Proposed data center in Mesa. Operated by Amazon Web Services.
This is a proposed or under-construction project. It is not operating capacity, and announced projects do sometimes change scope or fail to proceed.
Capacity: Estimate from a data center listing site. Cleanview project map, read October 7, 2026. The listing does not say what the figure measures.
Per-facility headcount is not published here: no reliable public figures exist for these sites, and construction announcements are not permanent employment. Open Arizona roles at this operator, where there are any, are listed on the operator's company page.
Compiled from public records and checked on 2026-10-07. Confidence in this record: medium. Blank figures mean the number is not publicly established, not that it is zero.
Each statement on this page is listed with the page it came from and the words that say it. Sources open in a new tab.
Status: Proposed
"issued_date":"2025-09-17T00:00:00.000" [...] "description":"Phase2-Building1. Civil Improvement Plans for New Data Center Building on existing campus.
Map record 3408: AWS PHX065 Pecos Road - Building 2 | status Planned | capacityMw 96.3
Capacity: 96 MW
Note: Only a listing site gives this figure.
Map record 3408: AWS PHX065 Pecos Road - Building 2 | status Planned | capacityMw 96.3
Floor area: 227,000 sq ft
Note: A 2023 press report gives this as the planned size of each building and does not name the site.
Each plan calls for two 227,000 sq ft (21,090 sqm) data center buildings on land owned by Amazon.
Location: Mesa
"property_address":"10464 E PECOS RD"
Mesa issued a civil improvement permit in September 2025 for a new data center building on the existing Pecos Road campus.
"issued_date":"2025-09-17T00:00:00.000" [...] "description":"Phase2-Building1. Civil Improvement Plans for New Data Center Building on existing campus.