NTT Mesa PH10 (Pacific Proving site)

NTT Mesa PH10 (Pacific Proving site) is a proposed data center development of about 2.26 million square feet on 170 acres at the northeast corner of East Pecos Road and the South Crismon Road alignment in Mesa. ABC15 reported in May 2026 that Mesa's zoning board approved it with conditions.

Proposed data center in Pecos Road and the Crismon Road alignment, Mesa. Operated by NTT.

Where it stands

ABC15 reported on May 19, 2026 that Mesa's Planning and Zoning Board had approved the NTT project with conditions and that it still needed City Council approval. In August 2026 ABC15 reported that a city spokesperson said NTT was requesting minor modifications to the city's allowances, which is why the project kept appearing in meetings. Mesa issued Clayco a permit on October 13, 2026 for a stockpile of about 6,000 cubic yards labeled NTT Data Centers on the site.

The short version

Where does it stand with the city?

  • The City Council approved a site plan and rezoning for the site on August 26, 2024 for an earlier development, which the staff report says never came to fruition before a new developer sought to revise the entitlements.
  • The staff report says the application was submitted on August 4, 2025, before Mesa's Ordinance No. 5957 took effect, so it is processed under the standards in effect when it was filed.
  • ABC15 reported on May 19, 2026 that the Planning and Zoning Board approved the project with conditions and that it still needed City Council approval.
  • Mesa issued Clayco a permit on October 13, 2026 for a stockpile of about 6,000 cubic yards labeled NTT Data Centers.

How much did NTT pay for the land?

  • The Maricopa County Assessor lists a sale price of $296,378,800 for the site's 7,412,696 square foot parcel, about 170.2 acres, owned by NTT GLOBAL DATA CENTERS PH10 LLC.
  • Data Center Dynamics reported in March 2025 that NTT paid $300 million for 173 acres. The sources do not say whether this and the Assessor's sale describe the same purchase.
  • Connect CRE reported that Levine Investments and Andrew Cohn owned the land and that Nathan & Associates Inc. and JLL negotiated the deal.

How big will it be and how much power will it use?

  • Mesa's staff report describes seven data center buildings from 309,638 to 399,753 square feet, 2,257,581 square feet in all, plus a Salt River Project substation, a private substation and a city well site.
  • A company spokesperson told Data Center Dynamics the first building would be available in November 2028. ConstructConnect reported up to 360 megawatts for the first phase by then, without saying what the figure measures.
  • The staff report says the applicant has been working with Salt River Project on an electrical network for the site and sites directly west of it.

What about water and cooling?

  • NTT's applicant narrative says each data hall building will have a closed-loop water cooling system filled up only once, with water from the City of Mesa.

Who has raised concerns?

  • At the applicant's October 15, 2025 neighborhood meeting, two attendees raised concerns including noise from the substation and generators.
  • ABC15 reported on August 15, 2026 that community activists oppose the plan over water use, job growth, wildlife and property values, and that a city spokesperson said NTT is requesting minor modifications to the city's allowances.

Where it is

2023 aerial photo of parcel 313-25-962, identified in Mesa's NTT Mesa PH10 data center campus plan, outlined in yellow.
Aerial photo flown September 15, 2023: USDA National Agriculture Imagery Program (NAIP); source: USGS, USDA, The National Map: Orthoimagery (public domain). Outline drawn by Arizona AI from Maricopa County Assessor parcel records.

Outlined in yellow: Parcel 313-25-962, identified in Mesa's ZON25-00626 plan for the NTT Mesa PH10 data center campus. It shows the land, not where buildings would go. Parcels: City of Mesa, May 13, 2026 ZON25-00626 staff report, NTT Mesa PH10, parcel 313-25-962. Shapes: Maricopa County Assessor (read November 8, 2026).

Open in Google Maps

  • Floor area: 2.3M sq ft
  • Land: 170 acres
  • Expected: 2028

Timeline

  1. : Mesa City Council approved a site plan and Light Industrial rezoning for the 170.1-acre site for an earlier development that the city later said never came to fruition. Source: City of Mesa, Planning and Zoning Report, ZON25-00626 NTT Mesa PH10 (staff report, May 13, 2026)
  2. : Data Center Dynamics reports NTT paid $300 million for 173 acres at Pecos and Crismon roads in Mesa. Source: Data Center Dynamics, NTT acquires 173-acre planned data center park in Mesa, Arizona, for $300m - DCD
  3. : The applicant submitted the NTT Mesa PH10 application before Mesa's Ordinance No. 5957 took effect, so the city processes it under the standards in effect when it was filed. Source: City of Mesa, Planning and Zoning Report, ZON25-00626 NTT Mesa PH10 (staff report, May 13, 2026)
  4. : The applicant held a neighborhood meeting where two attendees raised concerns, including noise from the substation and generators. Source: City of Mesa, Planning and Zoning Report, ZON25-00626 NTT Mesa PH10 (staff report, May 13, 2026)
  5. : Mesa's Design Review Board reviewed the project and gave minor comments on the building design, which the staff report says the applicant addressed. Source: City of Mesa, Planning and Zoning Report, ZON25-00626 NTT Mesa PH10 (staff report, May 13, 2026)
  6. : The NTT Mesa PH10 request, about 2.26 million sq ft of data centers on 170 acres, is on the Mesa Planning and Zoning Board hearing agenda, with staff recommending approval with conditions. Source: City of Mesa, City of Mesa Legistar matter PZ 26033 (ZON25-00626)
  7. : ABC15 reported that Mesa's Planning and Zoning Board approved the NTT project with conditions and that it still needed City Council approval. Source: ABC15, Mesa considers new data center project off SR 24
  8. : Mesa issued Clayco a permit for a stockpile of about 6,000 cubic yards labeled NTT Data Centers on the site. Source: City of Mesa, Building Permits (Commercial, Residential and Signs), permit PMT26-16525

Working here

Per-facility headcount is not published here: no reliable public figures exist for these sites, and construction announcements are not permanent employment. Open Arizona roles at this operator, where there are any, are listed on the operator's company page.

Other NTT facilities in Arizona

  • NTT Phoenix PH1
    NTT · 10256 E Elliot Rd, Mesa · Operating · 36 MW
  • NTT Phoenix PH2
    NTT · 10256 E Elliot Rd, Mesa · Operating · 50 MW · 235,550 sq ft
  • NTT Phoenix PH3
    NTT · 10256 E Elliot Rd, Mesa · Operating · 50 MW · 235,550 sq ft
  • NTT Phoenix PH4
    NTT · 10256 Elliot Rd, Bldg 4, Mesa · Temporary certificate of occupancy · 36 MW
  • NTT Phoenix PH5
    NTT · 10256 E Elliot Rd, Mesa · Proposed
  • NTT Phoenix PH6
    NTT · 10256 E Elliot Rd, Mesa · Design review filed · 195,408 sq ft

News

Stories in Arizona AI's news feed that name this facility, newest first.

All Arizona AI news

How we know this

Compiled from public records and checked on 2026-11-13. Confidence in this record: high. Blank figures mean the number is not publicly established, not that it is zero.