The live tracker for Arizona's AI economy

Vantage Data Centers in Arizona

By Arizona AI · Profile reviewed · 44 sourced facts

At a glance

Vantage Data Centers, a Denver, Colorado developer that leases wholesale data center space to hyperscale, cloud and enterprise customers, runs its AZ1 campus in Goodyear, Arizona, and holds land in Glendale. Vantage Data Centers announced its arrival in Arizona in January 2019 and topped out its first Goodyear data center, a 16MW building, in November 2021. Vantage Data Centers says the Goodyear campus will offer 176MW of IT capacity across five data centers once fully developed, and its architect says a fourth building of 64 MW became operational in 2025.

Key facts

Arizona locations (2)
Headquarters
Denver, Colorado
Ownership
Private company
Website
vantage-dc.com

Sources: Vantage Data Centers: Phoenix Data Center Campus - Arizona - Vantage Data Centers, City of Glendale, Vantage Data Centers: Vantage Secures $2B Credit Facility, Expanding Financing to Support Growing Demand, Reuters via BNN Bloomberg · Addresses open Google Maps in a new tab

Jobs listed on Arizona AI

18 open Arizona positions See Vantage Data Centers jobs

From Vantage Data Centers’ own careers site, refreshed twice a day.

How does Vantage Data Centers fit into AI?

Modern AI runs on physical silicon, and that silicon passes through several hands before it ever answers a question. Here is the path, and where Vantage Data Centers sits on it. Stages not marked below are shown for context and are not claims about Vantage Data Centers.

  1. Chip design: Companies like Nvidia, Apple and AMD design the chips. Chip designers decide what a chip does and hand the blueprint to a factory. The three companies whose designs matter most to AI - Nvidia, Apple and AMD - do that work elsewhere, then send the designs to fabs. None of them owns a fab of its own.
  2. Wafer fabrication: Fabs print billions of transistors onto silicon wafers. A fab prints a design onto a polished disc of silicon called a wafer, layer by layer, until billions of transistors exist where there was blank material. It is the hardest and most expensive step in the chain, and the reason a single factory can cost tens of billions of dollars.
  3. Advanced packaging: Wafers are cut and assembled into finished chips. Packaging cuts a finished wafer into individual chips and assembles them, often stacking several pieces of silicon and memory into one component. For AI chips this step is nearly as demanding as fabrication, and a wafer is not a usable product until it is done.
  4. Servers and devices: Chips are built into AI servers, phones and PCs. Finished chips are assembled into the things people actually buy and deploy: data-center servers, phones, laptops. This is where a chip stops being a component and starts being a product.
  5. AI in use (here today): Data centers and devices run AI models on that silicon. Hyperscale data center campus in Goodyear. The end of the chain: models answering questions, generating images and driving software, running on the silicon every earlier step produced. Every AI service anyone uses is running on physical hardware somewhere, and that hardware started as a wafer.

Vantage Data Centers: AI in use (here today)

  • 64 MW AZ14 building opened in 2025 (company-reported): AZ14, with 64 MW and high-density racks, became operational in 2025 and more than doubled the campus capacity. Source: Corgan
  • AZ13 built for liquid cooling (company-reported): The project architect states the AZ13 building is set to use liquid cooling to improve energy efficiency. Source: Corgan

About Vantage Data Centers

What Vantage Data Centers does

Vantage describes itself as a global provider of digital infrastructure serving AI and cloud innovators. Its business is building data center campuses and offering wholesale data center space to customers; when it entered the Phoenix market, Vantage said the campus would serve demand from hyperscale and cloud providers as well as technology, e-commerce and enterprise companies.

The company says it launched in June 2010 with an investment from Silver Lake Partners, when it acquired an operating data center in Santa Clara, California, that Intel Corp. had previously owned. A consortium of Digital Bridge, PSP Investments and TIAA Investments acquired Vantage from Silver Lake in March 2017, and the company's history page lists a $9.2 billion equity investment led by DigitalBridge and Silver Lake in June 2024. Vantage is not listed on a stock market: in August 2026 Reuters reported that Vantage, backed by Silver Lake and DigitalBridge, was exploring a stock market listing or a sale. That investment is company-wide, and Vantage does not state an Arizona share of it.

