Operating data center in 155 N Bullard Ave, Goodyear. Operated by Vantage Data Centers.

Outlined in yellow: Shared northern parcel named in Vantage AZ14 and AZ15 permits, APN 500-10-858A. It shows the land, not where buildings would go. Parcels: City of Goodyear, Permit B24-03650, Vantage AZ14, parcel 500-10-858A. Shapes: Maricopa County Assessor (read November 8, 2026).
Capacity: Figure from an official record. City of Goodyear permit B24-03650, read October 19, 2026. The source does not say what the figure measures.
Per-facility headcount is not published here: no reliable public figures exist for these sites, and construction announcements are not permanent employment. Open Arizona roles at this operator, where there are any, are listed on the operator's company page.
Compiled from public records and checked on 2026-10-19. Confidence in this record: medium. Blank figures mean the number is not publicly established, not that it is zero.
Each statement on this page is listed with the page it came from and the words that say it. Sources open in a new tab.
Status: Operating
Note: Only listing sites name this building as running. Press in February 2025 expected completion in summer 2026.
Vantage AZ14 Vantage Data Centers Operational
Map record 4115: Vantage AZ14 | status Operating
Capacity: 64 MW
in the 64MW 2-story building
Floor area: 225,600 sq ft
Note: A listing site table gives 225,600 without stating the unit.
Vantage AZ14 Vantage Data Centers Operational ░░░░ Request Dataset MW 225,600
Online since: 2025
Note: A listing site says it went into operation in 2025.
AZ14 facility went into operation at the AZ1 campus in 2025.
Location: 155 N Bullard Ave, Goodyear
155 N BULLARD AVE Goodyear AZ 85338
Topped out by February 2025 and expected to complete in summer 2026.
The team is simultaneously celebrating the topping out of AZ14 on the same campus, which is expected to complete in summer 2026.
Counted as operating under Arizona AI's rule for buildings whose operator has not announced an in-service date: construction press reports the first three buildings on the campus delivered, a listing site lists this building as running, and no source we found says otherwise.
AZ13 is the third of five planned data centers at Vantage's AZ1 campus in Goodyear
The first two, AZ11 and AZ12, were delivered in July 2023 and March 2024, respectively.
Vantage AZ14 Vantage Data Centers Operational
City of Goodyear permit B24-03650, for the interior fit-out of this 64 MW two-story building, is filed at 155 N Bullard Ave and has the record status TCO, for temporary certificate of occupancy.
VANTAGE AZ14 Fitup
This project proposes interior fit-out of data halls
in the 64MW 2-story building
Record Status: TCO
155 N BULLARD AVE Goodyear AZ 85338
Vantage gives 45 S Bullard Avenue for the whole campus.
45 S Bullard Avenue