The beginning phase of the project could support four data center buildings, with the full property potentially supporting up to 10 buildings.
The Arizona Corporation Commission approved the power supply agreement, Data Center Dynamics reported in December 2025.
The Arizona Corporation Commission has approved an energy-supply agreement between local utility Tucson Electric Power (TEP) and the company behind Project Blue
Reports suggest 600 MW at full build-out.
Reports suggest up to ten buildings totaling 2 million sq ft (185,805 sqm), with a capacity of 600MW at full build-out