Meta Mesa Building 5 is one of five buildings on Meta's data center campus at 3841 S Ellsworth Road in Mesa. A listing site reported that two of the five were online, and Meta has not said which buildings run.
Proposed data center in 3841 S Ellsworth Rd, Mesa. Operated by Meta.
Mesa's May 20, 2024 sitework permit for three new data center buildings on the campus uses the label Building 5, but it does not say that its label matches the Building 5 name that listing sites use. Data Center Map reported that two of the five campus buildings were online, and Meta has not said which buildings are running.
Capacity: Estimate from a data center listing site. Cleanview project map, read October 7, 2026. No operator or government source on this page gives a capacity for this building. The listing does not say what the figure measures.
Per-facility headcount is not published here: no reliable public figures exist for these sites, and construction announcements are not permanent employment. Open Arizona roles at this operator, where there are any, are listed on the operator's company page.
Compiled from public records and checked on 2026-11-13. Confidence in this record: medium. Blank figures mean the number is not publicly established, not that it is zero.
Each statement on this page is listed with the page it came from and the words that say it. Sources open in a new tab.
Status: Proposed
Note: Other listing sites show this building as operating. Meta has not said which buildings run.
Mesa, Arizona Data Center Campus went operational, with two out of five buildings now online
Capacity: 48 MW
Note: A listing site gave 48 MW for this building and the other four. The county air permit for the address covers backup generators: 21 large engines, about 69 MW in all when converted from brake horsepower. Backup power is not computing load, and the sources include no capacity published by Meta.
Map record 3104: Meta Mesa - Building 5 | status Operating | capacityMw 48
Location: 3841 S Ellsworth Rd, Mesa
for the development of approximately 396 acres of property generally located at the southeast corner of Elliot and Ellsworth Roads
Meta acquired 396 acres in Mesa on the southeast corner of Elliot and Ellsworth Roads for $123.2 million
REDALE LLC; 3841 S ELLSWORTH RD MESA 85212
Mesa's May 20, 2024 sitework permit for three new data center buildings on the campus uses the label Building 5, but it does not say that its label matches the Building 5 name that listing sites use.
"issued_date":"2024-05-20T00:00:00.000" [...] "contractor_name":"DPR CONSTRUCTION" [...] Sitework for three new data center buildings and associated administration buildings within the existing data center campus in Mesa, AZ. These buildings are referred to as Buildings 5, 6 and 3F.
Map record 3104: Meta Mesa - Building 5 | status Operating | capacityMw 48
Map record 3104: Meta Mesa - Building 5 | status Operating
Data Center Map reported that two of the five campus buildings were online, and Meta has not said which buildings are running.
Mesa, Arizona Data Center Campus went operational, with two out of five buildings now online
Meta is excited to announce that the Mesa Data Center is now serving traffic.
A listing site reported on January 29, 2025 that two of the five buildings on Meta's Mesa campus were online.
Mesa, Arizona Data Center Campus went operational, with two out of five buildings now online
Maricopa County's air permit for the site address, 3841 S Ellsworth Road, as revised in August 2023, covers 21 large emergency generators of 4,376 brake horsepower each, about 69 MW of engine power in all when converted from brake horsepower, and gives no computing load for this building.
the application for a permit revision has been approved and will be incorporated into your air quality permit. [...] Caterpillar C175-16 4,376 Tier 2 [...] Emergency Generators (21 total)
Redale has submitted a non-minor modification to expand the data center to include an additional 13 emergency generators. The total number of units at the facility after this expansion will be 22 emergency engines and 1 fire pump.
Construction Dive reported in December 2023 that DPR Construction expects to complete Meta's five-building Mesa campus in 2026.
is a greenfield development of a five-building campus encompassing over 2.5 million square feet of data center and admin space. The campus, which DPR expects to complete in 2026, will use 12,000 tons of steel
A City of Mesa permit for sitework on three more data center buildings on Meta's campus calls them Buildings 5, 6 and 3F, and the permit does not say how those labels match the Building 3, 4 and 5 names, which come from a listing site.
"description":"Sitework for three new data center buildings and associated administration buildings within the existing data center campus in Mesa, AZ. These buildings are referred to as Buildings 5, 6 and 3F.
These remarks are Arizona AI's own. They say how this record is counted or what we could not find, so there is no outside page to link.
This building is one of the three not yet confirmed online, so it stays with the announced projects until Meta or an official record confirms it.