The live tracker for Arizona's AI economy

Stack Infrastructure PHX02 Campus

Proposed data center in 800 N 40th St, Phoenix. Operated by Stack Infrastructure.

This is a proposed or under-construction project. It is not operating capacity, and announced projects do sometimes change scope or fail to proceed.

  • Capacity at full build-out: 250 MW
  • Floor area: 1.7M sq ft
  • Land: 51 acres

Capacity: Operator's own figure: computing (IT) load, at full build-out. STACK: nearly 250 MW of critical capacity.

Working here

Per-facility headcount is not published here: no reliable public figures exist for these sites, and construction announcements are not permanent employment. Open Arizona roles at this operator, where there are any, are listed on the operator's company page.

Other Stack Infrastructure facilities in Arizona

  • Stack Infrastructure PHX01 Campus
    Stack Infrastructure · 3001 S Litchfield Rd, Avondale · Proposed · 225 MW at full build-out
  • Stack PHX01A
    Stack Infrastructure · 3001 S Litchfield Rd, Avondale · Proposed · 98 MW
  • Stack PHX01B
    Stack Infrastructure · 3001 S Litchfield Rd, Avondale · Proposed · 98 MW
  • Stack PHX01C
    Stack Infrastructure · 3001 S Litchfield Rd, Avondale · Proposed · 98 MW
  • Stack PHX02A
    Stack Infrastructure · 800 N 40th St, Phoenix · Proposed · 65 MW
  • Stack PHX02B
    Stack Infrastructure · 800 N 40th St, Phoenix · Proposed · 65 MW
  • Stack PHX02C
    Stack Infrastructure · 800 N 40th St, Phoenix · Proposed · 65 MW

How we know this

Compiled from public records and checked on 2026-10-07. Confidence in this record: high. Blank figures mean the number is not publicly established, not that it is zero.