In Arizona

Goodyear AZ1 campus: Vantage Data Centers, which calls itself simply Vantage in its 2026 releases, is a Denver-based data center developer that runs the AZ1 campus in Goodyear, where three buildings with a combined 64 megawatts were fully leased to one tenant as of June 2025. Corgan, the campus architect, says a fourth building of 64 MW became operational in 2025, and its project page, as of October 2026, describes a fifth building as in conceptual design. Vantage's campus page, read the same month, says the campus will offer 176MW once fully developed; that is a planned total, not the capacity operating today.

Vantage announced its arrival in Arizona in January 2019, when it said it had acquired 50 acres in the Greater Phoenix area to build a mega-scale data center campus.

  • The campus, known as AZ1, sits at 45 S Bullard Avenue in Goodyear.
  • In November 2021 Vantage announced the topping out of its first data center there, which it described as a 16MW building.
  • In October 2022 the company began the second phase of construction and said it was investing more than $1.5 billion in the project, which it expected to create approximately 3,000 construction and technology jobs.

That investment figure was stated for an earlier plan of 160MW in three buildings. No later Vantage update to either the investment or the jobs figure was found after October 2022.

Goodyear Mayor Joe Pizzillo spoke at the phase two ceremony, and McCarthy Building Companies was the general contractor for that phase. The campus then grew. In December 2023 the law firm Quarles & Brady submitted a rezoning request on the project's behalf for 14 acres at the southeast corner of Bullard and Van Buren Street, to allow a two-story building for data center use.

City of Goodyear permit records show the AZ14 core and shell permit at 155 N. Bullard Ave. as completed. Vantage topped out that building, AZ14, in November 2024; it was expected to span 451,000 square feet across two stories on a 14-acre plot. Corgan says AZ14 became operational in 2025 with 64 MW of capacity, and its project page, as of October 2026, says a fifth building, AZ15, is in conceptual design with a planned capacity of 48 MW. City of Goodyear permit records show a building permit issued for AZ15, described as a 48 MW data center building and filed in June 2025 (permit B25-01411), with fire permits issued in 2026, so the city's records show the building further along than Corgan's page.

Vantage's campus page, read the same month, says the Goodyear campus will offer 176MW of IT capacity and more than one million square feet across five data centers once fully developed. That 176MW is a planned full build-out, not the capacity operating today.

Glendale site: Vantage also holds land elsewhere in the Phoenix area. DatacenterDynamics reported that in March 2023 Vantage acquired nearly 34 acres in Glendale from the Phoenix-based industrial developer Merit Partners for $50 million. The site is at the southwest corner of Loop 303 and Bethany Home Road, with Cotton Lane on its west side, in the Camelback 303 area; Maricopa County records now show nearly all of the Glendale land as a single parcel of about 102 acres owned by Vantage Data Centers AZ3 LLC.

As of June 2025, the same publication reported that Vantage had not yet announced plans for the Glendale site. In December 2025 Vantage bought about 70 more acres next to it for about $58.5 million, giving it more than 100 acres in Glendale, according to the Phoenix Business Journal.

The first three Goodyear buildings are fully leased to a single tenant, according to a Fitch Ratings report described by Bisnow in June 2025, and together offer 64 megawatts across 496,000 square feet. Vantage reports the first building at 16MW, and Corgan lists AZ12 at 16 MW and AZ13 at 32 MW. The tenant occupies the space through six separate 15-year leases with a weighted average remaining term of 13.9 years. City of Goodyear permits to fit out the AZ11, AZ12, AZ13 and AZ14 buildings carry Vantage project names, and one tenant improvement application for the campus at 45 S. Bullard Ave., B22-05331, filed October 20, 2022, gives its scope of work as "VANTAGE TI - META OLR"; the city lists it as in department review.

The same tenant had preleased the 64 MW building then under construction and holds an option on the planned 48-megawatt building. Corgan says that 64 MW building, AZ14, became operational in 2025; no update on the option after June 2025 was found.

In June 2025 Vantage secured a $735 million refinancing loan with its Phoenix-area data centers as collateral, to refinance the $560M of existing debt on the three buildings. This was a financing of existing buildings, not new investment. Vantage says AZ11 and AZ12 each earned Green Globe for New Construction certification from the Green Building Initiative.

Power: Vantage has described how the campus gets power and water. Vantage says Arizona Public Service powers the campus through a dedicated onsite substation with multiple utility feeds, receiving power at 69+kV.

