Aligned Phoenix - Behrend Drive (PHX-08) is a planned Aligned data center on a former office campus at 3151 and 3202 W Behrend Dr in Phoenix. The City Council voted 7-1 on March 25, 2026 to grant Aligned a waiver from the city's new data center permit rules.
Proposed data center in 3151 and 3202 W Behrend Dr, Phoenix. Operated by Aligned.
The Phoenix City Council voted 7-1 on March 25, 2026 to grant Aligned a binding waiver of the city's data center special permit rules, as revised by a Law Department memo of that date. Under the waiver, Aligned must give the city a load commitment agreement with APS before a certificate of occupancy is issued for any data center building. The city issued permits in 2024 to demolish buildings on the site, and the listing site Baxtel lists 3202 W Behrend Dr as under construction. The Ahwatukee Foothills News reported in July 2026 that Aligned's attorney had sought to delay the vote, stating the waiver did not allow for the site to get electric service.

Outlined in yellow: the three parcels in Aligned's Behrend Drive data center waiver in Phoenix. It shows the land, not where buildings would go. Parcels: City of Phoenix, File 26-0487, Aligned Behrend waiver, parcels 206-12-206, 206-12-207 and 206-12-208B. Shapes: Maricopa County Assessor (read November 7, 2026).
Capacity: Estimate from a data center listing site. Cleanview project map, read October 7, 2026. The listing does not say what the figure measures.
Per-facility headcount is not published here: no reliable public figures exist for these sites, and construction announcements are not permanent employment. Open Arizona roles at this operator, where there are any, are listed on the operator's company page.
Compiled from public records and checked on 2026-11-13. Confidence in this record: medium. Blank figures mean the number is not publicly established, not that it is zero.
Each statement on this page is listed with the page it came from and the words that say it. Sources open in a new tab.
Status: Proposed
Note: A listing site shows 3202 W Behrend Dr as under construction.
At the City’s request, Aligned has submitted detailed information and committed to measures designed to mitigate the potential impacts of its proposed data center.
Map record 4334: Aligned Phoenix PHX-08 | status Planned | capacityMw 201.6
Capacity: 202 MW
Note: Only a listing site gives this figure, for a record it calls Aligned Phoenix PHX-08.
Map record 4334: Aligned Phoenix PHX-08 | status Planned | capacityMw 201.6
Location: 3151 and 3202 W Behrend Dr, Phoenix
Parcel Address: 3151 W. Behrend Drive,19640 N. 31st Avenue, and 3202 W. Behrend Drive, Phoenix, AZ 85027
The Phoenix City Council voted 7-1 on March 25, 2026 to grant Aligned a binding waiver of the city's data center special permit rules, as revised by a Law Department memo of that date.
Betty Guardado: Yes; Anna Hernandez: No; Kesha Hodge Washington: Yes; Laura Pastor: Yes; Kevin Robinson: Yes; Debra Stark: Absent; Jim Waring: Yes; Ann O'Brien: Yes; Kate Gallego: Yes
Authorization to Grant Aligned Data Centers (Behrend) Propco, LLC (Aligned) a Binding Waiver of Enforcement (Waiver) of the Special Permit Provisions for Data Centers (Ordinance S-52717) - District 1 This item was approved as revised per the memo from the Law Department dated March 25, 2026.
Under the waiver, Aligned must give the city a load commitment agreement with APS before a certificate of occupancy is issued for any data center building.
Prior to the issuance of a Certificate of Occupancy for any data center building or portion thereof, the Owner will provide the City a copy of a load commitment agreement with APS that confirms its capacity and commitment to serve such proposed data center use.
The city issued permits in 2024 to demolish buildings on the site, and the listing site Baxtel lists 3202 W Behrend Dr as under construction.
Permit # DEM 24008702 Issued 16-MAY-2024 [...] DESCRIPTION OF WORK: TOTAL DEMOLITION OF TRCW building and pedestrian bridge.
Permit # DEM 24013645 Issued 08-AUG-2024 [...] Permit Description ALIGNED PHX08-TRCN BLD DEMO
3202 W Behrend Dr Under Construction New facility under construction
The Ahwatukee Foothills News reported in July 2026 that Aligned's attorney had sought to delay the vote, stating the waiver did not allow for the site to get electric service.
Council last March approved a waiver that included some size, setback and landscaping requirements, though Aligned's attorney had sought to delay a vote, stating the waiver did not allow for the site to get electric service.
Phoenix City Council considered a binding waiver for Aligned's properties at 3151 and 3202 W. Behrend Drive and 19640 N. 31st Avenue, and a motion to approve it was made on March 25, 2026.
A motion was made by Councilwoman O'Brien, seconded by Vice Mayor Hodge Washington, that this item be approved as revised
that this item be approved as revised per the memo from the Law Department dated March 25, 2026.
Parcel Address: 3151 W. Behrend Drive,19640 N. 31st Avenue, and 3202 W. Behrend Drive, Phoenix, AZ 85027
A listing site calls 3202 W. Behrend Drive PHX-08 and lists it as under construction.
3202 W Behrend Dr Under Construction New facility under construction
Maricopa County Assessor records show Aligned Data Centers Behrend Propco LLC bought 3151 W Behrend Dr for $55 million and 3202 W Behrend Dr for $38 million in September 2022, and 19640 N 31st Ave for $15 million in December 2022.
The current owner is ALIGNED DATA CENTERS BEHREND PROPCO LLC [...] It was last sold on 09/01/2022 for $55,000,000.
The current owner is ALIGNED DATA CENTERS BEHREND PROPCO LLC [...] It was last sold on 09/01/2022 for $38,000,000.
