Aligned Phoenix PHX-01/02/03

Operated by Aligned · Phoenix

Capacity for one phase
62 MW
Floor area
550,000 sq ft
Land
55 acres
Online since
2017

Capacity: Operator's own figure: computing (IT) load, one phase. Aligned figure for the first phase when the building opened in 2017.

Working here

We do not publish per-facility headcount, because no reliable public figures exist for these sites and construction announcements are not permanent employment. What we can show is real: open Arizona roles at this operator, gathered from their own job board.

Rest of Aligned Union Hills campus

Other Aligned sites in Arizona

More Arizona data centers

See all Arizona data centers

How we know this

Compiled from public records and checked on 2026-10-07. Our confidence in this record is high. Blank figures above mean the number is not publicly established, not that it is zero.

Each statement on this page is listed with the page it came from and the words that say it. Sources open in a new tab.

  1. Status: Operating

    Note: The newest source showing it running is a December 2024 press tour.

  2. Capacity for one phase: 62 MW

    Note: Aligned gave this figure for the first phase when the building opened in 2017.

  3. Floor area: 550,000 sq ft

    Note: The source gives this as the size when the building opened in 2017.

  4. Land: 55 acres

    Note: This is the size of the whole campus, which also includes PHX-05.

  5. Online since: 2017

  6. Location: Phoenix

  7. A former DEC factory at 2500 W Union Hills Drive that Aligned converted and opened in May 2017, described as three buildings under one roof.

  8. Aligned gave 62 MW of IT power for the first phase and later said a second phase could hold 60 MW at full build-out, and press has said the campus has room for 180 MW.

Our own notes

These remarks are Arizona AI's own. They say how this record is counted or what we could not find, so there is no outside page to link.

We found no Aligned statement of how much of that is running today, so only the first-phase figure is shown.

Operator site: https://aligneddc.com/