Proposed data center in Estrella Road and Houser Road, Eloy. Being developed by Ryan Companies.
This is a proposed or under-construction project. It is not operating capacity, and announced projects do sometimes change scope or fail to proceed.
Capacity: Figure reported in the press: at full build-out. Reported January 2025. The source does not say what the figure measures.
Per-facility headcount is not published here: no reliable public figures exist for these sites, and construction announcements are not permanent employment. Ryan Companies is developing this site rather than operating it, so any long-term operator has not been established here.
Compiled from public records and checked on 2026-10-07. Confidence in this record: high. Blank figures mean the number is not publicly established, not that it is zero.
Each statement on this page is listed with the page it came from and the words that say it. Sources open in a new tab.
Status: Proposed
Note: The newest press source is from January 2025. Only a listing site is more recent.
was recommended for approval by the Eloy Planning and Zoning Commission in its Jan. 15 meeting.
developing a 400MW, 1.25 million sq ft (116,130 sqm) campus, known as the Southwest Crossing Data Center.
Ryan Companies: Southwest Crossing Year Planned: 2027 Lot Size: 122 acres
Capacity at full build-out: 400 MW
three-building data center development with more than 855KSF of building area and a 400-megawatt capacity.
developing a 400MW, 1.25 million sq ft (116,130 sqm) campus, known as the Southwest Crossing Data Center.
Floor area: 1.3M sq ft
Note: The source gives this as the size of the campus. AZBEX reports more than 855,000 sq ft of building area.
developing a 400MW, 1.25 million sq ft (116,130 sqm) campus, known as the Southwest Crossing Data Center.
Land: 122 acres
The greenfield site, totaling 122 acres on the southeast corner of Estrella Road & Houser Road
Ryan Companies: Southwest Crossing Year Planned: 2027 Lot Size: 122 acres
Location: Estrella Road and Houser Road, Eloy
The greenfield site, totaling 122 acres on the southeast corner of Estrella Road & Houser Road
was recommended for approval by the Eloy Planning and Zoning Commission in its Jan. 15 meeting.
Eloy's Planning and Zoning Commission recommended rezoning in January 2025 for a 400 MW campus at the southeast corner of Estrella Road and Houser Road.
was recommended for approval by the Eloy Planning and Zoning Commission in its Jan. 15 meeting.
developing a 400MW, 1.25 million sq ft (116,130 sqm) campus, known as the Southwest Crossing Data Center.
The greenfield site, totaling 122 acres on the southeast corner of Estrella Road & Houser Road