Google Mesa Building 2 is the second building on Google's Redhawk campus in Mesa. City of Mesa records show a certificate of occupancy issued on September 29, 2026 on the permit for the campus's Phase 2 above-ground buildings and structures.
Proposed data center in 3164 S Sossaman Rd, Mesa. Operated by Google.
Permit PMT24-16556, which the City of Mesa issued on December 10, 2024 for the Phase 2 above-ground buildings and structures, shows the status C of O Issued, finaled on September 29, 2026. The Phase 2 foundation permit, PMT24-07723, and the permit for an electrical substation to power the Red Hawk Phase 2 Red building both show the status C of C Issued, finaled on September 10 and September 29, 2026. Cleanview, a listing site, listed the building as planned and expected to become operational in 2026.

Outlined in yellow: Google's two parcels at 3164 S Sossaman Rd, Mesa, the Redhawk campus at Elliot and Sossaman Roads. It shows the land, not where buildings would go. Parcels: Maricopa County Assessor, Parcel 304-05-019P (Stone Applications LLC). Shapes: Maricopa County Assessor (read November 7, 2026).
Capacity: Estimate from a data center listing site. Cleanview project map, read October 7, 2026. By November 2026 Cleanview no longer showed building figures publicly. The listing does not say what the figure measures.
Per-facility headcount is not published here: no reliable public figures exist for these sites, and construction announcements are not permanent employment. Open Arizona roles at this operator, where there are any, are listed on the operator's company page.
Stories in Arizona AI's news feed that name this facility, newest first.
Compiled from public records and checked on 2026-11-13. Confidence in this record: high. Blank figures mean the number is not publicly established, not that it is zero.
Each statement on this page is listed with the page it came from and the words that say it. Sources open in a new tab.
Status: Certificate of occupancy issued
Note: Cleanview lists it as planned. AZBEX reported in October 2025 that construction began as of early March.
Map record 1575: Mesa - Building 2 | status Planned | capacityMw 138
PMT24-16556 | issued 2024-12-10 | status C of O Issued | finaled 2026-09-29 | Install above ground buildings and structures associated with Phase 02. Foundations and underground utilities for Phase 02 have previously been permitted under PMT24-07723. [...] Other exclusions to this permit review include all pre-engineered metal buildings (PEMBs) located on the phase 02 site.
Capacity: 138 MW
Note: Only the listing site Cleanview gives this figure.
Map record 1575: Mesa - Building 2 | status Planned | capacityMw 138
Floor area: 280,000 sq ft
Note: The source gives this as the planned size at design review in April 2024.
consists of a 280,000-square-foot building used as a data center
Expected: 2026
Note: Only a listing site gives this year. By November 2026 Cleanview no longer showed building details publicly.
It is expected to become operational in 2026. Being developed by Google.
Location: 3164 S Sossaman Rd, Mesa
Redhawk - Phase 2" (District 6). Within the 7100 to 7600 blocks of East Elliot Road (north side)
Map record 1575: Mesa - Building 2 | status Planned | capacityMw 138
STONE APPLICATIONS LLC; 3164 S SOSSAMAN RD MESA 85212
Permit PMT24-16556, which the City of Mesa issued on December 10, 2024 for the Phase 2 above-ground buildings and structures, shows the status C of O Issued, finaled on September 29, 2026.
PMT24-16556 | issued 2024-12-10 | status C of O Issued | finaled 2026-09-29 | Install above ground buildings and structures associated with Phase 02. Foundations and underground utilities for Phase 02 have previously been permitted under PMT24-07723. [...] Other exclusions to this permit review include all pre-engineered metal buildings (PEMBs) located on the phase 02 site.
The Phase 2 foundation permit, PMT24-07723, and the permit for an electrical substation to power the Red Hawk Phase 2 Red building both show the status C of C Issued, finaled on September 10 and September 29, 2026.
PMT24-07723 | issued 2024-07-22 | status C of C Issued | finaled 2026-09-10 | Foundation and underground/slab utilities only for new Data Center.
PMT25-02428 | issued 2025-04-15 | status C of C Issued | finaled 2026-09-29 | Install electrical substation to power Red Hawk Phase 2 Red building.
PMT24-16556 | issued 2024-12-10 | status C of O Issued | finaled 2026-09-29 | Install above ground buildings and structures associated with Phase 02. Foundations and underground utilities for Phase 02 have previously been permitted under PMT24-07723. [...] Other exclusions to this permit review include all pre-engineered metal buildings (PEMBs) located on the phase 02 site.
Cleanview, a listing site, listed the building as planned and expected to become operational in 2026.
Map record 1575: Mesa - Building 2 | status Planned | capacityMw 138
It is expected to become operational in 2026. Being developed by Google.
