Prime Data Centers PHX01 Building 1 is a building on Prime's PHX01 campus at 3700 S Avondale Blvd in Avondale. Prime lists it at 48 MW and 267,000 square feet, with the status Construction and the availability Leased.

Proposed data center in 3700 S Avondale Blvd, Avondale. Operated by Prime Data Centers.

Where it stands

City of Avondale records list the building permit record for PHX01-01, opened July 9, 2024, as Permit Issued when read on November 13, 2026. A later city permit was opened for night slab-on-grade concrete placement and finishing of about 600 cubic yards at PHX01-01 from August 11 to September 11, 2026. Prime's campus page lists PHX01-01 with the status Construction and the availability Leased.

This record describes part of a larger campus. Its capacity is counted once at campus level in the statewide totals, so it is not added again here.

The short version

Is it built yet?

  • City of Avondale records show a building permit record for PHX01-01 opened July 9, 2024, and a permit for night slab concrete placement of about 600 cubic yards from August 11 to September 11, 2026, listed as Project Complete when read on November 13, 2026.
  • Prime announced the groundbreaking on its first three buildings in a May 21, 2026 statement.

Who will use it and who is building it?

  • Prime said Buildings 1 through 3 have already been secured by a leading hyperscaler, and it lists PHX01-01 as Leased.
  • Prime's campus page lists PHX01-01 as a hyperscale building with 48MW of capacity.

Where it is

2023 aerial photo of the shared Prime PHX01 campus parcel, APN 500-66-005K, outlined in yellow.
Aerial photo flown September 17, 2023: USDA National Agriculture Imagery Program (NAIP); source: USGS, USDA, The National Map: Orthoimagery (public domain). Outline drawn by Arizona AI from Maricopa County Assessor parcel records.

Outlined in yellow: Shared Prime PHX01 campus parcel for Buildings 1 to 5. It shows the land, not where buildings would go. Parcels: City of Avondale, Engineering record ELAS-26-0005, Prime PHX01 five-building campus, parcel 500-66-005K. Shapes: Maricopa County Assessor (read November 8, 2026).

Open in Google Maps

  • Capacity: 48 MW
  • Floor area: 267,000 sq ft

Capacity: Figure reported in the press: computing (IT) load. Prime figure reported May 2026.

Timeline

  1. : Avondale opened a building permit record for PHX01-01 Prime Data Center under planning case PL-23-0023, listed as Permit Issued on November 13, 2026. Source: City of Avondale (Accela Citizen Access), Avondale permit search, Engineering tab with "Search All Records"
  2. : Avondale opened a permit for night slab concrete placement at PHX01-01 from August 11 to September 11, 2026. Source: City of Avondale (Accela Citizen Access), Avondale permit search, Engineering tab with "Search All Records"

Working here

Per-facility headcount is not published here: no reliable public figures exist for these sites, and construction announcements are not permanent employment. Open Arizona roles at this operator, where there are any, are listed on the operator's company page.

Rest of Prime Data Centers PHX01 campus

How we know this

Compiled from public records and checked on 2026-11-13. Confidence in this record: high. Blank figures mean the number is not publicly established, not that it is zero.

Each statement on this page is listed with the page it came from and the words that say it. Sources open in a new tab.

Our own notes

These remarks are Arizona AI's own. They say how this record is counted or what we could not find, so there is no outside page to link.

Counted once in the campus total.