Proposed data center in 10464 E Pecos Rd, Mesa. Operated by Amazon Web Services.
This is a proposed or under-construction project. It is not operating capacity, and announced projects do sometimes change scope or fail to proceed.

Outlined in yellow: Amazon's parcel at 10464 E Pecos Rd, Mesa, the PHX065 campus. It shows the land, not where buildings would go. Parcels: Maricopa County Assessor, Parcel 304-34-015G. Shapes: Maricopa County Assessor (read November 7, 2026).
Capacity: Estimate from a data center listing site. Cleanview project map, read October 7, 2026. The listing does not say what the figure measures.
Per-facility headcount is not published here: no reliable public figures exist for these sites, and construction announcements are not permanent employment. Open Arizona roles at this operator, where there are any, are listed on the operator's company page.
Compiled from public records and checked on 2026-10-07. Confidence in this record: medium. Blank figures mean the number is not publicly established, not that it is zero.
Each statement on this page is listed with the page it came from and the words that say it. Sources open in a new tab.
Status: Proposed
Note: Only a listing site says planned. A September 2025 city permit says a permanent building is under construction here.
Map record 3407: AWS PHX065 Pecos Road - Building 1 | status Planned | capacityMw 96.3
Capacity: 96 MW
Note: Only a listing site gives this figure.
Map record 3407: AWS PHX065 Pecos Road - Building 1 | status Planned | capacityMw 96.3
Floor area: 229,416 sq ft
Note: The city permit gives this size for a data center at 10464 E Pecos Rd without naming the building.
Development of 229,416 SF, Type II-B construction, group B occupancy single story data center.
Expected: 2026
Note: A listing site gives 2026 as the year planned for PHX065.
Short Code: PHX065 Year Planned: 2026
Location: 10464 E Pecos Rd, Mesa
"property_address":"10464 E PECOS RD"
Mesa issued a building permit in March 2025 for a single-story data center of about 229,000 sq ft at 10464 E. Pecos Road, and a September 2025 city permit said a permanent building was under construction there. A September 2025 city civil permit for the campus calls this building "Phase1-Building2," and a September 2025 use permit names the project "AWS PHX065 Bldg. 2," so the city numbers the two Pecos Road buildings the other way around from the names on these pages.
"issued_date":"2025-03-25T00:00:00.000" [...] "description":"Development of 229,416 SF, Type II-B construction, group B occupancy single story data center.
"property_address":"10464 E PECOS RD"
"issued_date":"2025-09-29T00:00:00.000" [...] TEMPORARY CONSTRUCTION FIELD BREAK/LUNCHROOM FOR USE BY CONTRACTORS WHILE A PERMANENT BUILDING IS UNDER CONSTRUCTION. [...] PROJECT: AWS PHX065 Bldg. 2.
"description":"Phase2-Building1. Civil Improvement Plans for New Data Center Building on existing campus. [...] REF: PMT24-15709 Phase1-Building2