NTT Phoenix PH5 is a data center building listed at 10256 E Elliot Rd in Mesa. One listing site says it is planned for 2028, and another says it has been commissioned.
Proposed data center in 10256 E Elliot Rd, Mesa. Operated by NTT.
No record cited here says which of Mesa's numbered buildings on NTT's Elliot Road campus is PH5, and NTT's Phoenix campus page lists only PH1 and PH4. Mesa's permit for "Building #3", which does not use the name PH5, read Temporary C of O on November 13, 2026, while a vault 1.1 fit-out permit within building 3's shell read Revisions Required. Baxtel lists PH5 as planned for 2028, and ABC15 reported that NTT says construction on the campus will continue for at least another two years.

Outlined in yellow: NTT's parcel at 10256 E Elliot Rd, Mesa, the Elliot Road campus where PH5 is planned. It shows the land, not where buildings would go. Parcels: Maricopa County Assessor, Parcel 304-01-006N, 10256 E Elliot Rd, Mesa (owner NTT Global Data Centers PH LLC). Shapes: Maricopa County Assessor (read November 7, 2026).
Per-facility headcount is not published here: no reliable public figures exist for these sites, and construction announcements are not permanent employment. Open Arizona roles at this operator, where there are any, are listed on the operator's company page.
Stories in Arizona AI's news feed that name this facility, newest first.
Compiled from public records and checked on 2026-11-13. Confidence in this record: high. Blank figures mean the number is not publicly established, not that it is zero.
Each statement on this page is listed with the page it came from and the words that say it. Sources open in a new tab.
Status: Proposed
Note: Only one listing site says planned. Another listing site says commissioned.
Planned Future facility in planning stage
Short Code: PH5 Year Planned: 2028 This facility is part of NTT
Expected: 2028
Note: A listing site gives 2028 as the year planned.
Short Code: PH5 Year Planned: 2028 This facility is part of NTT
Location: 10256 E Elliot Rd, Mesa
Note: The parcel is NTT's Elliot Road campus. No city permit or NTT page names PH5 yet, so this is the campus address, not a building address.
10256 E ELLIOT RD MESA 85212 [...] NTT GLOBAL DATA CENTERS PH LLC
DRB25-00900. "NTT Data Centers PH6," 101± acres located at 10256 East Elliot Road. Design Review for an approximately 195,408 sq.ft. Data Center.
No record cited here says which of Mesa's numbered buildings on NTT's Elliot Road campus is PH5, and NTT's Phoenix campus page lists only PH1 and PH4.
"issued_date":"2022-04-11T00:00:00.000" [...] within the previously permitted NTT PH1 data center facility (PMT21-01151) for NTT (owner). This facility is bldg #5.
BUILDING 7. The proposed work is for the expansion of the mechanical & electrical systems to support NTT client's equipment in the Vault 1.1 space. The PH3 facility
10256 Elliot Rd., Bldg 4 Mesa, AZ 85212
combining the originally proposed PH6 (BLDG #2) and PH7 (BLDG #1) into a singular building that will be referenced as PH6.
Discover our Phoenix data centers Phoenix PH1 Data Center Phoenix PH4 Data Center
Mesa's permit for "Building #3", which does not use the name PH5, read Temporary C of O on November 13, 2026, while a vault 1.1 fit-out permit within building 3's shell read Revisions Required.
"status":"Temporary C of O"
Tenant improvement within building 3's shell vault 1.1.
"status":"Revisions Required"
Baxtel lists PH5 as planned for 2028, and ABC15 reported that NTT says construction on the campus will continue for at least another two years.
Short Code: PH5 Year Planned: 2028 This facility is part of NTT
NTT's Mesa campus is still under development. The company says construction will continue for at least another two years as it works toward completing all seven data centers planned for the property.
Once fully completed, NTT says its Mesa campus will have a power capacity exceeding 200 megawatts
Listed as planned for 2028 by one listing site and as commissioned by another.
Planned Future facility in planning stage
Short Code: PH5 Year Planned: 2028 This facility is part of NTT
Commissioned This facility has been commissioned.
NTT's Phoenix campus page lists only the PH1 and PH4 data centers.
