The Luckett Road Data Center Campus is a proposed data center campus by Beale Infrastructure on about 600 acres on Luckett Road in Marana. The Marana Town Council approved the rezoning applications on January 6, 2026.
Proposed data center in Luckett Road, Marana. Being developed by Beale Infrastructure.
Chamber Business News reported on October 1, 2026 that a three-judge appeals court panel unanimously affirmed the Superior Court judgment for the Town of Marana, leaving the Town Council's January zoning approvals in place. The town says it does not currently know the identity of the future occupant. Tucson Agenda reported in May 2026 that Fremont Peak Properties, the Beale Infrastructure subsidiary that submitted the proposals, had contracts with the Church of Jesus Christ of Latter-day Saints and the Kai Family Trust to buy the two 300-acre parcels.

Outlined in yellow: Parcels 208-08-004A and 208-09-001E, identified in Marana's Luckett Road North and South specific plans for the proposed data center campus. It shows the land, not where buildings would go. Parcels: Town of Marana, Luckett Road North and South project page, linking the separate specific plans. Shapes: Pima County GIS (read November 8, 2026).
Capacity: Figure reported in the press: expected electricity demand, at full build-out. Reported January 2026.
Per-facility headcount is not published here: no reliable public figures exist for these sites, and construction announcements are not permanent employment. Beale Infrastructure is developing this site rather than operating it, so any long-term operator has not been established here.
Stories in Arizona AI's news feed that name this facility, newest first.
Compiled from public records and checked on 2026-11-13. Confidence in this record: high. Blank figures mean the number is not publicly established, not that it is zero.
Each statement on this page is listed with the page it came from and the words that say it. Sources open in a new tab.
Status: Rezoning approved
The applications were presented before the Town Council at public hearings on January 6, 2026, and were approved.
The proposed project involves the development of a data center campus on approximately 600 acres in Marana.
The Town does not currently know the identity of the future occupant.
Expected power demand at full build-out: 1.5 GW
Note: Developer representatives said it could mean up to 1500 megawatts.
According to Beale reps, this could mean up to 1500 megawatts of power that would be supplied by Trico Electric Co-op and Tucson Electric Power.
The estimated electrical demand ranges between 550 and 750 megawatts for each site.
Land: 600 acres
Note: The town's project page gives approximately 600 acres for the campus, and a town map printed by the Tucson Spotlight totals 661.2 acres for the proposed project area. No source explains the difference.
The proposed project involves the development of a data center campus on approximately 600 acres in Marana.
Location: Luckett Road, Marana
The proposed project involves the development of a data center campus on approximately 600 acres in Marana.
Chamber Business News reported on October 1, 2026 that a three-judge appeals court panel unanimously affirmed the Superior Court judgment for the Town of Marana, leaving the Town Council's January zoning approvals in place.
The three-judge panel unanimously affirmed the Superior Court’s judgment in favor of the Town of Marana. [...] The decision affirms an earlier Pima County Superior Court ruling and leaves the Marana Town Council’s January zoning approvals in place.
The town says it does not currently know the identity of the future occupant.
The Town does not currently know the identity of the future occupant.
Tucson Agenda reported in May 2026 that Fremont Peak Properties, the Beale Infrastructure subsidiary that submitted the proposals, had contracts with the Church of Jesus Christ of Latter-day Saints and the Kai Family Trust to buy the two 300-acre parcels.
Fremont Peak Properties has contracts with the Church of Jesus Christ of Latter-day Saints and the Kai Family Trust to buy the two 300-acre parcels.
submitted the project proposals on behalf of its subsidiary, Fremont Peak Properties LLC, in October 2025 according to a Beale spokesperson.
The Town of Marana approved rezoning for about 600 acres on January 6, 2026, after Beale Infrastructure, through its subsidiary Fremont Peak Properties, applied in October 2025.
The applications were presented before the Town Council at public hearings on January 6, 2026, and were approved.
The proposed project involves the development of a data center campus on approximately 600 acres in Marana.
submitted the project proposals on behalf of its subsidiary, Fremont Peak Properties LLC, in October 2025 according to a Beale spokesperson.
on behalf of Beale Infrastructure - the same company developing Project Blue.
The town says the future occupant is unknown and puts each of two sites at 550 to 750 MW.
The Town does not currently know the identity of the future occupant.
The estimated electrical demand ranges between 550 and 750 megawatts for each site.
The Tucson Spotlight reported that the Marana Town Council voted 6-0 to rezone 661 acres of agricultural land for a large data center development, and that one council member did not attend the January 6 meeting or vote after declaring a conflict of interest related to partial ownership of the southern parcel.
the Marana Town Council voted 6–0 Tuesday to rezone 661 acres of agricultural land for a large data center development.
did not attend the Jan. 6 meeting or vote after declaring a conflict of interest related to partial ownership of the southern parcel.
The Tucson Spotlight printed a Town of Marana map of the proposed project area, totaling 661.2 acres.
A map of the proposed project area, totaling 661.2 acres. Courtesy of Town of Marana
Arizona Luminaria reported that one parcel is owned by the Kai Family Trust and the other by the Church of Jesus Christ of Latter-day Saints, and Tucson Agenda reported that Fremont Peak Properties has contracts with both to buy the two 300-acre parcels.
One owned by the Kai Family Trust and the other by the Church of Jesus Christ of Latter-day Saints
Fremont Peak Properties has contracts with the Church of Jesus Christ of Latter-day Saints and the Kai Family Trust to buy the two 300-acre parcels.
The Tucson Spotlight reported that Trico Electric Cooperative will provide the north site with 550 to 750 megawatts of power and Tucson Electric Power a matching amount to the southern portion, and that the facility has been proposed as air-cooled because Marana town code prohibits the use of potable water for cooling systems.
Trico Electric Cooperative will provide the north site with 550 to 750 megawatts of power, and Tucson Electric Power will provide a matching amount to the southern portion.
Because Marana town code prohibits the use of potable water for cooling systems, the facility has been proposed as air-cooled.
The Tucson Spotlight reported that the Town of Marana said the project would create about 4,500 temporary construction jobs and approximately 400 permanent jobs once operational.
The town of Marana said the data center project would create about 4,500 temporary construction jobs and approximately 400 permanent jobs once operational.
Arizona Luminaria reported on January 8, 2026 that a presentation on Tuesday promised $5 billion in capital investment, $145 million in town tax revenue and 4,200 construction jobs.
The presentation by Silvyn on Tuesday promised $5 billion in capital investment, $145 million in town tax revenue and 4,200 construction jobs.
AZPM reported in February 2026 that Marana residents had sued the town for rejecting the petitions, and on March 24, 2026 that a subsidiary of Beale Infrastructure was suing the town for not allowing petitioners to withdraw their requests to put the data center on the ballot.
Marana residents have filed a lawsuit against the Town of Marana for rejecting petitions that could put a proposed data center on a ballot.
A subsidiary of Beale Infrastructure – the company developing two data centers in Pima County – is suing the Town of Marana for not allowing petitioners to withdraw their requests to put a data center on the ballot.