The current owner is ALIGNED DATA CENTERS BEHREND PROPCO LLC [...] It was last sold on 12/01/2022 for $15,000,000.
The Real Deal reported that Aligned acquired the Deer Valley office park for $108 million in 2022 with plans to convert it into a data center campus.
The company had acquired a vacant Deer Valley office park near Interstate 17 and Loop 101 for $108 million in 2022 with plans to convert it into a data center campus.
The Ahwatukee Foothills News reported that Aligned bought two office buildings on the site for $93 million in 2022 with plans for a 513,361-square-foot data center and office space.
Aligned had purchased two office buildings on the site for $93 million in 2022 with plans for a 513,361-square-foot data center and office space.
City of Phoenix permits name the project Aligned Data Center PHX08, including its storm water management plan permit.
Permit Description ALIGNED DATA CENTER PHX08 / SWMP [...] DESCRIPTION OF WORK: Storm Water Management Plan for ALIGNED DATA CENTER PHX08 per approved plans.
Permit # DEM 24013645 Issued 08-AUG-2024 [...] Permit Description ALIGNED PHX08-TRCN BLD DEMO
The city issued permits in 2024 to demolish buildings on the site, including a total demolition of the TRCW building at 3202 W Behrend Dr.
Permit # DEM 24008702 Issued 16-MAY-2024 [...] DESCRIPTION OF WORK: TOTAL DEMOLITION OF TRCW building and pedestrian bridge.
Permit # DEM 24013645 Issued 08-AUG-2024 [...] Permit Description ALIGNED PHX08-TRCN BLD DEMO
The City of Phoenix adopted zoning rules on July 2, 2025 that require a data center to apply for a special permit for construction.
The Phoenix Mayor and City Council today approved updates to modernize the City's Zoning Ordinance to add data centers as a permitted use that must address health and safety concerns when applying for a special permit for construction.
On October 13, 2025, Aligned submitted a demand to the city for $75,435,397 in compensation under Proposition 207 for alleged impacts of those rules on the property.
On October 13, 2025, Owner submitted a demand for $75,435,397 of compensation under Proposition 207, for alleged impacts relating to the Data Center Regulations
On March 25, 2026 the City Council voted 7-1 to grant Aligned a binding waiver of the data center special permit rules, as revised by a Law Department memo of that date, with Anna Hernandez voting no and Debra Stark absent.
Betty Guardado: Yes; Anna Hernandez: No; Kesha Hodge Washington: Yes; Laura Pastor: Yes; Kevin Robinson: Yes; Debra Stark: Absent; Jim Waring: Yes; Ann O'Brien: Yes; Kate Gallego: Yes
Authorization to Grant Aligned Data Centers (Behrend) Propco, LLC (Aligned) a Binding Waiver of Enforcement (Waiver) of the Special Permit Provisions for Data Centers (Ordinance S-52717) - District 1 This item was approved as revised per the memo from the Law Department dated March 25, 2026.
The draft ordinance says the waiver resolves Aligned's claim that the rules lowered the property's value.
this Waiver issued under A.R.S. § 12-1134 resolves the claims asserting diminution in the fair market value of the property
The revised waiver bars nuclear power generation and permanent power generation other than emergency backup generators.
Nuclear power generation shall never be permitted on the Property. [...] Permanent power generation shall not be permitted on the Property, except for emergency backup generators. [...] Data center uses will not generate noise in excess of 55 dB(A) between 7:00 AM and 10:00 PM or 45 dB(A) between 10:00 PM and 7:00 AM
It limits data center noise to 55 dB(A) from 7 a.m. to 10 p.m. and 45 dB(A) at night, measured from the property line of the nearest residentially zoned property, and allows the limits to be adjusted to a level that does not exceed existing background noise if an updated noise study supports it.
Data center uses will not generate noise in excess of 55 dB(A) between 7:00 AM and 10:00 PM or 45 dB(A) between 10:00 PM and 7:00 AM [...] from the property line of the nearest residentially-zoned property [...] If supported by an updated noise study, the noise limits set forth above may be adjusted to a level that does not exceed the level of existing background noise.
Before a certificate of occupancy is issued for any data center building, Aligned must give the city a load commitment agreement with APS.
Prior to the issuance of a Certificate of Occupancy for any data center building or portion thereof, the Owner will provide the City a copy of a load commitment agreement with APS that confirms its capacity and commitment to serve such proposed data center use.
The Ahwatukee Foothills News reported in July 2026 that the waiver included some size, setback and landscaping requirements, and that Aligned's attorney had sought to delay the vote, stating the waiver did not allow for the site to get electric service.
Council last March approved a waiver that included some size, setback and landscaping requirements, though Aligned's attorney had sought to delay a vote, stating the waiver did not allow for the site to get electric service.
In July 2026, MGX, the Artificial Intelligence Infrastructure Partnership and BlackRock's Global Infrastructure Partners completed their purchase of Aligned Data Centers from funds managed by Macquarie Asset Management, at an enterprise value of about $40 billion.
MGX, the Artificial Intelligence Infrastructure Partnership (AIP), and BlackRock’s Global Infrastructure Partners (GIP), today successfully completed their previously announced acquisition of 100 per cent of the equity in Aligned Data Centers from private infrastructure funds managed by Macquarie Asset Management [...] Aligned’s enterprise value of approximately US$40 billion
has officially completed its acquisition of Aligned Data Centers from infrastructure funds managed by Macquarie Asset Management and its co-investors. The transaction values Aligned at an enterprise value of approximately US$ 40 billion
These remarks are Arizona AI's own. They say how this record is counted or what we could not find, so there is no outside page to link.
The city staff report on the waiver request (Legistar matter 26-0487) gives no size, capacity or opening date.