Iron Mountain AZP-2 is an operating Iron Mountain data center at 4802 E Van Buren St in Phoenix, on the company's 39-acre Phoenix campus. Iron Mountain's quarterly reports filed with the SEC list 46.5 MW in operation there, all leased, since March 31, 2024.
Operating data center in 4802 E Van Buren St, Phoenix. Operated by Iron Mountain.

Outlined in yellow: Parcel 125-08-002C, named in Phoenix permit BLD 26004581 for Iron Mountain AZP-2 at 4802 E Van Buren St. It shows the land, not where buildings would go. Parcels: City of Phoenix, Permit BLD 26004581, Iron Mountain AZP-2, parcel 125-08-002C. Shapes: Maricopa County Assessor (read November 8, 2026).
Capacity: Figure reported in the press: computing (IT) load. Iron Mountain figure reported in December 2022.
Per-facility headcount is not published here: no reliable public figures exist for these sites, and construction announcements are not permanent employment. Open Arizona roles at this operator, where there are any, are listed on the operator's company page.
Compiled from public records and checked on 2026-10-07. Confidence in this record: high. Blank figures mean the number is not publicly established, not that it is zero.
Each statement on this page is listed with the page it came from and the words that say it. Sources open in a new tab.
Status: Operating
Our 39-acre Phoenix campus contains our AZP-1, AZP-2 and AZP-3 data centers which offer a combined 125 MW
It said yesterday it had completed phase one of the latest building, having equipped it with a 4MW power capacity.
4802 East Van Buren Street Phoenix Operational Fully operational facility
Capacity: 48 MW
Note: A 2019 report gave 48 MW as the figure upon completion.
existing 39-acre campus that houses their AZP1 (41 megawatt) and AZP2 (48 megawatt) data centers.
Upon completion, it will be three stories high, and will have a capacity to deliver 48MW of power to servers across 530,000 square feet (49,200 sq m) of floor space.
Floor area: 530,000 sq ft
Note: A 2019 report gave this as the floor space upon completion.
Upon completion, it will be three stories high, and will have a capacity to deliver 48MW of power to servers across 530,000 square feet (49,200 sq m) of floor space.
Online since: 2019
It said yesterday it had completed phase one of the latest building, having equipped it with a 4MW power capacity.
4802 East Van Buren, Phoenix, Arizona [...] 2019 [...] (3)Date of construction or acquired represents the date we constructed the facility or acquired the facility through purchase or acquisition.
Location: 4802 E Van Buren St, Phoenix
4802 East Van Buren, Phoenix, Arizona [...] 2019
4802 East Van Buren Street Phoenix Operational Fully operational facility
Opened its first 4 MW phase in August 2019, planned for 48 MW of power to servers and about 530,000 sq ft when complete.
It said yesterday it had completed phase one of the latest building, having equipped it with a 4MW power capacity.
Upon completion, it will be three stories high, and will have a capacity to deliver 48MW of power to servers across 530,000 square feet (49,200 sq m) of floor space.
Iron Mountain lists it among the data centers on its Phoenix campus.
Our 39-acre Phoenix campus contains our AZP-1, AZP-2 and AZP-3 data centers
Iron Mountain said in September 2020 that AZP-2 is powered by 100 percent renewable energy and would deliver 48 MW of IT capacity at full build-out.
AZP-2 is a hyperscale-ready data center powered by 100 percent renewable energy. [...] the three-story purpose-built facility will span more than 530KSF and deliver 48MW of total IT capacity at full build out
Iron Mountain describes AZP-2 as North America's first BREEAM design certified data center.
AZP-2 also holds the distinction of being North America's first-ever BREEAM design certified data center, with AZP-3 built to the same BREEAM standards.
Iron Mountain's quarterly reports filed with the SEC list 46.5 MW in operation at AZP-2, all leased, since March 31, 2024.
Data Center Operating Portfolio Stabilized Pre-Stabilized Total Leaseable MW Leased % by MW Leaseable MW Leased % by MW Leaseable MW Leased % by MW [...] AZP-2 46.5 100.0% — — 46.5 100.0%
Data Center Operating Portfolio Stabilized Pre-Stabilized Total Leaseable MW Leased % by MW Leaseable MW Leased % by MW Leaseable MW Leased % by MW [...] AZP-2 46.5 100.0% — — 46.5 100.0%
Lifecycle status Actual Partially operational Source Capacity basis Actual 46.5 MW is the Q2 2026 SEC-reported leaseable operating capacity.
Iron Mountain's quarterly reports filed with the SEC list 34.5 MW in operation at AZP-2, all leased, at March 31, 2023, and 40.5 MW, all leased, at December 31, 2023.
Data Center Operating Portfolio Stabilized Pre-Stabilized Total Leaseable MW Leased % by MW Leaseable MW Leased % by MW Leaseable MW Leased % by MW [...] AZP-2 34.5 100.0% — — 34.5 100.0%
Data Center Operating Portfolio Stabilized Pre-Stabilized Total Leaseable MW Leased % by MW Leaseable MW Leased % by MW Leaseable MW Leased % by MW [...] AZP-2 40.5 100.0% — — 40.5 100.0%