Prime Data Centers PHX01 Building 1 is a building on Prime's PHX01 campus at 3700 S Avondale Blvd in Avondale. Prime lists it at 48 MW and 267,000 square feet, with the status Construction and the availability Leased.
Proposed data center in 3700 S Avondale Blvd, Avondale. Operated by Prime Data Centers.
City of Avondale records list the building permit record for PHX01-01, opened July 9, 2024, as Permit Issued when read on November 13, 2026. A later city permit was opened for night slab-on-grade concrete placement and finishing of about 600 cubic yards at PHX01-01 from August 11 to September 11, 2026. Prime's campus page lists PHX01-01 with the status Construction and the availability Leased.
This record describes part of a larger campus. Its capacity is counted once at campus level in the statewide totals, so it is not added again here.

Outlined in yellow: Shared Prime PHX01 campus parcel for Buildings 1 to 5. It shows the land, not where buildings would go. Parcels: City of Avondale, Engineering record ELAS-26-0005, Prime PHX01 five-building campus, parcel 500-66-005K. Shapes: Maricopa County Assessor (read November 8, 2026).
Capacity: Figure reported in the press: computing (IT) load. Prime figure reported May 2026.
Per-facility headcount is not published here: no reliable public figures exist for these sites, and construction announcements are not permanent employment. Open Arizona roles at this operator, where there are any, are listed on the operator's company page.
Compiled from public records and checked on 2026-11-13. Confidence in this record: high. Blank figures mean the number is not publicly established, not that it is zero.
Each statement on this page is listed with the page it came from and the words that say it. Sources open in a new tab.
Status: Under construction
Note: The source is a May 2026 report that Prime broke ground on the first three buildings.
Prime Data Centers broke ground on the first three buildings of its PHX01 campus in Avondale
Capacity: 48 MW
Note: This is the planned IT load Prime gave for each of the first three buildings.
The company said each of the first three buildings will deliver 48MW of critical IT load, for a combined 144MW in the opening phase.
Floor area: 267,000 sq ft
The first three buildings are listed at 267,000 square feet and 48MW each.
Location: 3700 S Avondale Blvd, Avondale
The campus is being developed on a 66.5-acre site at 3700 S. Avondale Boulevard in Phoenix
Prime Data Centers broke ground on the first three buildings of its PHX01 campus in Avondale
City of Avondale records list the building permit record for PHX01-01, opened July 9, 2024, as Permit Issued when read on November 13, 2026.
PHX01-01 Prime Data Center (PL-23-0023)
A later city permit was opened for night slab-on-grade concrete placement and finishing of about 600 cubic yards at PHX01-01 from August 11 to September 11, 2026.
PHX01-01 Prime Data Center 12:01AM to 6:00AM from August 11 2026 to September 11 2026 Slab on grade concrete placement and finishing operations, aprox 600 cubic yards
Prime's campus page lists PHX01-01 with the status Construction and the availability Leased.
PHX01-01 Name PHX01-01 Type Hyperscale Use Single or multi-tenant Status Construction Availability Leased Capacity 48MW Size 267,000 sq ft
Prime said in May 2026 that it had broken ground on this building and that it was already secured by a leading hyperscaler.
Prime Data Centers broke ground on the first three buildings of its PHX01 campus in Avondale
Prime also said Buildings 1 through 3 have already been secured by a leading hyperscaler
The start marks the opening phase of a $3 billion planned investment, the company said in a May 21, 2026, statement
Prime's campus page lists PHX01-01 with the status Construction and the availability Leased, at 48 MW and 267,000 square feet.
PHX01-01 Name PHX01-01 Type Hyperscale Use Single or multi-tenant Status Construction Availability Leased Capacity 48MW Size 267,000 sq ft
These remarks are Arizona AI's own. They say how this record is counted or what we could not find, so there is no outside page to link.
Counted once in the campus total.