CyrusOne Chandler Campus (PHX1-PHX8)

Operating data center in 2305 to 2705 S Ellis St, Chandler. Operated by CyrusOne.

  • Capacity for the whole campus: 169 MW
  • Land: 85 acres
  • Online since: 2012

Capacity: Operator's own figure: computing (IT) load, whole campus. CyrusOne: total IT capacity.

Working here

Per-facility headcount is not published here: no reliable public figures exist for these sites, and construction announcements are not permanent employment. Open Arizona roles at this operator, where there are any, are listed on the operator's company page.

Other CyrusOne facilities in Arizona

How we know this

Compiled from public records and checked on 2026-10-07. Confidence in this record: high. Blank figures mean the number is not publicly established, not that it is zero.