Microsoft PHX-14 is a data center building at 14250 W Broadway Rd in Goodyear. Listing sites name it as running, and City of Goodyear records read November 12, 2026 show TCO (temporary certificate of occupancy) on its shell, admin area and COLO 1, with COLO 2 to COLO 5 at Permit Issued.
Operating data center in 14250 W Broadway Rd, Goodyear. Operated by Microsoft.
The short version
Is PHX-14 open?
Baxtel lists PHX-14 as operating and gives 2025 as the year it was built, and Cleanview listed it as operating in October 2026.
City of Goodyear records read November 12, 2026 show the shell permit (B23-00279, opened January 24, 2023) and the fit-outs for the administration area and COLO 1 at TCO, a temporary certificate of occupancy, while COLO 2 to COLO 5 still read Permit Issued.
The shell permit lists an estimated valuation of $46,143,356.
What did Goodyear agree on water and cooling?
ABC15 reported that the Goodyear City Council unanimously approved an updated Microsoft agreement on March 6, 2023, under which the company will pay $36 million for the estimated $90 million expansion of the city's 157th Avenue Wastewater Treatment Plant.
Where does each Broadway Road building stand?
City of Goodyear permit statuses read November 12, 2026 list PHX10's data center building permit as Completed and its COLO 2 to COLO 5 fit-outs as CO or Final Inspection, with one interior alteration record at TCO, a temporary certificate of occupancy.
PHX11's shell and all six fit-out permits show CO or Final Inspection, and PHX12's shell and six fit-out permits show TCO.
PHX13 shows TCO on its shell, admin area and COLO 1 to COLO 3 with COLO 4 and COLO 5 at Permit Issued, and PHX14 shows TCO on its shell, admin area and COLO 1 with COLO 2 to COLO 5 at Permit Issued.
PHX15 and PHX16 have shell permits with the status Permit Issued.
Capacity: Estimate from a data center listing site. Cleanview project map, read October 7, 2026. By November 2026 Cleanview no longer showed building figures publicly, and no other public source gives one for this building. The listing does not say what the figure measures.
Per-facility headcount is not published here: no reliable public figures exist for these sites, and construction announcements are not permanent employment. Open Arizona roles at this operator, where there are any, are listed on the operator's company page.
Rest of Microsoft Goodyear campus (PHX-10 to PHX-16)
Microsoft PHX-70 Microsoft · 3785 N Citrus Rd, Goodyear · Operating · 57 MW
Microsoft PHX-71 Microsoft · 3785 N Citrus Rd, Goodyear · Operating · 57 MW
Microsoft PHX-72 Microsoft · 3785 N Citrus Rd, Goodyear · Operating · 57 MW
Microsoft PHX-73 Microsoft · 3785 N Citrus Rd, Goodyear · Building permit issued · 57 MW
Microsoft PHX-74 Microsoft · 3785 N Citrus Rd, Goodyear · Proposed · 57 MW
Microsoft PHX-80 Microsoft · 12901 W Olive Ave, El Mirage · Operating · 57 MW · 245,000 sq ft
Microsoft PHX-81 Microsoft · 12901 W Olive Ave, El Mirage · Operating · 57 MW · 245,000 sq ft
Microsoft PHX-82 Microsoft · 12901 W Olive Ave, El Mirage · Under construction · 57 MW · 245,000 sq ft
Microsoft PHX-83 Microsoft · 12901 W Olive Ave, El Mirage · Under construction · 57 MW · 245,540 sq ft
News
Stories in Arizona AI's news feed that name this facility, newest first.
Jun 11, 2026 Microsoft purchases 100 acres next to existing data center campus in Goodyear, Arizona Microsoft paid $131 million to First Industrial Realty Trust for 100 acres near Citrus and Indian School roads, next to its 150-acre Goodyear campus under development, bringing its Arizona holdings to more than 550 acres by Data Center Dynamics' count.
Mar 2, 2024 Microsoft Is Draining Arizona's Water for its AI Summarizing The Atlantic, the report said Microsoft's own estimate put the three-building Goodyear campus at about 56 million gallons a year and that Microsoft had redacted exact water figures in city records as proprietary.
Mar 16, 2023 Microsoft to swap water for air cooling at campus in Phoenix, Arizona City documents showed the Goodyear campus was capped at 500,000 gallons of industrial discharge a day, that Microsoft had abandoned its water-reuse plan, and that dissolved solids were near the agreed limit.
Sep 21, 2020 Microsoft's newest sustainable datacenter region coming to Arizona in 2021 Microsoft named the Arizona region West US 3, said it would open in 2021 with Availability Zones, and described groundwater storage credits dedicated to Goodyear and El Mirage as part of a new water-positive pledge.
Compiled from public records and checked on 2026-11-13. Confidence in this record: medium. Blank figures mean the number is not publicly established, not that it is zero.
Each statement on this page is listed with the page it came from and the words that say it. Sources open in a new tab.
Status: Operating
Note: Only listing sites name this building as running.
Counted as operating under the rule for buildings whose operator has not announced an in-service date: Microsoft says it operates data centers in Goodyear, listing sites list this building as running, and no available source says otherwise.
City of Goodyear records read November 12, 2026 show the PHX14 administration area (B23-00280) and data hall COLO 1 (B23-00281) at TCO, while COLO 2 to 5 (B23-00282 to B23-00284 and B23-03363) still read Permit Issued.
City of Goodyear permit records read November 12, 2026 show the other Microsoft buildings at 14250 W Broadway Rd at these stages: PHX10 with its data center building permit Completed, its COLO 2 to COLO 5 fit-outs at CO or Final Inspection and one interior alteration record at TCO (temporary certificate of occupancy), PHX11 with its shell and six fit-out permits at CO or Final Inspection, PHX12 with its shell and six fit-out permits at TCO, PHX13 at TCO on its shell, admin area and COLO 1 to COLO 3 and at Permit Issued on COLO 4 and COLO 5, PHX15 with its shell permit at Permit Issued, and PHX16 with its shell permit at Permit Issued.