NTT Phoenix PH6

NTT Phoenix PH6 is a proposed NTT data center building of about 195,408 square feet on a site of about 101 acres at 10256 E Elliot Rd in Mesa, according to Mesa's design review notice. It was on the agenda of Mesa's Design Review Board on January 13, 2026.

Proposed data center in 10256 E Elliot Rd, Mesa. Operated by NTT.

Where it stands

Mesa's Design Review Board listed PH6 for design review on January 13, 2026, and AZBEX reported that the board met to discuss the aesthetics and landscape plans and took no action. Mesa's open data lists a foundation permit for a 188,093 SF data center and a civil site permit, both Fees Paid with no issue date when read on November 13, 2026, and neither names PH6 or PH7. Baxtel gives 2029 as the year planned for PH6.

The short version

Why is PH6 one building instead of two?

  • A design review narrative by Corgan dated November 11, 2025 combines the originally proposed PH6 and PH7 into a single building referenced as PH6, reducing the campus from 7 to 6 buildings.
  • AZBEX reported the combined building at 195.4KSF. In October 2026, ABC15 reported that NTT says it is working toward all seven data centers planned for the property.

Where does it stand with the city?

  • AZBEX reported that Mesa's Design Review Board met on January 13, 2026 to discuss the building's aesthetics and landscape plans and took no action.
  • Mesa's open data lists a foundation permit for a 188,093 SF data center and a civil site permit, both "Fees Paid" with no issue date on November 13, 2026. They do not name PH6 or PH7, and no record cited here links them to an NTT PH name.
  • Baxtel gives 2029 as the year planned, and datacenterHawk says the building has not yet been commissioned or leased.

Who is building it?

  • AZBEX reported that NTT Global Data Centers Americas is the owner, Corgan the design firm and Colliers Engineering & Design the engineer.
  • Maricopa County lists Clayco on a dust control record named "NTT PH6", a construction record.

Where it is

Aerial photo of NTT's Mesa campus at Elliot Road west of the Loop 202, with the parcel outlined in yellow around three long white data center buildings, a fourth under construction and graded land for more
Aerial photo flown September 15, 2023: USDA National Agriculture Imagery Program (NAIP); source: USGS, USDA, The National Map: Orthoimagery (public domain). Outline drawn by Arizona AI from Maricopa County Assessor parcel records.

Outlined in yellow: NTT's parcel at 10256 E Elliot Rd, Mesa, the campus that holds PH1 to PH6. It shows the land, not where buildings would go. Parcels: Maricopa County Assessor, Parcel 304-01-006N (NTT Global Data Centers PH LLC). Shapes: Maricopa County Assessor (read November 7, 2026).

Open in Google Maps

  • Floor area: 195,408 sq ft
  • Expected: 2029

Timeline

  1. : NTT announced a 102-acre Mesa campus of seven data centers with 240MW of critical IT load and an on-site dedicated substation, AZBEX reported. Source: AZBEX (republishing NTT Ltd release), NTT Ltd Building 1.5MSF Mesa Data Center
  2. : A design review narrative by Corgan for Mesa combined the originally proposed PH6 and PH7 into one building referenced as PH6, cutting the campus from 7 to 6 buildings. Source: City of Mesa (applicant narrative by Corgan), Project Narrative, NTT PH6 Design Review Submission, DRB25-00900
  3. : Mesa's Design Review Board listed PH6, case DRB25-00900, a data center of about 195,408 sq ft, for design review, and AZBEX reported that no action was taken. Source: City of Mesa, Legistar matter DSN 26001, DRB25-00900 NTT Data Centers PH6

Working here

Per-facility headcount is not published here: no reliable public figures exist for these sites, and construction announcements are not permanent employment. Open Arizona roles at this operator, where there are any, are listed on the operator's company page.

Rest of this campus

  • NTT Phoenix PH1
    NTT · 10256 E Elliot Rd, Mesa · Operating · 36 MW
  • NTT Phoenix PH2
    NTT · 10256 E Elliot Rd, Mesa · Operating · 50 MW · 235,550 sq ft
  • NTT Phoenix PH3
    NTT · 10256 E Elliot Rd, Mesa · Operating · 50 MW · 235,550 sq ft
  • NTT Phoenix PH4
    NTT · 10256 Elliot Rd, Bldg 4, Mesa · Temporary certificate of occupancy · 36 MW
  • NTT Phoenix PH5
    NTT · 10256 E Elliot Rd, Mesa · Proposed

Other NTT facilities in Arizona

News

Stories in Arizona AI's news feed that name this facility, newest first.

All Arizona AI news

How we know this

Compiled from public records and checked on 2026-11-13. Confidence in this record: high. Blank figures mean the number is not publicly established, not that it is zero.

Each statement on this page is listed with the page it came from and the words that say it. Sources open in a new tab.

Our own notes

These remarks are Arizona AI's own. They say how this record is counted or what we could not find, so there is no outside page to link.

Mesa's open data lists permit PMT26-09976 for a 188,093 SF data center, "Underground and foundation only," and civil permit PMT26-09201, both in the status "Fees Paid" with no issue date when read on November 13, 2026, with Chad Labucki named as contractor on the first.