Proposed data center in South Crismon Road north of Elliot Road, Mesa. Operated by CyrusOne.
This is a proposed or under-construction project. It is not operating capacity, and announced projects do sometimes change scope or fail to proceed.
Capacity: Figure reported in the press: computing (IT) load, at full build-out. CyrusOne's 2018 plan, reported by In Business Magazine.
Per-facility headcount is not published here: no reliable public figures exist for these sites, and construction announcements are not permanent employment. Open Arizona roles at this operator, where there are any, are listed on the operator's company page.
Compiled from public records and checked on 2026-10-07. Confidence in this record: high. Blank figures mean the number is not publicly established, not that it is zero.
Each statement on this page is listed with the page it came from and the words that say it. Sources open in a new tab.
Status: Proposed
Note: The newest source for this plan is from August 2024.
2024-07-24T00:00:00 0 153 Planning and Zoning Board - Public Hearing
CyrusOne's data center campus. The former passed unanimously, while the latter passed 4-3.
up to five two-story buildings, spanning 286,530 square feet (26,620 sqm) each, for a total of around 1.4 million sq ft
Capacity at full build-out: 198 MW
Note: This is the planned maximum from a 2018 announcement.
is planned to have five building facilities with up to 198 MW of critical power
Floor area: 1.4M sq ft
Note: This is the planned total for up to five buildings, reported in 2024.
up to five two-story buildings, spanning 286,530 square feet (26,620 sqm) each, for a total of around 1.4 million sq ft
Land: 67 acres
Located north of Elliot Road and west of Crismon Road. (67± acres).
Location: South Crismon Road north of Elliot Road, Mesa
Within the 3200 to 3400 blocks of South Crismon Road (west side)
Located north of Elliot Road and west of Crismon Road.
CyrusOne announced in June 2018 that it had bought about 68 acres in Mesa and planned up to 198 MW of critical power there.
today announced it purchased 68.227 acres in Mesa, Arizona for the development of a new data center cloud campus
is planned to have five building facilities with up to 198 MW of critical power
Mesa's Planning and Zoning Board held a public hearing on July 24, 2024, on the CyrusOne site on South Crismon Road. Data Center Dynamics reported a 4-3 vote in favor of the campus, where CyrusOne aims to build up to five two-story buildings of about 1.4 million sq ft in all.
2024-07-24T00:00:00 0 153 Planning and Zoning Board - Public Hearing
Within the 3200 to 3400 blocks of South Crismon Road (west side)
CyrusOne's data center campus. The former passed unanimously, while the latter passed 4-3.
up to five two-story buildings, spanning 286,530 square feet (26,620 sqm) each, for a total of around 1.4 million sq ft
CyrusOne's current location list shows only Chandler under Arizona.
Arizona Chandler, AZ, PHX1-PHX8 Illinois Aurora, IL, CHI1-CHI3 Sangamon County, IL In Development