Microsoft PHX-83
Operated by Microsoft · El Mirage
This is a proposed or under-construction project. It is not operating capacity, and announced projects do sometimes change scope or fail to proceed.
- Capacity
- 57 MW
- Floor area
- 245,540 sq ft
- Expected
- 2027
Capacity: Estimate from a data center listing site. Cleanview project map, read October 7, 2026. The listing does not say what the figure measures.
Rest of Microsoft El Mirage campus
- Microsoft El Mirage CampusOperating
- Microsoft PHX-80Operating · 57 MW
- Microsoft PHX-81Operating · 57 MW
- Microsoft PHX-82Operating · 57 MW
Other Microsoft sites in Arizona
- Microsoft Goodyear Campus (PHX-10 to PHX-14)Operating
- Microsoft PHX-10Operating · 57 MW
- Microsoft PHX-11Operating · 57 MW
- Microsoft PHX-12Operating · 57 MW
- Microsoft PHX-13Operating · 57 MW
- Microsoft PHX-14Operating · 57 MW
- Microsoft PHX-15Proposed · 57 MW
- Microsoft PHX-16Proposed · 57 MW
- Microsoft PHX-70Operating · 57 MW
- Microsoft PHX-71Operating · 57 MW
- Microsoft PHX-72Operating · 57 MW
- Microsoft PHX-73Proposed · 57 MW
- Microsoft PHX-74Proposed · 57 MW
More Arizona data centers
How we know this
Compiled from public records and checked on 2026-10-07. Our confidence in this record is medium. Blank figures above mean the number is not publicly established, not that it is zero.
Each statement on this page is listed with the page it came from and the words that say it. Sources open in a new tab.
Status: Proposed
Note: One listing site says planned and another says under construction.
- [1] City of El Mirage, Staff Report SPA24-09-01 MS PHX83 (El Mirage City Council, December 3, 2024) (opens in a new tab) · December 3, 2024
Show quote
The Commission recommends approving the zoning application at the November 12, 2024, public meeting with a 4-0 vote.
- [2] Cleanview, Data Centers in Arizona - Project List & Locations (opens in a new tab) · read October 7, 2026
Show quote
Map record 3535: Microsoft PHX-83 | status Planned
- [1] City of El Mirage, Staff Report SPA24-09-01 MS PHX83 (El Mirage City Council, December 3, 2024) (opens in a new tab) · December 3, 2024
Capacity: 57 MW
Note: Only a listing site gives this figure.
- [2] Cleanview, Data Centers in Arizona - Project List & Locations (opens in a new tab) · read October 7, 2026
Show quote
Map record 3535: Microsoft PHX-83 | status Planned | capacityMw 57
- [2] Cleanview, Data Centers in Arizona - Project List & Locations (opens in a new tab) · read October 7, 2026
Floor area: 245,540 sq ft
- [1] City of El Mirage, Staff Report SPA24-09-01 MS PHX83 (El Mirage City Council, December 3, 2024) (opens in a new tab) · December 3, 2024
Show quote
The new PHX83 data center building will be approximately 245,540 square feet in total area and will be a single-story building.
- [1] City of El Mirage, Staff Report SPA24-09-01 MS PHX83 (El Mirage City Council, December 3, 2024) (opens in a new tab) · December 3, 2024
Expected: 2027
Note: A listing site gives 2027 as the year planned.
- [3] Baxtel, Microsoft: PHX83 Data Center (opens in a new tab) · read October 7, 2026
Show quote
Year Planned: 2027
- [3] Baxtel, Microsoft: PHX83 Data Center (opens in a new tab) · read October 7, 2026
Location: El Mirage
- [1] City of El Mirage, Staff Report SPA24-09-01 MS PHX83 (El Mirage City Council, December 3, 2024) (opens in a new tab) · December 3, 2024
Show quote
Microsoft PHX83 Stantec LLC / Microsoft Corporation 12901 W Olive Avenue, El Mirage AZ 85335
- [1] City of El Mirage, Staff Report SPA24-09-01 MS PHX83 (El Mirage City Council, December 3, 2024) (opens in a new tab) · December 3, 2024
An El Mirage commission recommended approving the zoning application in November 2024 for a building of about 245,500 sq ft.
- [1] City of El Mirage, Staff Report SPA24-09-01 MS PHX83 (El Mirage City Council, December 3, 2024) (opens in a new tab) · December 3, 2024
Show quotes
The Commission recommends approving the zoning application at the November 12, 2024, public meeting with a 4-0 vote.
The new PHX83 data center building will be approximately 245,540 square feet in total area and will be a single-story building.
- [1] City of El Mirage, Staff Report SPA24-09-01 MS PHX83 (El Mirage City Council, December 3, 2024) (opens in a new tab) · December 3, 2024
Operator site: https://datacenters.microsoft.com/
Something here wrong or out of date? Tell us.