Water: On water, Vantage says the buildings use a closed-loop chilled water design that needs no ongoing water, giving a planned water usage efficiency near zero. These are company design claims; no metered figure for the campus's actual water use was found.

In September 2026 Vantage said it had joined a group of organizations committing $32 million to the Colorado River Basin Collaborative, but its own share of that group total is not stated, and no update after that September 2026 announcement was found. The same month it closed a $2 billion financing facility for early-stage development across North America, and the release does not identify any Arizona share.

For Arizona, the facts add up to a large, partly built campus in Goodyear whose first three buildings and a fourth are committed to one AAA-rated tenant, a fifth building with a city building permit, and a Glendale site with no announced plans.

Role in AI and technology

Vantage's place in the AI economy is the physical layer: the buildings, power and cooling that cloud and computing customers lease. The company says it serves AI and cloud innovators, but no source found names an AI customer or AI workloads at its Goodyear campus.

The closest stated links are design features. Vantage says the Goodyear campus offers an average density of 250 watts per square foot, with options to go higher or lower, for high-density applications. Corgan is the campus architect. Corgan says the AZ13 building is set to use liquid cooling and that AZ14 includes high-density racks.

Vantage Data Centers in Arizona: By the Numbers

Each figure is dated and linked to its source. Figures that are company-reported, announced, or projected rather than measured are labeled.

  • Goodyear AZ1 campus planned IT capacity at full build-out: 176MW at full build-out (planned) (announced)
  • Announced investment in the Goodyear campus: More than $1.5 billion (announced)
  • Combined IT capacity of the first three Goodyear buildings: 64 MW across 496,000 sq ft
  • Goodyear campus land area: 50 acres
  • Construction and technology jobs expected from the Goodyear project: Approximately 3,000 (projected) (projected)
  • Ownership: Acquired from Silver Lake in March 2017 by a consortium of Digital Bridge, PSP Investments and TIAA Investments

The Arizona build-out, 2010 to 2025

  • 2010: Vantage Data Centers launched
  • 2019: Phoenix market entry announced with Goodyear land purchase
  • 2021: First Goodyear data center topped out
  • 2022: Phase two construction began in Goodyear
  • 2024: AZ14 topped out
  • 2025: AZ14 became operational

Vantage Data Centers Goodyear AZ1 campus (45 S Bullard Avenue), Arizona

MeasureValueAs ofBasisSource
Address45 S Bullard Avenue, Goodyear, AZ 853382026-10-28verifiedVantage Data Centers
Campus roleWholesale hyperscale data center campus for cloud and large enterprise customers2019-01-08company-reported From the company's own published information.Vantage Data Centers
Planned building area at full build-outMore than 1 million sq ft (planned)2026-10-03announced From a public announcement. Plans can change.Vantage Data Centers
Number of data center buildings planned52026-10-03announced From a public announcement. Plans can change.Vantage Data Centers
AZ11, first building, IT capacity16MW2021-11-23company-reported From the company's own published information.Vantage Data Centers
AZ12 and AZ13 IT capacityAZ12: 16 MW; AZ13: 32 MW2026-10-03company-reported From the company's own published information.Corgan
AZ14 IT capacity64 MW2026-10-03company-reported From the company's own published information.Corgan
AZ14 building size and parcel451,000 sq ft on a 14-acre plot2024-11-25announced From a public announcement. Plans can change.DCD (DatacenterDynamics)
AZ15 planned IT capacity48 MW (planned, conceptual design)2026-10-03announced From a public announcement. Plans can change.Corgan
Campus statusAZ14 became operational in 2025 per the project architect; AZ15 is in conceptual design2026-10-03company-reported From the company's own published information.Corgan
Power supplyServed by APS through a dedicated onsite substation, receiving power at 69+ kV2026-10-03company-reported From the company's own published information.Vantage Data Centers
Green building certificationAZ11 and AZ12 certified Green Globes for New Construction (Green Building Initiative)2026-10-03company-reported From the company's own published information.Vantage Data Centers
Tenant arrangementA single AAA-rated tenant leases the first three buildings under six 15-year leases2025-06-24verifiedBisnow
Tenant pre-lease and option on further buildingsSame tenant pre-leased a 64 MW building then under construction and holds an option on a planned 48 MW building2025-06-24announced From a public announcement. Plans can change.Bisnow
Refinancing loan secured by three Goodyear buildings$735 million2025-06-27verifiedDCD (DatacenterDynamics)
AZ13 liquid cooling readinessProject architect states AZ13 is set to use liquid cooling2026-10-03company-reported From the company's own published information.Corgan
AZ14 rezoning requestRezoning of 14 acres at Bullard Avenue and Van Buren Street from General Commercial to Light Industrial requested for AZ142023-12-15verifiedAZBEX
Planned water use for coolingClosed-loop chilled water with air-cooled chillers and air-side economizers; planned WUE near zero2026-10-03company-reported From the company's own published information.Vantage Data Centers
Claimed ongoing cooling water useCompany states the cooling system uses no ongoing water2021-11-23company-reported From the company's own published information.Vantage Data Centers

