Proposed data center in Southeast corner of Attaway Road and Judd Road, Florence. Being developed by Ryan Companies.
This is a proposed or under-construction project. It is not operating capacity, and announced projects do sometimes change scope or fail to proceed.
Per-facility headcount is not published here: no reliable public figures exist for these sites, and construction announcements are not permanent employment. Ryan Companies is developing this site rather than operating it, so any long-term operator has not been established here.
Compiled from public records and checked on 2026-10-23. Confidence in this record: medium. Blank figures mean the number is not publicly established, not that it is zero.
Each statement on this page is listed with the page it came from and the words that say it. Sources open in a new tab.
Status: Proposed
Town Council approved the adoption Ordinance No. 768-25 by a vote of 7-0.
Ryan Companies and EdgeCore are hoping to develop a new data center and industrial campus in the town of Florence in Pinal County.
Land: 780 acres
the approximately 780-acre property located at the southeast corner of Attaway Road and Judd Road
Location: Southeast corner of Attaway Road and Judd Road, Florence
the approximately 780-acre property located at the southeast corner of Attaway Road and Judd Road
On October 7, 2025, the Florence Town Council approved, 7 to 0, a general plan amendment and a planned unit development amendment for the Florence Tech Park at Dobson Farms, about 780 acres at the southeast corner of Attaway Road and Judd Road, changing its general plan designation from suburban neighborhood to industrial.
Town Council (TC) Regular Session - (Tuesday, October 7th / 6:00 pm / Town Hall Council Chambers)
Town Council approved the adoption Ordinance No. 768-25 by a vote of 7-0.
Town Council approved the adoption Ordinance No. 769-25 by a vote of 7-0.
the approximately 780-acre property located at the southeast corner of Attaway Road and Judd Road
from the Suburban Neighborhood Place Type to the Industrial Place Type
The town's Planning and Zoning Commission had recommended both, 4 to 0, on September 18, 2025.
carried by a 4-0 vote, to forward a recommendation of approval to the Town Council
A trade report says Ryan Companies made the request, with a concept plan of two Salt River Project substations, two office buildings and ten industrial pads in two phases.
The first request from Ryan Companies would change the designation of 780 acres
would include a Salt River Project substation, two office buildings and five industrial pads
The second phase would have another SRP substation and five more industrial pads.
Press reports tie EdgeCore to data centers on the Dobson Farms land but disagree on the size: Data Center Dynamics, citing planning documents, reports up to ten buildings of 72 MW each, while Connect CRE reports one 72 MW project on 750 acres with Ryan Companies as the developer.
Documents suggest the EdgeCore portion of the project could include ten two-story data centers, each totaling 332,100 sq ft (30,855 sqm) and 72MW
EdgeCore is just a vote away from building a 72 megawatt data center in the Arizona rural town of Florence
The project, on 750 acres, will include 332,000 square feet of space across 10 two-story buildings.
Ryan Companies is listed as the developer.
Data Center Dynamics also reports that Ryan Companies' own application could include five data centers.
Documents in Ryan Companies’ applications said its part of the project could total five data centers, two office buildings, and a general industrial building
In July 2026 KJZZ reported that Florence had no data centers and was forming an advisory committee for data center proposals.
This Arizona town doesn't have data centers. But they want to be ready for proposals
The town is currently accepting applications for a data center ad hoc committee.
These remarks are Arizona AI's own. They say how this record is counted or what we could not find, so there is no outside page to link.
Arizona AI shows no power figure because the published reports disagree by a factor of ten and it found no figure published by the developer or the town. Arizona AI has not established which part of the Dobson Farms land EdgeCore's plans cover, and found no site plan, building permit or construction for a data center here.