Operating data center in Mesa. Operated by Google.
Capacity: Estimate from a data center listing site. Cleanview project map, read October 7, 2026. The listing does not say what the figure measures.
Per-facility headcount is not published here: no reliable public figures exist for these sites, and construction announcements are not permanent employment. Open Arizona roles at this operator, where there are any, are listed on the operator's company page.
Stories in Arizona AI's news feed that name this facility, newest first.
Compiled from public records and checked on 2026-10-11. Confidence in this record: medium. Blank figures mean the number is not publicly established, not that it is zero.
Each statement on this page is listed with the page it came from and the words that say it. Sources open in a new tab.
Status: Operating
Note: Only listing sites name this building as running. Google's list shows Mesa as not in development.
"location": "Mesa, Arizona", "latitude": null, "longitude": null, "inDevelopment": false
Mesa - Building 1 is a data center located in Maricopa, Arizona. It became operational in 2025. Developed by Google.
Map record 1351: Mesa - Building 1 | status Operating
Fully operational facility
Capacity: 138 MW
Note: Only the listing site Cleanview gives this figure.
Map record 1351: Mesa - Building 1 | status Operating | capacityMw 138
Floor area: 288,530 sq ft
Note: The source gives this as the planned size of the first phase in 2023.
The first 288,530 sq ft (26,805 sqm) phase is reportedly due live in July 2025, and set for full build-out across three phases by 2030.
Online since: 2025
Note: A listing site says it became operational in 2025.
Mesa - Building 1 is a data center located in Maricopa, Arizona. It became operational in 2025. Developed by Google.
Location: Mesa
Last year, construction started for our first Arizona data center in Mesa, which will use air-cooled technology
"location": "Mesa, Arizona", "latitude": null, "longitude": null, "inDevelopment": false
Google broke ground on the first building at the Mesa campus in July 2023
The first building on Google's Mesa campus at the northwest corner of Elliot and Sossaman Roads. The campus development agreement went to Mesa City Council in July 2019, and Google broke ground on the building in July 2023.
Google broke ground on the first building at the Mesa campus in July 2023
for the development of approximately 187 acres of property generally located at the northwest corner of Elliot and Sossaman Roads
DA and GPLET with Stone Applications, LLC - Google 2019-07-01
Google said in 2024 it would open in 2025.
Our Mesa data center will be operational in 2025
The listing site Baxtel calls it Redhawk 1.
Fully operational facility
Counted as operating under Arizona AI's rule for buildings whose operator has not announced an in-service date: Google lists Mesa as one of its data center locations, listing sites list this building as running, and no source we found says otherwise.
"location": "Mesa, Arizona", "latitude": null, "longitude": null, "inDevelopment": false
Map record 1351: Mesa - Building 1 | status Operating
Mesa - Building 1 is a data center located in Maricopa, Arizona. It became operational in 2025. Developed by Google.
Fully operational facility
City of Mesa permit records show a certificate of occupancy issued on August 8, 2025 for permit PMT23-13926, a new data center at 7232 E. Elliot Road on the Redhawk campus.
"status":"C of O Issued"
"cofo_date":"2025-08-08T00:00:00.000"
New ground up data center with electrical yard, mechanical yard
A City of Mesa permit for heating, cooling and plumbing work, PMT23-17942, describes Project Red Hawk as an 80-MW data center.
80-MW Data Center. HVAC and Plumbing for Project Red Hawk
These remarks are Arizona AI's own. They say how this record is counted or what we could not find, so there is no outside page to link.
Arizona AI takes permit PMT23-13926 to be this building's, since it is the only data center building permit on the campus with a certificate of occupancy in the city's published permit data on October 11, 2026. A certificate of occupancy means the city allowed the building to be occupied. It does not by itself show computer equipment in service. The 138 MW shown on this page is a listing site's figure. Permit PMT23-17942 does not say which building its 80 MW refers to, so Arizona AI has not changed the figure.