Our Phoenix data center campus, set to deliver over 240MW of IT load when fully operational
Discover our Phoenix data centers Phoenix PH1 Data Center Phoenix PH4 Data Center
That permit does not use the name PH5, no record cited here says Building #3 is PH5, and the status does not by itself show the building is operating.
Building #3. New 225,606 sf 2-story data center.
"status":"Temporary C of O"
"issued_date":"2025-02-10T00:00:00.000"
A permit for tenant improvements to vault 1.1 within "building 3's shell" had the status "Revisions Required" in Mesa's open data on November 13, 2026, and it does not name PH5.
Tenant improvement within building 3's shell vault 1.1.
"status":"Revisions Required"
Mesa's permit for Building 3 says another permit modified the separation between Buildings 3 and 6 and evaluated the structures as portions of a single building on the same lot, without saying which NTT PH name Building 3 carries.
Permit PMT24-17530A modified the separation between Buildings 3 and 6 and included a code analysis evaluating the structures as portions of a single building on the same lot.
Permit PMT24-17530A modified the separation between Buildings 3 and 6 and included a code analysis evaluating the structures as portions of a single building on the same lot.
Maricopa County's air quality dataset lists a Clayco dust control record named "NTT Data Center PH4 & PH5" for a new base build data center complex with underground utilities, site grading, landscaping, onsite parking and material laydown.
"facility_nm":"NTT Data Center PH4 & PH5"
"facility_desc":"New base build Data Center complex, underground utilities, site grading, landscaping, onsite parking and material laydown"
NTT's Phoenix data centers page says "Our Phoenix campus features a planned capacity of 240MW" and that the campus is "set to deliver over 240MW of IT load when fully operational", figures for the whole campus rather than for PH5.
Our Phoenix campus features a planned capacity of 240MW and offers expansion opportunities for clients of all sizes.
Our Phoenix data center campus, set to deliver over 240MW of IT load when fully operational
Maricopa County Air Quality lists facility F040194, "PH Data Center", at 10302 E Elliot Rd in Mesa as a "429 MW generating capacity data center." The record calls the figure generating capacity and does not say which buildings it covers.
"facility_nm":"PH Data Center" ... "address1":"10302 E Elliot Rd" ... "facility_desc":"429 MW generating capacity data center." ... "operating_status_dsc":"Operating"
"OnBaseWebLink":"https://edms.maricopa.gov/aq/index.html?OBKey__3635_1=F040194"
Mesa's building numbers on NTT's Elliot Road campus do not follow the PH names: a Mesa permit says the PH1 facility is bldg #5, a vault permit for the PH3 facility is headed Building 7, NTT lists PH4 at Bldg 4, and a November 2025 design narrative says the originally proposed PH6 was BLDG #2 and PH7 was BLDG #1. None of these records says which city building number PH5 carries.
"issued_date":"2022-04-11T00:00:00.000" [...] within the previously permitted NTT PH1 data center facility (PMT21-01151) for NTT (owner). This facility is bldg #5.
BUILDING 7. The proposed work is for the expansion of the mechanical & electrical systems to support NTT client's equipment in the Vault 1.1 space. The PH3 facility
10256 Elliot Rd., Bldg 4 Mesa, AZ 85212
combining the originally proposed PH6 (BLDG #2) and PH7 (BLDG #1) into a singular building that will be referenced as PH6.
ABC15 reported that NTT says construction on the Mesa campus will continue for at least another two years as it works toward completing all seven data centers planned for the property, and that the campus will have a power capacity exceeding 200 megawatts once fully completed, a figure for the whole campus.
NTT's Mesa campus is still under development. The company says construction will continue for at least another two years as it works toward completing all seven data centers planned for the property.
Once fully completed, NTT says its Mesa campus will have a power capacity exceeding 200 megawatts
These remarks are Arizona AI's own. They say how this record is counted or what we could not find, so there is no outside page to link.
Mesa permit PMT24-17530 for "Building #3," a new 225,606 sf two-story data center, was issued February 10, 2025, and its status in Mesa's open data read "Temporary C of O" on November 13, 2026.