The second building on Google's Mesa campus, about 280,000 sq ft. AZBEX reported in October 2025 that construction had begun as of early March.
DATABEX cites Mesa permitting as showing construction on Phase II began as of early March.
consists of a 280,000-square-foot building used as a data center
The City of Mesa issued permit PMT24-16556 on December 10, 2024 for all above-ground buildings and structures of Redhawk Phase 2.
This application is intended for the installation and construction of all above ground buildings and structures associated with Phase 02.
The City of Mesa's permit PMT24-16556, covering the Phase 2 above-ground buildings and structures (which excludes pre-engineered metal buildings), shows a certificate of occupancy issued on September 29, 2026.
PMT24-16556 | issued 2024-12-10 | status C of O Issued | finaled 2026-09-29 | Install above ground buildings and structures associated with Phase 02. Foundations and underground utilities for Phase 02 have previously been permitted under PMT24-07723. [...] Other exclusions to this permit review include all pre-engineered metal buildings (PEMBs) located on the phase 02 site.
The Phase 2 building permit says the Phase 2 foundations and underground utilities were permitted earlier, under PMT24-07723, issued July 22, 2024.
PMT24-16556 | issued 2024-12-10 | status C of O Issued | finaled 2026-09-29 | Install above ground buildings and structures associated with Phase 02. Foundations and underground utilities for Phase 02 have previously been permitted under PMT24-07723. [...] Other exclusions to this permit review include all pre-engineered metal buildings (PEMBs) located on the phase 02 site.
PMT24-07723 | issued 2024-07-22 | status C of C Issued | finaled 2026-09-10 | Foundation and underground/slab utilities only for new Data Center.
A City of Mesa permit to install an electrical substation "to power Red Hawk Phase 2 Red building", PMT25-02428, shows a certificate of completion on September 29, 2026.
PMT25-02428 | issued 2025-04-15 | status C of C Issued | finaled 2026-09-29 | Install electrical substation to power Red Hawk Phase 2 Red building.
The City of Mesa announced that the City Council approved the development agreement with Google on July 1, 2019, and said the milestone minimums in the agreement do not reflect the actual project scope.
The Mesa City Council approved a development agreement with the multinational technology and Internet services giant, Google. [...] While the Development Agreement contemplates milestone minimums which Google must achieve, they do not reflect the actual project scope.
The city's council report describes a first milestone, tied to the water allowance, of at least 250,000 square feet of buildings and $600 million of capital investment before July 1, 2025, and an annual water allowance of 1,120 acre-feet that rises by 1,120 acre-feet with each of three milestones, up to 4,480 acre-feet.
First Milestone Date: Before July 1st, 2025, the company must complete construction on a minimum cumulative total of 250,000 square feet of Building Gross Area, and invest a minimum of $600,000,000 in cumulative Capital Investment in the project.
Upon the execution of the Development Agreement, the annual Water Allowance will be 1,120 Acre Feet per Year (AFY). The Allowance will then increase by 1,120 AFY for each of the three Milestones achieved, up to a maximum of 4,480 AFY. [...] New permanent Full-Time Equivalent Positions/Jobs created by the company must receive an annual average compensation of at least $65,000 per year.
Google said in December 2023 that its planning study found the local water source at high risk of depletion and scarcity, so it chose to air-cool the Mesa data center.
Notably, the responsible-use evaluation completed during the planning stage for our recently announced data center in Mesa, Arizona, found the local water source was at high risk of depletion and scarcity. Therefore, we opted to air-cool the data center, minimizing our impact on the local watershed.
SRP's witness said at a November 2019 hearing that SRP could serve in the neighborhood of 500 megawatts to the site, for a customer described as an affiliate of Google, and SRP says the Arizona Corporation Commission approved the project's transmission line certificate on December 10, 2019.
We anticipate SRP can serve in the neighborhood of 500 megawatts utilizing up to ten 230kV lines on the project site. [...] The customer is a yet-to-be-named affiliate of Google.
On Dec. 10, 2019, the ACC unanimously approved the CEC for the project.
Epoch AI, which estimates data center capacity from satellite imagery and a cooling equipment model, estimates that Building 2 became operational on August 15, 2026, based on near-complete construction seen in May 2026, and puts the campus at 183 MW of IT power after that.
The timeline of IT power and AI compute capacity is based on satellite imagery, our cooling equipment power model, chip availability, and chip efficiency. [...] Jul 1, 2025 Satellite explorer Building 1 is operational. [...] IT Power 90 MW [...] Aug 15, 2026 Satellite explorer Building 2 is operational. This is estimated based on the close-to-complete construction status from May 2026.
IT Power 183 MW
These remarks are Arizona AI's own. They say how this record is counted or what we could not find, so there is no outside page to link.
The city's permits name phases, not buildings. Phase 2 is taken to be this building, the second on the campus, but no city record states that.