Vantage Data Centers Glendale land (Camelback 303), Arizona

MeasureValueAs ofBasisSource
AddressSoutheast corner of Bethany Home Road and Cotton Lane, Glendale, AZ2026-10-28verifiedCity of Glendale
Glendale land purchase, 2023$50 million for nearly 34 acres2023-03-01verifiedDCD (DatacenterDynamics)
Glendale land purchase, December 2025$58.5 million for 70 adjacent acres2026-10-28verifiedRose Law Group Reporter (Phoenix Business Journal)
Site work permitsGrading and drainage permits issued September 2025 and May 20262026-10-28verifiedCity of Glendale
Glendale site statusLand held; no announced data center plans as of June 20252025-06-27verifiedDCD (DatacenterDynamics)

Investment

MeasureValueAs ofBasisSource
Development credit facility for North America (company-wide)$2 billion2026-09-14verifiedVantage Data Centers
Equity investment led by DigitalBridge and Silver Lake (worldwide)$9.2 billion2024-06-01verifiedVantage Data Centers

Production

MeasureValueAs ofBasisSource
What Vantage doesGlobal provider of digital infrastructure (data centers) serving AI and cloud companies2026-09-14company-reported From the company's own published information.Vantage Data Centers

Water and environment

MeasureValueAs ofBasisSource
Colorado River Basin water commitment (group pledge)Joined a group of organizations committing $32 million to the Colorado River Basin Collaborative2026-09-22announced From a public announcement. Plans can change.Vantage Data Centers

Other

MeasureValueAs ofBasisSource
Vantage Data Centers launchedJune 20102010-06-01company-reported From the company's own published information.Vantage Data Centers
Phoenix market entry announced with Goodyear land purchaseJanuary 20192019-01-08verifiedVantage Data Centers
First Goodyear data center topped outNovember 20212021-11-23verifiedVantage Data Centers
Phase two construction began in GoodyearOctober 20222022-10-18verifiedVantage Data Centers
AZ14 topped outNovember 20242024-11-25verifiedDCD (DatacenterDynamics)
AZ14 became operational20252026-10-03company-reported From the company's own published information.Corgan
HeadquartersDenver, Colorado2026-09-14company-reported From the company's own published information.Vantage Data Centers
Tie to Intel (California, not Arizona)Vantage's first data center (2010) was a former Intel facility in Santa Clara, California2010-06-01verifiedVantage Data Centers

Sources

Vantage Data Centers Jobs in Arizona (18 open)

Arizona AI currently tracks 18 open Vantage Data Centers roles in Arizona, the largest named category being business & corporate (3). Counts come from the Arizona AI job index, aggregated from the employer's own careers system and refreshed twice daily; they reflect published listings, not total employment.

Most current listings at Vantage Data Centers in Arizona advertise $157,500 to $167,500 a year, with a midpoint of $162,500. Across every listing the full span runs $83,200 to $265,000. Medians across 6 of 18 listings with employer-published pay.

Vantage Data Centers Business & Corporate Jobs in Arizona (3)

Vantage Data Centers Facilities, Construction & Utilities Jobs in Arizona (2)

Vantage Data Centers Hardware & Design Engineering Jobs in Arizona (2)

Vantage Data Centers IT, Security & Networking Jobs in Arizona (2)

Vantage Data Centers Software, Data & AI Jobs in Arizona (2)

Vantage Data Centers Other Roles Jobs in Arizona (7)

Vantage Data Centers in Arizona: Key Developments

No coverage of Vantage Data Centers in Arizona has been picked up yet. Browse all Arizona AI news.

