Microsoft PHX-72 is a data center building at 3785 N Citrus Rd in Goodyear. City of Goodyear records read November 12, 2026 show TCO (temporary certificate of occupancy) status for its shell, admin area and two of five data halls, with the other three halls at Permit Issued.
Operating data center in 3785 N Citrus Rd, Goodyear. Operated by Microsoft.
The short version
Is PHX-72 open?
Listing sites disagree: Baxtel shows PHX-72 under construction, while Cleanview's PHX-72 page said in October 2026 that it became operational in 2026.
Its temporary certificates of occupancy cover the shell, admin area and first two data halls.
City of Goodyear permit statuses read November 12, 2026 show the shell, admin area, COLO 1 and COLO 2 at TCO, a temporary certificate of occupancy, and the COLO 3, COLO 4 and COLO 5 fit-out permits at Permit Issued.
An application opened November 6, 2026 to place three new temporary construction trailers on the existing jobsite was in prescreen review on November 12, 2026.
What do the newest PHX-72 permits cover?
An electrical permit for UPS battery rooms (B25-02559), opened November 4, 2025 with an estimated valuation of $8,800,000 and listed as Permit Issued, says PHX72 was permitted with five internal electrical rooms, one per data hall, holding lithium-ion batteries for uninterruptible power supply.
The Arizona Department of Environmental Quality issued stormwater construction general permit coverage for more than 5 acres for "PHX72 - MICROSOFT CAMPUS" on August 29, 2025.
The shell permit (B23-02617) was opened June 21, 2023, and the six fit-out permits on August 9, 2023.
Where does each Citrus Road building stand?
For PHX70, City of Goodyear permit statuses read November 12, 2026 list the shell and all five fit-out permits as CO or Final Inspection.
PHX71 shows TCO, a temporary certificate of occupancy, on its shell and fit-outs, while PHX72 itself shows TCO only on its shell, admin area, COLO 1 and COLO 2.
PHX73's shell and fit-out permits, opened in April 2026, show Permit Issued, while PHX74's shell and fit-out applications have not been issued.
Capacity: Estimate from a data center listing site. Cleanview project map, read October 7, 2026. By November 2026 Cleanview no longer showed building figures publicly, and no other public source gives one for this building. The listing does not say what the figure measures.
Per-facility headcount is not published here: no reliable public figures exist for these sites, and construction announcements are not permanent employment. Open Arizona roles at this operator, where there are any, are listed on the operator's company page.
Rest of Microsoft Goodyear campus (PHX-70 to PHX-74)
Microsoft PHX-70 Microsoft · 3785 N Citrus Rd, Goodyear · Operating · 57 MW
Microsoft PHX-71 Microsoft · 3785 N Citrus Rd, Goodyear · Operating · 57 MW
Microsoft PHX-73 Microsoft · 3785 N Citrus Rd, Goodyear · Building permit issued · 57 MW
Microsoft PHX-74 Microsoft · 3785 N Citrus Rd, Goodyear · Proposed · 57 MW
Microsoft PHX-10 Microsoft · 14250 W Broadway Rd, Goodyear · Operating · 57 MW · 244,666 sq ft
Microsoft PHX-11 Microsoft · 14250 W Broadway Rd, Goodyear · Operating · 57 MW · 242,678 sq ft
Microsoft PHX-12 Microsoft · 14250 W Broadway Rd, Goodyear · Operating · 57 MW · 250,000 sq ft
Microsoft PHX-13 Microsoft · 14250 W Broadway Rd, Goodyear · Operating · 57 MW
Microsoft PHX-14 Microsoft · 14250 W Broadway Rd, Goodyear · Operating · 57 MW
Microsoft PHX-15 Microsoft · 14250 W Broadway Rd, Goodyear · Under construction · 57 MW
Microsoft PHX-16 Microsoft · 14250 W Broadway Rd, Goodyear · Under construction · 48 MW
Microsoft PHX-80 Microsoft · 12901 W Olive Ave, El Mirage · Operating · 57 MW · 245,000 sq ft
Microsoft PHX-81 Microsoft · 12901 W Olive Ave, El Mirage · Operating · 57 MW · 245,000 sq ft
Microsoft PHX-82 Microsoft · 12901 W Olive Ave, El Mirage · Under construction · 57 MW · 245,000 sq ft
Microsoft PHX-83 Microsoft · 12901 W Olive Ave, El Mirage · Under construction · 57 MW · 245,540 sq ft
News
Stories in Arizona AI's news feed that name this facility, newest first.
Jun 11, 2026 Microsoft purchases 100 acres next to existing data center campus in Goodyear, Arizona Microsoft paid $131 million to First Industrial Realty Trust for 100 acres near Citrus and Indian School roads, next to its 150-acre Goodyear campus under development, bringing its Arizona holdings to more than 550 acres by Data Center Dynamics' count.
Mar 2, 2024 Microsoft Is Draining Arizona's Water for its AI Summarizing The Atlantic, the report said Microsoft's own estimate put the three-building Goodyear campus at about 56 million gallons a year and that Microsoft had redacted exact water figures in city records as proprietary.
Mar 16, 2023 Microsoft to swap water for air cooling at campus in Phoenix, Arizona City documents showed the Goodyear campus was capped at 500,000 gallons of industrial discharge a day, that Microsoft had abandoned its water-reuse plan, and that dissolved solids were near the agreed limit.
Sep 21, 2020 Microsoft's newest sustainable datacenter region coming to Arizona in 2021 Microsoft named the Arizona region West US 3, said it would open in 2021 with Availability Zones, and described groundwater storage credits dedicated to Goodyear and El Mirage as part of a new water-positive pledge.
Compiled from public records and checked on 2026-11-13. Confidence in this record: medium. Blank figures mean the number is not publicly established, not that it is zero.
Each statement on this page is listed with the page it came from and the words that say it. Sources open in a new tab.
Status: Operating
Note: Goodyear shows temporary certificates of occupancy on the shell, admin area and two of five data halls, with the other three halls at Permit Issued. Baxtel shows the building under construction. Neither source says how many halls are running.
City of Goodyear permit records read November 12, 2026 show the other Microsoft buildings at 3785 N Citrus Rd at these stages: PHX70 at CO or Final Inspection on its shell and five fit-out permits, PHX71 at TCO (temporary certificate of occupancy) on its shell and six fit-out permits, PHX73 at Permit Issued on its shell and six fit-out permits opened in April 2026, and PHX74 with its shell and six fit-out applications not issued.
City of Goodyear permit records read November 12, 2026 show the shell, admin area, COLO 1 and COLO 2 with the status TCO (temporary certificate of occupancy) and the COLO 3, COLO 4 and COLO 5 fit-out permits with the status Permit Issued.