Proposed data center in W Camelback Rd, Glendale (Litchfield Park mailing address). Operated by QTS.
This is a proposed or under-construction project. It is not operating capacity, and announced projects do sometimes change scope or fail to proceed.
Capacity: Figure reported in the press: computing (IT) load, at full build-out. QTS website figure, reported May 2024.
Per-facility headcount is not published here: no reliable public figures exist for these sites, and construction announcements are not permanent employment. Open Arizona roles at this operator, where there are any, are listed on the operator's company page.
Compiled from public records and checked on 2026-10-07. Confidence in this record: high. Blank figures mean the number is not publicly established, not that it is zero.
Each statement on this page is listed with the page it came from and the words that say it. Sources open in a new tab.
Status: Proposed
Phoenix 3 Glendale, Arizona In Development
QTS’s Phoenix 3 data center campus in Glendale, Arizona, will offer one of the most flexible, efficient solutions in the region
QTS Glendale AZ Latest Podcast 17501 W Bethany Home Rd Planned Future facility in planning stage
Capacity at full build-out: 750 MW
Note: This is the planned capacity of the full campus, as reported in May 2024.
QTS’ website says the 375-acre campus will offer 750MW of critical capacity.
Floor area: 3.0M sq ft
Note: The source gives around 3 million sq ft as the planned total for 16 buildings.
The Blackstone-owned company aims to develop 16 buildings - each around 180,000 sq ft (16,720 sqm)- totaling around 3 million sq ft
Land: 375 acres
Note: A May 2024 report says the QTS website gave 375 acres. AZBEX reported 391 acres.
QTS’ website says the 375-acre campus will offer 750MW of critical capacity.
Location: W Camelback Rd, Glendale (Litchfield Park mailing address)
PHX 3 DC1 - 17408 W. Camelback Rd, Litchfield Park, Arizona 85340
QTS’s Phoenix 3 data center campus in Glendale, Arizona, will offer one of the most flexible, efficient solutions in the region
QTS bought the site on W. Camelback Road in July 2022 and filed for 16 buildings of about 180,000 sq ft each, to be built in phases over several years.
The company acquired the site in July 2022 for $255.3 million.
The Blackstone-owned company aims to develop 16 buildings - each around 180,000 sq ft (16,720 sqm)
The project, which is expected to take years to build, will be done in multiple phases.
PHX 3 DC1 - 17408 W. Camelback Rd, Litchfield Park, Arizona 85340
QTS lists the campus as in development and describes it in the future tense.
Phoenix 3 Glendale, Arizona In Development
QTS’s Phoenix 3 data center campus in Glendale, Arizona, will offer one of the most flexible, efficient solutions in the region