Vantage Data Centers in Arizona: Common Questions

How many jobs does Vantage Data Centers have open in Arizona right now?

Arizona AI is currently tracking 18 open Vantage Data Centers roles in Arizona, in Phoenix. The count updates automatically as Vantage Data Centers adds and removes postings, and duplicate listings for the same role are merged.

What does Vantage Data Centers pay in Arizona?

Most current postings at Vantage Data Centers in Arizona advertise $157,500 to $167,500 a year, with a midpoint of $162,500; across all listings the full span runs $83,200 to $265,000. These are ranges Vantage Data Centers publishes on its own job postings, not estimates or self-reported figures, drawn from 6 of 18 current listings. An individual posting's range may span several job levels.

What kinds of roles does Vantage Data Centers hire for in Arizona?

The largest categories among current listings at Vantage Data Centers in Arizona are business & corporate (3), facilities, construction & utilities (2), hardware & design engineering (2), it, security & networking (2). Categories are derived from job titles by Arizona AI.

Where in Arizona are Vantage Data Centers jobs located?

Vantage Data Centers lists Arizona roles in Phoenix. Locations are shown exactly as Vantage Data Centers publishes them; the company's main Arizona site is Goodyear, AZ. Employers sometimes label roles with the metropolitan area rather than the specific campus city.

How do I apply for a job at Vantage Data Centers in Arizona?

Each listing on this page links through to Vantage Data Centers' own application page. Arizona AI does not collect applications or charge job seekers, and roles are aggregated from the employer's official careers system rather than from third-party recruiters.

What does Vantage Data Centers do?

Vantage builds data center campuses and offers wholesale data center space. It describes itself as a global provider of digital infrastructure serving AI and cloud innovators, and it said its Arizona campus would serve hyperscale and cloud providers as well as technology, e-commerce and enterprise companies.

Where is the Vantage data center in Arizona?

Vantage's AZ1 campus is at 45 S Bullard Avenue in Goodyear, just outside Phoenix. Vantage also acquired nearly 34 acres in Glendale in 2023, according to DatacenterDynamics, but had not announced plans for that site as of June 2025. In December 2025 it bought about 70 adjacent acres, according to the Phoenix Business Journal.

When did Vantage Data Centers come to Arizona?

Vantage announced in January 2019 that it had acquired 50 acres in the Greater Phoenix area for a data center campus. It topped out its first Goodyear building in November 2021 and began phase two construction in October 2022.

How big is the Vantage Goodyear data center campus?

Vantage says the campus will offer 176MW of IT capacity and more than one million square feet across five data centers once fully developed. That is the planned total. The first three buildings offer a combined 64 megawatts, according to a Fitch Ratings report described by Bisnow; Corgan, the campus architect, says a fourth building of 64 MW became operational in 2025, and its project page, as of October 2026, says a fifth, planned at 48 MW, is in conceptual design. City of Goodyear permit records show a building permit issued for that 48 MW building, filed in June 2025.

Does the Vantage Goodyear data center run AI?

Vantage says it serves AI and cloud innovators, but no source found names an AI customer or AI workloads at the Goodyear campus. Corgan is the campus architect. Corgan says one building is set to use liquid cooling and another includes high-density racks, and Vantage says the campus supports high-density applications.

Who is the tenant at Vantage Goodyear?

A Fitch Ratings report described by Bisnow says a single AAA-rated tenant leases the first three buildings through six separate 15-year leases and had preleased the 64 MW building then under construction, with an option on the planned 48-megawatt building. Corgan says that 64 MW building became operational in 2025; no update on the option after June 2025 was found.

How much is Vantage investing in Arizona?

In October 2022 Vantage said it was investing more than $1.5 billion in the Goodyear project, and no later update to that figure was found. In June 2025 it secured a $735 million refinancing loan backed by its Phoenix-area data centers; that loan refinanced existing debt rather than adding new investment.

How many people does Vantage Data Centers employ in Arizona?

Vantage does not publish an Arizona employee count. In 2022 it said the Goodyear project was expected to create approximately 3,000 construction and technology jobs, which is a projection and not a headcount; no later jobs figure was found.

Where does the Vantage Goodyear campus get its power and water?

Vantage says Arizona Public Service powers the campus through a dedicated onsite substation. It says the buildings use a closed-loop chilled water system that needs no ongoing water for cooling, a design claim; no metered water use figure was found.